Sec. 189.40-5  Notice and plans required.

    (a) The master, owner, operator, or agent of the vessel shall notify 
the Officer in Charge, Marine Inspection, whenever the vessel is to be 
drydocked regardless of the reason for drydocking.
    (b) Each vessel, except barges, that holds a Load Line Certificate 
must have on board a plan showing the vessel's scantlings. This plan 
must be made available to the Coast Guard marine inspector whenever the 
vessel undergoes a drydock examination, internal structural examination, 
or underwater survey or whenever repairs are made to the vessel's hull.
    (c) Each barge that holds a Load Line Certificate must have a plan 
showing the barge's scantlings. The plan need not be maintained on board 
the barge but must be made available to the Coast Guard marine inspector 
whenever the barge undergoes a drydock examination, internal structural 
examination, or underwater survey or whenever repairs are made to the 
barge's hull.

[CGD 84-024, 52 FR 39657, Oct. 23, 1987]