Sec. 39.40-5 Operational requirements for vapor balancing--TB/ALL.
(a) During a lightering or topping-off operation each cargo tank
being loaded must be connected by the vapor collection system to a cargo
tank which is being discharged.
(b) If the cargo tanks on both the vessel discharging cargo and the
vessel receiving cargo are inerted, the following requirements must be
met:
(1) Each tank on a vessel receiving cargo which is connected to the
vapor collection system must be tested prior to cargo transfer to ensure
that the oxygen content in the vapor space does not exceed 8 percent by
volume. The oxygen content of each tank must be measured at a point one
meter (3.28 feet) below the tanktop and at a point equal to one-half of
the ullage. Where tanks have partial bulkheads, the oxygen content of
each area of that tank formed by each partial bulkhead must be measured
at a point one meter (3.28 feet) below the tanktop and at a point equal
to one-half of the ullage;
(2) The oxygen analyzer required by Sec. 39.40-3(a) must be tested
for proper operation prior to the start of each transfer operation;
(3) The oxygen content of vapors being transferred must be
continuously monitored during the transfer operation;
(4) Cargo transfer must be terminated if the oxygen content exceeds
8 percent by volume and must not be restarted until the oxygen content
in the tanks of the vessel receiving cargo is reduced to 8 percent by
volume or less; and
(5) The vapor transfer hose must be purged of air and inerted prior
to starting vapor transfer.
(c) The isolation valve, required by Sec. 39.20-1(c) of this part,
located on the
[[Page 509]]
service vessel must not be opened until the pressure in the vapor
collection system on the vessel receiving cargo exceeds the pressure in
the vapor collection system on the vessel discharging cargo.
(d) The cargo transfer rate must be controlled from the vessel
discharging cargo, and must not exceed the maximum allowable transfer
rate for the vessel receiving cargo.
(e) The pressure in the vapor space of any cargo tank connected to
the vapor collection line on either the vessel receiving cargo or the
vessel discharging cargo must not exceed 80 percent of the lowest
setting of any pressure relief valve during ballasting or cargo
transfer.
(f) All impressed current cathodic protection systems must be
deenergized during cargo transfer operations.
(g) Tank washing is prohibited unless the cargo tanks on both the
vessel discharging cargo and the vessel receiving cargo are inerted or
the tank is isolated from the vapor collection line.
[CGD 88-102, 55 FR 25446, June 21, 1990; 55 FR 39270, Sept. 26, 1990]
[[Page 511]]
INDEX
SUBCHAPTER D_TANK VESSELS
Editorial Note: This listing is provided for informational purposes
only. It is compiled and kept current by the U.S. Coast Guard,
Department of Homeland Security. This index is updated as of October 1,
2003.
Part, subpart, or section
A
Accident or casualty report................................Subpart 35.15
Accommodations for crew....................................Subpart 32.40
Application......................................................32.40-1
Construction....................................................32.40-15
Heating and cooling.............................................32.40-50
Hospital space..................................................32.40-35
Insect screens..................................................32.40-55
Location of Crew spaces.........................................32.40-10
Messrooms.......................................................32.40-30
On tankships constructed before June 15, 1987...................32.40-65
On tankships of less than 100 gross tons and manned tank barges
32.40-60
Other spaces....................................................32.40-40
Sleeping Accommodations.........................................32.40-20
Washrooms and toilet rooms......................................32.40-25
Aids to Navigation:
Charts or information regarding..................................35.20-1
Coast pilots.....................................................35.20-1
Current tables...................................................35.20-1
Light lists......................................................35.20-1
Nautical publications............................................35.20-1
Notice to Mariners...............................................35.20-1
Sailing directions...............................................35.20-1
Tide tables......................................................35.20-1
Air compressor........................................32.35-15, 35.35-85
Alarm bells........................................................32.25
Marking required.................................................35.40-5
Switches, markings of............................................35.40-1
Alarm systems..............................................Subpart 32.25
Alcohol or drugs, used by crew..................................35.05-25
Alterations and repairs, regulations governing........30.01-10, 31.10-25
American Bureau of Shipping......................................31.10-1
Anniversary date................................................30.10-2a
Annual inspection:
Application for:................................................31.01-15
Fire extinguishers..............................................31.10-18
Anode installations, sacrificial................................35.01-25
Appeal right of.................................................30.20-50
Application for inspection.............................31.01-15, 31.1-20
Application, electrical installations Subpart......................32.45
Application of regulations:
Governing alterations and repairs...............................30.01-10
[[Page 512]]
Vessels on an international voyage...............................30.01-6
