           TITLE 41--PUBLIC CONTRACTS AND PROPERTY MANAGEMENT
 
              CHAPTER 105--GENERAL SERVICES ADMINISTRATION
 
PART 105-71_UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND COOPERATIVE 
AGREEMENTS WITH STATE AND LOCAL GOVERNMENTS--Table of Contents
 
    Subpart 105-71.13_Post-Award Requirements/Changes, Property, and 
                                Subawards
 
Sec. 105-71.130  Changes.


    (a) General. Grantees and subgrantees are permitted to rebudget 
within the approved direct cost budget to meet unanticipated 
requirements and may make limited program changes to the approved 
project. However, unless waived by the awarding agency, certain types of 
post-award changes in budgets and projects shall require the prior 
written approval of the awarding agency.
    (b) Relation to cost principles. The applicable cost principles (see 
Sec. 105-71.122) contain requirements for prior approval of certain 
types of costs. Except where waived, those requirements apply to all 
grants and subgrants even if paragraphs (c) through (f) of this section 
do not.
    (c) Budget changes-- (1) Non-construction projects. Except as stated 
in other regulations or an award document, grantees or subgrantees shall 
obtain the prior approval of the awarding agency whenever any of the 
following changes is anticipated under a non-construction award:

[[Page 532]]

    (i) Any revision which would result in the need for additional 
funding.
    (ii) Unless waived by the awarding agency, cumulative transfers 
among direct cost categories, or, if applicable, among separately 
budgeted programs, projects, functions, or activities which exceed or 
are expected to exceed ten percent of the current total approved budget, 
whenever the awarding agency's share exceeds $100,000.
    (iii) Transfer of funds allotted for training allowances (i.e., from 
direct payments to trainees to other expense categories).
    (2) Construction projects. Grantees and subgrantees shall obtain 
prior written approval for any budget revision which would result in the 
need for additional funds.
    (3) Combined construction and non-construction projects. When a 
grant or subgrant provides funding for both construction and non-
construction activities, the grantee or subgrantee must obtain prior 
written approval from the awarding agency before making any fund or 
budget transfer from non-construction to construction or vice versa.
    (d) Programmatic changes. Grantees or subgrantees must obtain the 
prior approval of the awarding agency whenever any of the following 
actions is anticipated:
    (1) Any revision of the scope or objectives of the project 
(regardless of whether there is an associated budget revision requiring 
prior approval).
    (2) Need to extend the period of availability of funds.
    (3) Changes in key persons in cases where specified in an 
application or a grant award. In research projects, a change in the 
project director or principal investigator shall always require approval 
unless waived by the awarding agency.
    (4) Under non-construction projects, contracting out, subgranting 
(if authorized by law) or otherwise obtaining the services of a third 
party to perform activities which are central to the purposes of the 
award. This approval requirement is in addition to the approval 
requirements of Sec. 105-71.136 but does not apply to the procurement 
of equipment, supplies, and general support services.
    (e) Additional prior approval requirements. The awarding agency may 
not require prior approval for any budget revision which is not 
described in paragraph (c) of this section.
    (f) Requesting prior approval. (1) A request for prior approval of 
any budget revision will be in the same budget format the grantee used 
in its application and shall be accomplished by a narrative 
justification for the proposed revision.
    (2) A request for a prior approval under the applicable Federal cost 
principles (see Sec. 105-71.122) may be made by letter.
    (3) A request by a subgrantee for prior approval will be addressed 
in writing to the grantee. The grantee will promptly review such request 
and shall approve or disapprove the request in writing. A grantee will 
not approve any budget or project revision which is inconsistent with 
the purpose or terms and conditions of the Federal grant to the grantee. 
If the revision, requested by the subgrantee would result in a change to 
the grantee's approved project which requires Federal prior approval, 
the grantee will obtain the Federal agency's approval before approving 
the subgrantee's request.