[Code of Federal Regulations]
[Title 44, Volume 1]
[Revised as of October 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 44CFR9.11]

[Page 94-96]
 
              TITLE 44--EMERGENCY MANAGEMENT AND ASSISTANCE
 
 CHAPTER I--FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND 
                                SECURITY
 
PART 9_FLOODPLAIN MANAGEMENT AND PROTECTION OF WETLANDS--Table of Contents
 
Sec. 9.11  Mitigation.

    (a) Purpose. The purpose of this section is to expand upon the 
directives set out in Sec. 9.6 of this part, and to set out the 
mitigative actions required if the preliminary determination is made to 
carry out an action that affects or is in a floodplain or wetland.
    (b) General provisions. (1) The Agency shall design or modify its 
actions so as to minimize harm to or within the floodplain;
    (2) The Agency shall minimize the destruction, loss or degradation 
of wetlands;
    (3) The Agency shall restore and preserve natural and beneficial 
floodplain values; and
    (4) The Agency shall preserve and enhance natural and beneficial 
wetland values.
    (c) Minimization provisions. The Agency shall minimize:
    (1) Potential harm to lives and the investment at risk from the base 
flood, or, in the case of critical actions, from the 500-year flood;
    (2) Potential adverse impacts the action may have on others; and
    (3) Potential adverse impact the action may have on floodplain and 
wetland values.
    (d) Minimization Standards. In its implementation of the Disaster 
Relief Act of 1974, the Agency shall apply at a minimum, the following 
standards to its actions to comply with the requirements of paragraphs 
(b) and (c), of this section, (except as provided in Sec. 9.5 (c), (d), 
and (g) regarding categories of partial or total exclusion). Any Agency 
action to which the following specific requirements do not apply, shall 
nevertheless be subject to the full 8-step process (Sec. 9.6) including 
the general requirement to minimize harm to and within floodplains:
    (1) There shall be no new construction or substantial improvement in 
a floodway, and no new construction in a coastal high hazard area, 
except for:
    (i) A functionally dependent use; or
    (ii) A structure or facility which facilitates an open space use.
    (2) For a structure which is a functionally dependent use, or which 
facilitates an open space use, the following applies. There shall be no 
construction of a new or substantially improved structure in a coastal 
high hazard area unless it is elevated on adequately anchored pilings or 
columns, and securely anchored to such piles or columns so that the 
lowest portion of the structural members of the lowest floor (excluding 
the pilings or columns) is elevated to or above the base flood level 
(the 500-year flood level for critical actions) (including wave height). 
The structure shall be anchored so as to withstand velocity waters and 
hurricane wave wash. The Regional Director shall be responsible for 
determining the base flood level, including the wave height, in all 
cases. Where there is a FIRM in effect, it shall be the basis of the 
Regional Director's determination. If the FIRM does not reflect wave 
heights, or if there is no FIRM in effect, the Regional Director is 
responsible for delineating the base flood level, including wave 
heights.
    (3) Elevation of structures. (i) There shall be no new construction 
or substantial improvement of structures unless the lowest floor of the 
structures (including basement) is at or above the level of the base 
flood.
    (ii) There shall be no new construction or substantial improvement 
of structures involving a critical action unless the lowest floor of the 
structure (including the basement) is at or above the level of the 500-
year flood.
    (iii) If the subject structure is nonresidential, FEMA may, instead 
of elevating the structure to the 100-year or 500-year level, as 
appropriate, approve the design of the structure and its attendant 
utility and sanitary facilities so that below the flood level the 
structure is water tight with walls substantially impermeable to the 
passage of water and with structural components having the capability of 
resisting hydrostatic and hydrodynamic loads and effects of buoyancy.
    (iv) The provisions of paragraphs (d)(3)(i), (ii), and (iii) of this 
section do not apply to the extent that the Federal Insurance 
Administration has granted an exception under 44 CFR Sec. 60.6(b) 
(formerly 24 CFR 1910.6(b)), or the community has granted a variance

[[Page 95]]