Approved, definition.............................................30.10-3
Arresters, flame......................................30.10-23, 32.20-10
Assignment of functions.........................................31.01-10
Auto pilot......................................................35.20-45
Auxiliary machinery:
Construction.....................................................32.35-1
Design...........................................................32.35-1
Installation of internal combustion engine.......................32.35-5
Axes, fire...............................................34.05-20, 34.60
B
Ballasting......................................................31.10-32
Bell, alarm Subpart................................................32.25
Bell signals.....................................................32.30-5
Bilge injection valves..........................................31.10-20
Bilge systems Subpart..............................................32.52
Bills of lading required........................................35.01-10
Boilerroom, fire extinguishing systems for.......................34.05-5
Boilers:
Accident report by chief engineer................................35.25-5
Examination by engineer..........................................35.25-1
Safety rules for fires...........................................35.30-5
Breeches buoy, poster containing instruction regarding use of....Subpart
35.12
Breathing apparatus, fresh air........................35.30-20, 35.40-20
Butterworth plates, safety rules regarding......................35.30-10
C
Carbon dioxide extinguishing systems:
Alarms..........................................................34.15-30
Amount of carbon dioxide required................................34.15-5
Application......................................................34.15-1
Controls........................................................34.15-10
Discharge outlets...............................................34.15-25
Dry cargo spaces.................................................34.15-5
Enclosed ventilation systems for rotating electrical propulsion
equipment........................................................34.15-5
Enclosure openings..............................................34.15-35
Installation contracted for prior to January 1, 1962............34.15-90
Machinery spaces pumprooms paint lockers and similar spaces......34.15-5
Piping..........................................................34.15-15
Pressure relief.................................................34.15-40
Quantity, pipe sizes, and discharge rates........................34.15-5
Storage.........................................................34.15-20
Total available supply...........................................34.15-5
Cargo definition.................................................30.10-5
Cargo discharge...................................................32.5-3
Cargoes elevated temperatures....................................Part 36
Cargoes regulated..........................................Subpart 30.25
Cargo gear certificates or registers.............31.10-16, Subpart 31.37
Cargo gear inspection....................................31.10-16, 31.37
Cargo handling:
Equipment maintenance...........................................35.35-70
General............................................................35.35
Liquefied petroleum gases..................................Subpart 38.15
Loading information................................................35.35
Safety requirements................................................35.30
[[Page 513]]
Unmanned tank barges.............................................35.35-1
Cargo handling room, definitions.................................30.10-6
Cargo hose...................................35.35-15, 35.35-70, 38.15-5
Cargo piping............................................40.15-1,38.10-10
Cargo pumps................................................Subpart 32.50
Cargo pump relief valves.........................................36.10-1
Cargo pump, testing of..........................................35.35-70
Cargo tank hatches, ullage holes and Butterworth plates, safety
rules regarding.................................................35.30-10
Cargo tanks:
Construction and testing of.......32.60-40, 32.65-40, 32.70-25, 32.75-10
Design and installation of.........................................38.05
Electric bonding and grounding of...............................32.75-15
Filling densities................................................38.15-1
Fire extinguishing systems for...................................34.05-5
Hydrostatic test of..............................................38.25-1
Installation for carrying liquids at elevated temperatures.......36.05-1
Independent.......................32.60-30, 32.65-30, 32.70-25, 32.75-10
Lagging.........................................................38.05-20
Liquefied petroleum gases........................................Part 38
Liquid level gauging devices..........................38.10-20, 32.20-20
Marking of.......................................................38.05-5
Periodic test....................................................38.25-1
Piping..........................................................38.10-10
Refrigeration system used with..................................38.05-25
Removal from service.............................................38.25-5
Venting of...............................Subpart 32.55, 38.20-1, 38.20-5
Cargo transfer:
Approval of.....................................................35.35-25
Conditions affecting............................................35.35-40
Connecting of cargo hose........................................35.35-15
Declaration of inspection.......................................35.35-30
Duties of senior deck officer...................................35.35-35
