                           TITLE 23--HIGHWAYS
 
 CHAPTER I--FEDERAL HIGHWAY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
 
PART 636_DESIGN-BUILD CONTRACTING--Table of Contents
 
             Subpart B_Selection Procedures, Award Criteria
 
Sec. 636.209  What items must be included in a phase-two solicitation?

    (a) You must include the requirements for technical proposals and 
price proposals in the phase-two solicitation. All factors and 
significant subfactors that will affect contract award and their 
relative importance must be stated clearly in the solicitation. Use your 
own procedures for the solicitation as long as it complies the 
requirements of this part.
    (b) At your discretion, you may allow proposers to submit alternate 
technical

[[Page 193]]

concepts in their proposals as long as these alternate concepts do not 
conflict with criteria agreed upon in the environmental decision making 
process. Alternate technical concept proposals may supplement, but not 
substitute for base proposals that respond to the RFP requirements.