Sec. 58.53  Use of prior environmental impact statements.

    Where any final EIS has been listed in the Federal Register for a 
project pursuant to this part, or where an areawide or similar broad 
scale final EIS has been issued and the EIS anticipated a subsequent 
project requiring an environmental clearance, then no new EIS is 
required for the subsequent project if all the following conditions are 
met:
    (a) The ERR contains a decision based on a finding pursuant to Sec. 
58.40 that the proposed project is not a new major Federal action 
significantly affecting the quality of the human environment. The 
decision shall include:
    (1) References to the prior EIS and its evaluation of the 
environmental factors affecting the proposed subsequent action subject 
to NEPA;
    (2) An evaluation of any environmental factors which may not have 
been previously assessed, or which may have significantly changed;
    (3) An analysis showing that the proposed project is consistent with 
the location, use, and density assumptions for the site and with the 
timing and capacity of the circulation, utility, and other supporting 
infrastructure assumptions in the prior EIS;
    (4) Documentation showing that where the previous EIS called for 
mitigating measures or other corrective action, these are completed to 
the extent reasonable given the current state of development.
    (b) The prior final EIS has been filed within five (5) years, and 
updated as follows:
    (1) The EIS has been updated to reflect any significant revisions 
made to the assumptions under which the original EIS was prepared;
    (2) The EIS has been updated to reflect new environmental issues and 
data or legislation and implementing regulations which may have 
significant environmental impact on the project area covered by the 
prior EIS.
    (c) There is no litigation pending in connection with the prior EIS, 
and no final judicial finding of inadequacy of the prior EIS has been 
made.