Electric bonding.................................................35.35-5
Filling densities................................................38.15-1
Handling of packaged goods, etc.................................35.35-55
Inspection prior to............................................35.35-2 0
Liquefied flammable gases........................................38.15-5
Maintenance of equipment........................................35.35-70
Men on duty......................................................35.35-1
Tank barges.....................................................35.35-60
Termination of..................................................35.35-50
Towing vessels furnishing steam, air or electricity.............35.35-45
Vapor control systems............................................Part 39
Vessels coming alongside during.................................35.35-42
Carriage of person other than crew..............................35.01-15
Casualty or accident report................................Subpart 35.15
Certificate of class.............................................31.10-5
Certificate of inspection:
Application for.......................................31.01-15, 31.01-20
Cargoes of elevated temperatures, carriage of....................36.01-5
Delivery of......................................................31.05-1
Endorsed for liquefied flammable gas.............................38.01-5
Indication of water traveled on..................................31.20-1
Ocean or unlimited coastwise vessels on inland and Great Lakes
Routes-TB/OC.....................................................30.01-7
Posting of.......................................................31.05-5
Terms, endorsements.............................................31.05-15
[[Page 514]]
Validity.......................................................31.10-17a
Certificates regarding shipboard cargo gear..............31.10-16, 31.37
Certificates under International Convention for Safety of Life at
Sea......................................................31.10-16, 31.37
1960 American Bureau of Shipping................................31.40-45
Application......................................................31.40-1
Cargo Ship Safety Construction Certificate.......................31.40-5
Cargo Ship Safety Equipment Certificate.........................31.40-10
Cargo Ship Safety Radiotelegraphy Certificate...................31.40-15
Cargo Ship Safety Radiotelephony Certificate....................31.40-20
Duration of Convention Certificate..............................31.40-40
Exemption Certificate...........................................31.40-25
Posting of Convention Certificates..............................31.40-35
Certified crewmembers............................................31.15-1
Certified definition.............................................30.10-7
Charts of navigable waters required..............................35.20-1
Chief Engineer:
Repairs of boilers and unfired pressure vessels and reports or
accidents........................................................35.25-5
Class, certificate of............................................31.10-5
Classification requirements, definition..........................30.10-9
CO2 fire apparatus, marking required.................35.40-10
Coast Guard District Commander..................................30.10-19
Coast pilots.....................................................35.20-1
Coastwise, definition...........................................30.10-11
Cofferdam:
Definition of...................................................30.10-13
Location of.................................32.60-10, 32.65-15, 32.70-10
Requirements of.................................................32.70-10
Venting of......................................................32.55-45
Combustible gas indicator.......................................35.30-15
Combustible liquids, definition.................................30.10-15
Commandant, definition..........................................30.10-17
Commodities regulated......................................Subpart 30.25
Communication, interior system.............................Subpart 32.30
Construction and testing of cargo tanks and bulkheads on tank
vessels.....................................32.65-40, 32.60-40, 32.75-10
Construction of tank barges of materials other than steel or iron,
requirements.....................................................32.80-1
Construction of tank vessels:
Cargo spaces segregated from cargo tanks.................32.57-10, 32.60
Ceilings.........................................................32.57-1
Deck............................................................32.57-10
Enclosed spaces.................................................32.60-10
General cargo spaces............................................32.60-15
Hatch covers....................................................32.57-10
Hull requirements.............................32.60, 32.65, 32.70, 32.75
Lamp Lockers....................................................32.57-10
Living quarters.......................................32.60-25, 32.65-25
Location of cargo tank spaces...................................32.60-10
Location of independent....................................tanks32.60-30
Machinery........................................................32.35-1
Paint lockers...................................................32.57-10
Requirements for scantlings, material and workmanship...........32.60-1,
32.65-1, 32.70-5, 32.75-5
Segregation of cargo............................................32.60-10
Stowage spaces..................................................32.60-10
Subdivision of cargo space.............................32.60-5, 32.65-10
[[Page 515]]
Testing of cargo tanks and bulkheads.......32.60-40, 32.65-40, 32.70-25,
32.75-10
Construction of vessels for liquefied gases......................38.05-1
