    (a) In general. Grants of authority issued by the Board for the 
establishment of zones or subzones, including

[[Page 71]]

those already issued, are subject to the Act and this part and the 
following general conditions or limitations:
    (1) Approvals from the grantee and the Port Director, pursuant to 19 
CFR part 146, are required prior to the activation of any portion of an 
approved zone project; and
    (2) Approval of the Board or the Commerce Department's Assistant 
Secretary for Import Administration pursuant to subpart D of this part 
is required prior to the commencement of manufacturing beyond the scope 
of that approved as part of the application or pursuant to reviews under 
this part (e.g., new end products, significant expansions of plant 
production capacity), and of similar changes in processing activity 
which involves foreign articles subject to quantitative import controls 
(quotas) or results in articles subject to a lower (actual or effective) 
duty rate (inverted tariff) than any of their foreign components.
    (3) Sourcing changes--(i) Notification requirement. The grantee or 
operator of a zone or subzone shall notify the Executive Secretary when 
there is a change in sourcing for authorized manufacturing or processing 
activity which involves the use of new foreign articles subject to 
quotas or inverted tariffs, unless--
    (A) Entries for consumption are not to be made at the lower duty 
rate; or
    (B) The product in which the foreign articles are to be incorporated 
is being produced for exportation.
    (ii) Notification procedure. Notification shall be given prior to 
the commencement of the activity, when possible, otherwise at the time 
the new foreign articles arrive in the zone or are withdrawn from 
inventory for use in production. Requests may be made to the Executive 
Secretary for authority to submit notification of sourcing changes on a 
quarterly federal fiscal year basis covering changes in the previous 
quarter.
    (iii) Reviews. (A) Upon notification of a sourcing change under 
paragraph (a)(3)(i) of this section, within 30 days, the Executive 
Secretary will conduct a preliminary review of the changes in relation 
to the approved activity to determine whether they could have 
significant adverse effects, taking into account the factors enumerated 
in Sec.  400.31(b), and will submit a report and recommendation to the 
Commerce Department's Assistant Secretary for Import Administration, who 
shall determine whether review is necessary. The procedures of Sec.  
400.32(b) shall be used in these situations when appropriate.
    (B) The Board or the Commerce Department's Assistant Secretary for 
Import Administration may, based on public interest grounds, prohibit or 
restrict the use of zone procedures in regard to the change in sourcing, 
including requiring that items be placed in privileged foreign status 
(19 CFR 146.41) upon admission to a zone or subzone.
    (C) The Executive Secretary shall direct reviews necessary to ensure 
that activity involved in these situations continues to be in the public 
interest.
    (4) Prior to activation of a zone, the zone grantee or operator 
shall obtain all necessary permits from federal, state and local 
authorities, and except as otherwise specified in the Act or this part, 
shall comply with the requirements of those authorities.
    (5) A grant of authority for a zone or a subzone shall lapse unless 
the zone project (in case of subzones, the subzone facility) is 
activated, pursuant to 19 CFR part 146, and in operation not later than 
five years from:
    (i) A Board order (authorizing the zone or subzone) issued after 
November 7, 1991; or
    (ii) November 7, 1991.
    (6) A grant of authority approved under this subpart includes 
authority for the grantee to permit the erection of buildings necessary 
to carry out the approved zone project subject to concurrence of the 
Port Director.
    (7) Zone grantees, operators, and users shall permit federal 
government officials acting in an official capacity to have access to 
the zone project and records during normal business hours and under 
other reasonable circumstances.
    (8) A grant of authority may not be sold, conveyed, transferred, set 
over, or assigned (FTZ Act, section 17; 19 U.S.C. 81q). Private 
ownership of zone land and facilities is permitted provided the zone 
grantee retains the control necessary to implement the approved zone

[[Page 72]]

project. Should title to land or facilities be transferred after a grant 
of authority is issued, the zone grantee must retain, by agreement with 
the new owner, a level of control which allows the grantee to carry out 
its responsibilities as grantee. The sale of a zone site or facility for 
more than its fair market value without zone status could, depending on 
the circumstances, be subject to section 17 of the Act.
    (9) A grant of authority will not be construed to make the zone 
grantee automatically liable for violations by operators, users, or 
other parties.
    (b) Additional conditions, prohibitions and restrictions. Other 
requirements, conditions or restrictions under Federal, State or local 
law may apply to the zone or subzone authorized by the grant of 
authority.
    (c) Revocation of grants of authority. (1) In general. As provided 
in this section, the Board can revoke in whole or in part a grant of 
authority for a zone or subzone whenever it determines that the zone 
grantee or, in the case of subzones, the subzone operator, has violated, 
repeatedly and willfully, the provisions of the Act.
    (2) Procedure. When the Board has reason to believe that the 
conditions for revocation, as described in paragraph (a) of this 
section, are met, the Board will:
    (i) Notify the zone or subzone grantee in writing stating the nature 
of the alleged violations, and provide the grantee an opportunity to 
request a hearing on the proposed revocation;
    (ii) Conduct a hearing, if requested or otherwise if appropriate;
    (iii) Make a determination on the record of the proceeding not 
earlier than 4 months after providing notice to the zone grantee under 
paragraph (b)(1) of this section; and
    (iv) If the Board's determination is affirmative, publish notice of 
revocation of the grant of authority in the Federal Register.
    (3) As provided in section 18 of the Act (19 U.S.C. 81r(c)), the 
zone or subzone grantee may appeal an order of the Board revoking the 
grant of authority.

[56 FR 50798, Oct. 8, 1991; 56 FR 65833, Dec. 19, 1991, as amended at 62 
FR 53535, Oct. 15, 1997]