which the Regional Director determines is consistent with 44 CFR 60.6(a) 
(formerly 24 CFR 1910.6(a)). In a community which does not have a FIRM 
in effect, FEMA may approve a variance from the standards of paragraphs 
(d)(3)(i), (ii), and (iii) of this section, after compliance with the 
standards of 44 CFR 60.6(a).
    (4) There shall be no encroachments, including fill, new 
construction, substantial improvements of structures or facilities, or 
other development within a designated regulatory floodway that would 
result in any increase in flood levels within the community during the 
occurrence of the base flood discharge. Until a regulatory floodway is 
designated, no new construction, substantial improvements, or other 
development (including fill) shall be permitted within the base 
floodplain unless it is demonstrated that the cumulative effect of the 
proposed development, when combined with all other existing and 
anticipated development, will not increase the water surface elevation 
of the base flood more than one foot at any point within the community.
    (5) Even if an action is a functionally dependent use or facilitates 
open space uses (under paragraph (d) (1) or (2) of this section) and 
does not increase flood heights (under paragraph (d)(4) of this 
section), such action may only be taken in a floodway or coastal high 
hazard area if:
    (i) Such site is the only practicable alternative; and
    (ii) Harm to and within the floodplain is minimized.
    (6) In addition to standards (d)(1) through (d)(5) of this section, 
no action may be taken if it is inconsistent with the criteria of the 
National Flood Insurance Program (44 CFR part 59 et seq.) or any more 
restrictive Federal, State or local floodplain management standards.
    (7) New construction and substantial improvement of structures shall 
be elevated on open works (walls, columns, piers, piles, etc.) rather 
than on fill, in all cases in coastal high hazard areas and elsewhere, 
where practicable.
    (8) To minimize the effect of floods on human health, safety and 
welfare, the Agency shall:
    (i) Where appropriate, integrate all of its proposed actions in 
floodplains into existing flood warning and preparedness plans and 
ensure that available flood warning time is reflected;
    (ii) Facilitate adequate access and egress to and from the site of 
the proposed action; and
    (iii) Give special consideration to the unique hazard potential in 
flash flood, rapid-rise or tsunami areas.
    (9) In the replacement of building contents, materials and 
equipment, the Regional Director shall require as appropriate, disaster 
proofing of the building and/or elimination of such future losses by 
relocation of those building contents, materials and equipment outside 
or above the base floodplain or the 500-year floodplain for critical 
actions.
    (e) In the implementation of the National Flood Insurance Program. 
(1) The Federal Insurance Administration shall make identification of 
all coastal high hazard areas a priority;
    (2) Beginning October 1, 1981, the Federal Insurance Administration 
of FEMA may only provide flood insurance for new construction or 
substantial improvements in a coastal high hazard area if:
    (i) Wave heights have been designated for the site of the structure 
either by the Director of FEMA based upon data generated by FEMA or by 
another source, satisfactory to the Director; and
    (ii) The structure is rated by FEMA-FIA based on a system which 
reflects the capacity to withstand the effects of the 100-year frequency 
flood including, but not limited to, the following factors:
    (A) Wave heights;
    (B) The ability of the structure to withstand the force of waves.
    (3)(i) FEMA shall accept and take fully into account information 
submitted by a property owner indicating that the rate for a particular 
structure is too high based on the ability of the structure to withstand 
the force of waves. In order to obtain a rate adjustment, a property 
owner must submit to FEMA specific information regarding the structure 
and its immediate environment. Such information must be certified by a 
registered professional

[[Page 96]]

architect or engineer who has demonstrable experience and competence in 
the fields of foundation, soils, and structural engineering. Such 
information should include:
    (A) Elevation of the structure (bottom of lowest floor beam) in 
relation to the Base Flood Elevation including wave height;
    (B) Distance of the structure from the shoreline;
    (C) Dune protection and other environmental factors;
    (D) Description of the building support system; and
    (E) Other relevant building details.

Adequate completion of the ``V-Zone Risk Factor Rating Form'' is 
sufficient for FEMA to determine whether a rate adjustment is 
appropriate. The form is available from and applications for rate 
adjustments should be submitted to:

National Flood Insurance Program
Attention: V-Zone Underwriting Specialist
9901-A George Palmer Highway
Lanham, MD 20706


Pending a determination on a rate adjustment, insurance will be issued 
at the class rate. If the rate adjustment is granted, a refund of the 
appropriate portion of the premium will be made. Unless a property owner 
is seeking an adjustment of the rate prescribed by FEMA-FIA, this 
information need not be submitted.
    (ii) FIA shall notify communities with coastal high hazard areas and 
federally related lenders in such communities, of the provisions of this 
paragraph. Notice to the lenders may be accomplished by the Federal 
instrumentalities to which the lenders are related.
    (4) In any case in which the Regional Director has been, pursuant to 
Sec. 9.11(d)(1), precluded from providing assistance for a new or 
substantially improved structure in a floodway, FIA may not provide a 
new or renewed policy of flood insurance for that structure.
    (f) Restore and preserve. (1) For any action taken by the Agency 
which affects the floodplain or wetland and which has resulted in, or 
will result in, harm to the floodplain or wetland, the Agency shall act 
to restore and preserve the natural and beneficial values served by 
floodplains and wetlands.
    (2) Where floodplain or wetland values have been degraded by the 
proposed action, the Agency shall identify, evaluate and implement 
measures to restore the values.
    (3) If an action will result in harm to or within the floodplain or 
wetland, the Agency shall design or modify the action to preserve as 
much of the natural and beneficial floodplain and wetland values as is 
possible.

[45 FR 59526, Sept. 9, 1980, as amended at 46 FR 51752, Oct. 22, 1981; 
48 FR 44543, Sept. 29, 1983; 49 FR 33879, Aug. 27, 1984; 49 FR 35584, 
Sept. 10, 1984; 50 FR 40006, Oct. 1, 1985]

    Effective Date Note: At 45 FR 79070, Nov. 28, 1980, Sec. 9.11(e)(4) 
was temporarily suspended until further notice.