Construction of wood hull tank vessels:
Application of regulations.......................................32.75-1
Electric bonding and grounding of cargo tanks...................32.75-15
Hold spaces.....................................................32.75-20
Independent cargo tanks.........................................32.75-10
Convention certificates....................................Subpart 31.40
Conversion of vessels to tank vessels...........................31.10-10
Crew:
Certified members of.............................................31.15-1
Illness of......................................................35.05-25
Licensed officers................................................31.15-1
Physical condition of...........................................35.05-20
Required for cargo handling......................................35.35-1
Crew accommodations:
Inspection of...................................................31.10-45
Requirements for...........................................Subpart 32.40
Sanitary condition of............................................35.01-5
Current tables...................................................35.20-1
D
Deck foam system...........................................Subpart 34.20
Declaration of inspection prior to bulk cargo transfer..........35.35-30
Definition of terms........................................Subpart 30.10
Delivery of certificate of inspection............................31.05-1
Design:
Cargo tanks......................................................38.05-2
Main and auxiliary machinery.....................................32.35-1
Vapor control system.......................................Subpart 39.20
Devices, spark producing........................................35.30-35
Display of Plans.................................................35.10-3
Draft marks.............................................32.05-1, 35.20-5
Drills:
Boat.............................................................35.10-5
Fire.............................................................35.10-5
Line throwing appliance..........................................35.10-1
Drydock or hauling out..........................................31.10-20
E
Effective date of regulation....................................30.01-15
Electric bonding and grounding.........................32.75-15, 35.35-5
Electrical installations....................................31.35, 32.45
Elevated temperature cargoes:
Cargo pump relief valves.........................................36.10-1
Certificate of inspection........................................36.01-5
Flame Screens, vents and ventilations............................36.20-1
Installation of cargo tanks......................................36.05-1
Lagged tanks, periodic inspections...............................36.30-1
Protection of personnel.........................................36.05-10
Ventilation of pumproom..........................................36.20-5
Emergency:
Authority of senior officer.....................................35.35-75
Breathing equipment, marking....................................35.40-20
Lighting and power systems......................................35.10-15
Outfit..........................................................35.30-20
Repairs to firefighting equipment...............................35.01-35
[[Page 516]]
Signals..........................................................35.10-5
Training.........................................................35.10-1
Enclosed ventilating system, fire extinguishing system...........34.05-5
Enforcement......................................................30.20-1
Engineering, electrical.....................................31.35, 32.45
Engineering, marine Subpart........................................31.30
Equipment:
Cargo handling.............................................Subpart 32.50
Emergency.......................................................35.30-20
Fire and emergency, marking......................Subpart 35.40, 35.40-40
Installed but not required.......................................34.01-5
Portable electrical.............................................35.30-30
Previously approved.............................................30.01-15
Equipment installations....................................Subpart 32.20
Equipment installations on vessels during World War II...........32.20-1
Equipment, navigation......................................Subpart 32.15
Equivalents......................................................30.15-1
Escape, means of.................................................32.02-1
Examination of tail shaft.......................................61.15-15
Examination of sea chests, sea valves, sea strainers, and bilge
injection valves................................................31.10-20
Exemption certificate...........................................31.40-25
Explosives, transportation of...................................35.30-25
F
Fire axes................................................34.05-20, 34.60
Location of.....................................................34.60-10
Number required..................................................34.60-5
Fire drills......................................................35.10-5
Fire extinguishers, portable and semiportable:
Application......................................................34.50-1
Classification...................................................34.50-5
Location........................................................34.50-10
Spare charges...................................................34.50-15
Vessels contracted for prior to January 1, 1962.................34.50-90
Fire extinguishing deck foam system:
Application......................................................34.20-1
Area protected...................................................34.20-5
Cargo area definitions...........................................34.20-3
