[Code of Federal Regulations]
[Title 24, Volume 3]
[Revised as of April 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 24CFR511.75]

[Page 24-26]
 
                 TITLE 24--HOUSING AND URBAN DEVELOPMENT
 
  CHAPTER V--OFFICE OF ASSISTANT SECRETARY FOR COMMUNITY PLANNING AND 
        DEVELOPMENT, DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT
 
PART 511_RENTAL REHABILITATON GRANT PROGRAM--Table of Contents
 
                     Subpart H_Grant Administration
 
Sec. 511.75  Disbursement of rental rehabilitation grant amounts: 
Cash and Management Information System.

    (a) General. Rental Rehabilitation grants are managed through HUD's 
C/MI System for the Rental Rehabilitation Program. The C/MI System is a 
computerized system which manages program funds, disburses grant 
amounts, and collects and reports data on properties and tenants 
assisted under the Program.
    (b) Project set-up. (1) After the grantee executes the Grant 
Agreement, complies with the requirements under part

[[Page 25]]

58 of this title for release of funds, and submits the appropriate 
security documents, the grantee may identify (set-up) specific local 
projects in the C/MI System. State recipients are also granted access to 
the C/MI System for projects upon designation by the State and 
submission of the appropriate security documents. Within 12 calendar 
days of project set-up, grantees and State recipients are required to 
submit a Pre-Rehabilitation Report to HUD for each project set-up in the 
C/MI System. Until an acceptable Pre-Rehabilitation Report is received 
and entered in the C/MI System, grant amounts for the project are not 
considered ``committed,'' as defined in Sec. 511.2, and, therefore, are 
subject to deobligation to the extent authorized by 24 CFR 511.33(c).
    (2) Beginning in Fiscal Year 1991, if Pre-Rehabilitation Reports are 
not received within 20 days of the project set-up call, the project will 
be cancelled automatically by the C/MI System. In addition, projects 
which have been committed in the C/MI System for 6 months without an 
initial disbursement of funds will be automatically cancelled by the C/
MI System.
    (c) Disbursement of rental rehabilitation grant amounts. After an 
acceptable Pre-Rehabilitation Report is entered into the C/MI System, 
obligated grant amounts may be drawn down for the project by the grantee 
or State recipient by electronic funds transfer to the designated 
depository institution of the grantee or State recipient within 48 to 72 
hours of the disbursement request. Grant amounts for eligible 
administrative costs may be similarly drawn down by grantees by 
electronic funds transfer to their designated depository institutions, 
but State recipients are not permitted to draw down State grant amounts 
for administrative expenses. Any drawdown is conditioned upon the 
submission of satisfactory information by the grantee or State recipient 
about the project or the administrative expenses and compliance with 
other procedures specified by HUD in HUD's forms and issuances 
concerning the Rental Rehabilitation Program Cash and Management 
Information System. Copies of these forms and issuances may be obtained 
from HUD Field Offices. Drawdowns shall be requested by the grantee or 
State recipient as closely as possible to the time they are needed by a 
grantee or State recipient and the owner to pay eligible project costs 
or by a grantee to pay eligible administrative costs. Drawdowns for 
project costs shall be requested only for work or services that have 
been satisfactorily performed, or materials that are acceptable. After 
receipt in the grantee or State recipient's depository account, grant 
amounts for project costs shall immediately be disbursed by the grantee 
or State recipient and the owner in payment for eligible project costs 
and shall not be disbursed at any time, relative to a project's matching 
funds, in any greater proportion than the proportion of rental 
rehabilitation grant amounts to matching funds for the project.
    (d) Payment vouchers. As post-documentation of each drawdown, a 
grantee or State recipient must submit to HUD a payment voucher, for 
each drawdown made by HUD, in the form required for the C/MI System. If 
the drawdown was for eligible project costs and the payment voucher is 
not received within ten calendar days of the drawdown, the grantee or 
State recipient will be suspended from setting up new projects until the 
required payment voucher is received by HUD. If the drawdown was for 
administrative costs and the payment voucher is not received within ten 
calendar days of the drawdown, the grantee will not be allowed to make 
another drawdown for administrative costs until the payment voucher is 
received.
    (e) Submission of project completion reports. After the final draw 
for a project, a Project Completion Report must be submitted to HUD 
within 90 days of the drawdown request. However, for projects 
rehabilitated pursuant to Sec. 511.11(c)(2) (publicly owned project at 
the time of commitment), the Project Completion Report must be submitted 
within 90 days of the final draw, but not later than 2 years and 90 days 
after the date of commitment. If a satisfactory Project Completion 
Report is not submitted by the due date, HUD will suspend further 
project set-ups for the grantee or State recipient. Project set-

[[Page 26]]

ups will remain suspended until a satisfactory Project Completion Report 
is received and entered into the C/MI System.

(Approved by the Office of Management and Budget under control number 
2506-0080)