Sec. 636.112  May stipends be used?

    At your discretion, you may elect to pay a stipend to unsuccessful 
offerors who have submitted responsive proposals. The decision to do so 
should be based on your analysis of the estimated proposal development 
costs and the anticipated degree of competition during the procurement 
process.