Controls........................................................34.20-10
Discharge outlets...............................................34.20-20
Installations contracted for prior to January 1, 1970...........34.20-90
Marking.........................................................35.40-10
Piping..........................................................34.20-15
Quantity of foam required........................................34.20-5
Rate of application..............................................34.20-5
Separate supply of foam-producing material.......................34.20-5
Supply of foam producing material................................34.20-5
Water supply.....................................................34.20-5
Fire extinguishing fixed foam systems:
Additional protection required..................................34.17-25
Application......................................................34.17-1
Area protected...................................................34.17-5
Controls........................................................34.17-10
Discharge outlets...............................................34.17-20
Installations contracted for prior to January 1, 1962...........34.17-90
Piping..........................................................34.17-15
[[Page 517]]
Rate of Application..............................................34.17-5
Separate supply of foam-producing material.......................34.17-5
Supply of foam producing material................................34.17-5
Water supply for required pumps..................................34.17-5
Fire extinguishing systems:
Boilerrooms......................................................34.05-5
Carbon dioxide.....................................................34.15
Cargo tanks......................................................34.05-5
Dry cargo compartments...........................................34.05-5
Enclosed ventilating systems.....................................34.05-5
Foam, deck.................................................Subpart 34.20
Foam, fixed................................................Subpart 34.17
Installations contracted for prior to January 1, 1962...........34.10-90
Lamp, paint lockers and similar pages............................34.05-5
Machinery spaces.................................................34.05-5
Marking.........................................................35.40-10
Piping..........................................................34.10-15
Pumprooms........................................................34.05-5
Fire extinguishing system, steam smothering:
Application......................................................34.13-1
Installations contracted for prior to January 1, 1962...........34.17-90
Firefighting equipment:
Application......................................................34.01-1
Fire axes................................................34.05-20, 34.60
Fire main system.................................................34.05-1
Hose............................................................34.10-10
Nozzles.........................................................35.40-10
Hydrants........................................................35.40-15
Installed but not required.......................................34.01-5
Portable, vessel's name on......................................35.40-40
Protection for unusual arrangements or special products.........34.01-10
Testing and inspection................................31.10-18, 31.10-19
Fire main system:
Application......................................................34.10-1
Fire pumps.......................................................34.10-5
Fire station hydrants hose and nozzles..........................34.10-10
Fire, matches and smoking safety rules...........................35.30-5
Fire protection, structu1ral, for tank vessels contracted for on
or after January 1, 1963...................................Subpart 32.57
Fire protection, structural for ships with a keel laying date on
or after January 1, 1975...................................Subpart 32.56
Fire station....................................................34.10-10
Fitting and piping for liquefied petroleum gases................38.10-10
Fittings, cargo............................................Subpart 32.50
Flame arresters.......................................30.10-23, 32.20-10
Flame screen...........................................30.10-25, 36.20-1
Flammable liquid, definition....................................30.10-22
Flammable liquid and gas fuels as ships' stores.................35.30-40
Flammable or inflammable, definition............................30.10.21
Flashpoint, definition..........................................30.10-27
Foam hose/monitor stations......................................35.40-17
Fresh air breathing apparatus.........................35.30-20, 35.40-20
Fuel oil, requirements..........................................35.25-10
Fuels, flammable liquid and gas.................................35.30-40
Functions, assignment of.........................................30.01-3
G
Galley fires, safety rules.......................................35.30-5
[[Page 518]]
Gangway signs....................................................35.30-1
Gas chemist certified by American Bureau of Shipping.............35.01-1
Gas free, definition............................................30.10-29
Gauge, liquid level..........................32.20-20, 38.10-20, 39.20-3
Gear, shipboard cargo, certificates or registers.........31.10-16, 31.37
General alarm switch, marking of.................................35.40-1
General alarm systems:
Alarm bells for tankships constructed on or after September
15,1943..........................................................32-25-1
Alarm bells for tankships constructed prior to September 15, 1943
