Sec. 771.113  Timing of Administration activities.

    (a) The Administration in cooperation with the applicant will 
perform the work necessary to complete a

[[Page 384]]

FONSI or an EIS and comply with other related environmental laws and 
regulations to the maximum extent possible during the NEPA process. This 
work includes environmental studies, related engineering studies, agency 
coordination and public involvement. However, final design activities, 
property acquisition (with the exception of hardship and protective 
buying, as defined in Sec. 771.117(d)), purchase of construction 
materials or rolling stock, or project construction shall not proceed 
until the following have been completed:
    (1)(i) The action has been classified as a categorical exclusion 
(CE), or
    (ii) A FONSI has been approved, or
    (iii) A final EIS has been approved and available for the prescribed 
period of time and a record of decision has been signed;
    (2) For actions proposed for FHWA funding, the FHWA Division 
Administrator has received and accepted the certifications and any 
required public hearing transcripts required by 23 U.S.C. 128;
    (3) For activities proposed for FHWA funding, the programming 
requirements of 23 CFR part 450, subpart B, and 23 CFR part 630, subpart 
A, have been met.
    (b) For FHWA, the completion of the requirements set forth in 
paragraphs (a)(1) and (2) of this section is considered acceptance of 
the general project location and concepts described in the environmental 
document unless otherwise specified by the approving official. However, 
such approval does not commit the Administration to approve any future 
grant request to fund the preferred alternative.
    (c) Letters of Intent issued under the authority of section 3(a)(4) 
of the UMT Act are used by UMTA to indicate an intention to obligate 
future funds for multi-year capital transit projects. Letters of Intent 
will not be issued by UMTA until the NEPA process is completed.

[52 FR 32660, Aug. 28, 1987; 53 FR 11066, Apr. 5, 1988]