[Code of Federal Regulations]
[Title 10, Volume 1]
[Revised as of January 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 10CFR40.33]

[Page 658]
 
                            TITLE 10--ENERGY
 
                CHAPTER I--NUCLEAR REGULATORY COMMISSION
 
PART 40--DOMESTIC LICENSING OF SOURCE MATERIAL--Table of Contents
 
Sec. 40.33  Issuance of a license for a uranium enrichment facility.

    (a) The Commission will hold a hearing pursuant to 10 CFR part 2, 
subparts A, G, and I, on each application with regard to the licensing 
of the construction and operation of a uranium enrichment facility. The 
Commission will publish public notice of the hearing in the Federal 
Register at least 30 days before the hearing.
    (b) A license for a uranium enrichment facility may not be issued 
before the hearing is completed and a decision issued on the 
application.

[57 FR 18391, Apr. 30, 1992]