32.25
Alarm bells for manned barges......................................32.25
General rules and regulations...................................30.10-31
Grade D, combustible liquid.....................................30.10-15
Grade E, combustible liquid.....................................30.10-15
Great Lakes.....................................................30.10-33
H
Hauling out or drydocking.......................................31.10-20
Headquarters....................................................30.10-35
Hose, cargo.....................................................32.50-30
Hospital accommodations..........................................32.40-1
Hull and cargo tank requirements:
Alternative arrangements.........................................32.63-8
Application......................................................32.63-1
Barge hull classifications.......................................32.63-5
Cargo tanks and supports........................................32.63-25
Hull structure..................................................32.63-20
Rakes and coamings..............................................32.63-10
Hull requirements...............32.60, 32.63, 32.65, 32.70, 32.75, 32.80
Hydrostatic test for cargo tanks.................................38.25-1
I
Independent cargo tanks...........32.60-30, 32.60-35, 32.65-30, 32.70-25
32.75-10
Inert gas system...........................................Subpart 32.53
Inspection:
Alternations and repairs........................................31.10-25
Bilges..........................................................31.10-50
Certificate of.............................................Subpart 31.05
Conversion of a vessel to a tank vessel, application for........31.01-20
Crew accommodations.............................................31.10-45
During trial trip...............................................31.10-40
General requirements.......................................Subpart 31.01
Initial, scope of................................................31.01-5
Lagged tanks.....................................................36.30-1
New tank vessel........................................31.01-20, 31.10-5
Plans and specifications.........................................31.10-5
Recognized classification society................................31.10-1
Required.........................................................31.01-1
Required before making repairs...................................35.01-1
Required, liquefied, petroleum gas tanks.........................38.25-1
Required on new tank vessels.....................................31.01-1
Safety valves...................................................38.25-10
Two years.............................................31.10-15, 31.10-17
Inspection and certification of cargo gear......................31.10-16
Inspection and test, periodic, of independent cargo tanks..........38.25
Inspection of cargo gear:
Additions to gear...............................................31.37-60
[[Page 519]]
Advance notice that cargo gear testing is desired...............31.37-80
Alterations, renewals, or repairs of cargo gear.................31.37-65
Annealing.......................................................31.37-55
Cargo gear plans................................................31.37-15
Certification...................................................31.10-16
Definitions of terms.............................................31.37-3
Dismantling or disassembling.....................................31.37-3
Factors of safety...............................................31.37-25
Loose gear certificates and tests...............................31.37-30
Marking of booms and cranes.....................................31.37-45
Proof test of cargo gear as a unit..............................31.37-40
Records.........................................................31.37-75
Responsibility for conducting required tests and examinations...31.37-85
Responsibility of ship's officer for inspection of cargo gear...31.37-70
Safe working load................................................31.37-3
Tests and examinations of shipboard cargo gear...................31.37-5
Thorough examination.............................................31.37-3
Ton..............................................................31.37-3
When made........................................................31.37-1
Installation of cargo tanks.....................................38.05-10
Installation of internal combustion engines......................32.35-5
Installations made during the Unlimited National Emergency.......32.20-1
Internal combustion installations, fire extinguishing systems....34.05-5
International voyage.............................................30.01-6
Interior communications system:
Bell signals between engineroom and pilothouse...................32.30-5
Inspection of......................................................32.30
Telegraph systems..................................................32.30
Telephone equipment..............................................32.30-1
Voice tubes......................................................32.30-1
Issuance of certificates of inspection...........................31.05-1
L
Lagging for independent cargo tanks.............................38.05-20
Lakes, bays and sounds..........................................30.10-41
Lamp and paintrooms:
Fire extinguishing system for....................................34.05-5
Fireproofing of..................................................32.85-1
Licensed officers required.......................................31.15-1
Lifeboat drills..................................................35.10-5
Lifesaving Appliances and Approaches.......................Subpart 31.36
Actions to be required..........................................35.07-10
Certificate of inspection regulation.............................31.05-1
