Sec. 84.71  Closeout procedures.

    (a) Recipients shall submit, within 90 calendar days after the date 
of completion of the award, all financial, performance, and other 
reports as required by the terms and conditions of the award. HUD may 
approve extensions when requested by the recipient.
    (b) Unless HUD authorizes an extension, a recipient shall liquidate 
all obligations incurred under the award not later than 90 calendar days 
after the funding period or the date of completion as specified in the 
terms and conditions of the award or in HUD instructions.
    (c) HUD shall make prompt payments to a recipient for allowable 
reimbursable costs under the award being closed out.
    (d) The recipient shall promptly refund any balances of unobligated 
cash that HUD has advanced or paid and that is not authorized to be 
retained by the recipient for use in other projects. OMB Circular A-129 
governs unreturned amounts that become delinquent debts.
    (e) When authorized by the terms and conditions of the award, HUD 
shall make a settlement for any upward or downward adjustments to the 
Federal share of costs after closeout reports are received.
    (f) The recipient shall account for any real and personal property 
acquired with Federal funds or received from the Federal Government in 
accordance with Sec. Sec. 84.31 through 84.37.
    (g) In the event a final audit has not been performed prior to the 
closeout of an award, HUD shall retain the right to recover an 
appropriate amount after fully considering the recommendations on 
disallowed costs resulting from the final audit.