PART 2800_RIGHTS-OF-WAY, PRINCIPLES AND PROCEDURES--Table of Contents
 
                   Subpart 2808_Reimbursement of Costs
 
Sec. 2808.3-3  Costs incurred for a withdrawn or denied application.

    (a) An applicant whose application is denied is liable for any costs 
incurred by the United States in processing the application. Those 
amounts that have not been paid are due within 30 days of the receipt of 
a bill from the authorized officer identifying the amount due.
    (b) An applicant who withdraws an application before a grant or 
temporary use permit is issued is liable for all costs incurred by the 
United States in processing the application up to the date the 
authorized officer receives the written notice of withdrawal, and for

[[Page 257]]

costs subsequently incurred in terminating the processing of said 
application. Those amounts that have not been paid are due within 30 
days of receipt of a bill from the authorized officer identifying the 
amount due.