Drills...........................................................35.10-1
Inspections required.............................................31.01-1
Musters..........................................................35.10-5
Lights, flashing the ray of.....................................35.20-30
Light List.......................................................35.20-1
Liquid, flammable...............................................30.10-22
Liquid level gauging devices.........32.20-20, 38.10-1, 38.10-20 39.20-3
Liquefied flammable gas.........................................30.10-39
Cargo hose.......................................................38.15-5
Cargo piping....................................................38.10-10
Certificate of inspection........................................38.01-5
Design and construction of cargo tanks...........................38.05-2
Design and construction of nonpressure vessel type cargo tanks...38.05-4
Design and construction of pressure vessel type cargo tanks......38.05-3
[[Page 520]]
Design and construction of vessels, general......................38.05-1
Electrical installations........................................38.15-15
Filling and discharge pipes......................................38.10-5
Filling of tanks.................................................38.15-1
Installation of cargo tanks.....................................38.05-10
Insulation......................................................38.05-20
Leak detection systems..........................................38.15-10
Liquid level gauging devices....................................38.10-20
Markings.........................................................38.05-5
Refrigerated systems............................................38.05-25
Remote shutdowns................................................38.15-20
Removal of defective tanks.......................................38.25-5
Safety relief valves............................................38.25-10
Safety relief valves for pressure vessel type tanks.............38.10-15
Scope of regulations.............................................38.01-1
Tests and inspections............................................38.25-1
Transportation of................................................Part 38
Transportation of portable cylinders or portable tanks containing
or having previously contained liquefied flammable gases in dry
cargo spaces.....................................................38.01-2
Valves, fittings, and accessories................................38.10-1
Vapor control system.............................................Part 39
Ventilation.....................................................38.20-10
Venting.................................................38.20-1, 38.20-5
Living quarters.......................................32.60-25, 32.65-25
Load lines.................................................Subpart 31.25
Loading information.............................................31.10-32
Logbook entries:
Actions required to be logged...................................35.07-10
Application......................................................35.07-1
Draft of tank ship...............................................35.20-5
Fire and lifeboat drills.........................................35.10-5
Fuel oil requirements...........................................35.25-10
Logbooks and records.............................................35.07-5
Steering gear tests.............................................35.20-10
M
Machinery spaces, fire extinguishing systems for.................34.05-5
Machinery, main and auxiliary:
Accident report by chief engineer................................35.25-5
Air compressors.................................................32.35-15
Construction.....................................................32.35-1
Design...........................................................32.35-1
Examination by engineer..........................................32.25-1
Installation of internal combustion engines......................32.35-5
Steering apparatus..............................................32.35-10
Maneuvering characteristics, display of.........................35.20-40
Manning:
Tank vessels..............................................31.15, 35.35-1
Marine engineering and material specifications.............Subpart 31.30
Marine inspector, authority of..................................31.01-10
Markings:
Booms and cranes................................................31.37-45
CO2 alarm.............................................35.40-7
Draft marks......................................................32.05-1
Emergency breathing apparatus...................................35.40-20
Emergency lights.................................................35.40-6
[[Page 521]]
Fire and emergency equipment...............................Subpart 35.40
Firehose stations...............................................35.40-15
General alarm bell...............................................35.40-5
General alarm bell switch........................................35.40-1
Lifesaving equipment............................................35.40-40
Portable fire extinguishers.....................................35.40-25
Steam, foam or CO2 apparatus.........................35.40-10
Steering station................................................35.40-35
Tanks for liquefied flammable gas, marking of....................38.05-5
Vapor control system piping......................................39.20-1
Vessel's name.........................................32.05-10, 32.05-15
Vessel's name on equipment.......................................32.05-5
Master:
Casualty or accident report......................................35.15-1
Licensed officer.................................................35.05-1
Station bills and muster list...........................35.10-1, 35.10-5
Master's and officer's responsibility...........................35.20-20
Matches:
Use of...........................................................35.30-5
Materials specification....................................Subpart 31.30
Material, scantlings and workmanship....................32.60-1, 32.65-1
Means of escape..................................................32.02-1
Muster list.............................................35.10-1, 35.10-5
N
Nautical publications............................................35.20-1
Navigation, use of Auto Pilot...................................35.20-45
Navigation equipment:
Anchors for seagoing barges.....................................32.15-15
Magnetic compass and gyro compass...............................32.15-35
Radar...........................................................32.15-30
Sounding machines...............................................32.15-10
Whistles.........................................................32.15-5
New tank vessels, inspection of..................................31.10-5
New tank vessels, plans for inspection of.....................31.10-5(a)
Notice to mariners...............................................35.20-1
O
Ocean, definition...............................................30.10-45
Officer in Charge, Marine Inspection............................30.10-47
Officers required on tank vessels..........................Subpart 35.05
Open hopper type barges.........................................35.01-45
Overfill protection, liquid, tank barge..........................39.20-9
Overfill protection, liquid, tank ship...........................39.20-7
Overpressure and vacuum protection, vapor, tank barge and ship
39.20-11
Oxygen breathing apparatus, marking of..........................35.40-20
P
Paintrooms......................................Subparts 32.85, 34.05-05
Penalties for violations of regulations.........................30.20-10
Period covered by certificate of inspection.....................31.05-10
Permit definition...............................................30.10-49
Permit to proceed to another port for repairs...................31.10-35
Piping:
Fire extinguishing systems.......34.10-10, 34.10-15, 34.10-90, 34.15-15,
34.17-15, 34.20-15, 34.25-15
[[Page 522]]
Piping, bilge....................................................32.52-5
Piping, cargo..............................................Subpart 32.50
Cargo tanks.....................................................38.10-10
Steering apparatus..............................................32.35-10
Placard of lifesaving signals and breeches buoy instructions.....Subpart
35.12
Application......................................................35.12-1
Availability.....................................................35.12-5
Plans, Display of................................................35.10-3
Plans for inspection of new tank vessels......................31.10-5(a)
Portable and semiportable extinguishers..................34.05-10, 34.50
Portable tanks-interpretive rulings.............................30.01-20
Portable electrical equipment...................................35.30-30
Posting of certificate of inspection.............................31.05-5
Pressure-vacuum relief valve...........................30.10-55, 32.20-5
Prevention of oil pollution.....................................35.01-40
Proof test of cargo gear as a unit..............................31.37-40
Protection for personnel........................................36.05-10
Pumprooms:
Electrical installations........................................32.60-20
Fire extinguishing systems for...................................34.05-5
Lighting........................................................32.60-20
Location of...........................................32.60-20, 32.65-20
Requirements for......................................32.70-15, 32.70-20
Ventilation............................................32.60-20, 36.20-5
Pumps, bilge...........................................32.60-20, 36.20-5
Pumps, cargo.....................................................32.52-1
Q
Quarters, living......................................32.60-25, 32.65-25
R
Radar...........................................................32.15-30
Radio room warning signs.........................................35.30-1
Recognized classification society, definition...................30.10-57
Refrigerated systems............................................38.05-25
Registers regarding shipboard cargo gear.........31.10-16, Subpart 31-37
Regulations:
Application of...................................................30.01-5
Authority vested in Commandant...................................30.01-1
Effective date..................................................30.01-15
Explanation of vessel description................................30.01-5
Governing alterations and repairs...............................30.01-10
Liquefied flammable gas..........................................Part 38
Scope of.........................................................36.01-1
Vapor control system.............................................Part 39
Reid vapor pressure, definition.................................30.10-59
Reinspection....................................................31.10-17
Relief valves:
Cargo pump.......................................................36.10-1
Cargo pump, testing of..........................................35.35-70
Cargo tanks.....................................................38.10-15
Repairs:
Application of regulations......................................30.01-10
Firefighting equipment..........................................35.01-35
Inspection before making.........................................35.01-1
Involving hot work...............................................35.01-1
Permit to proceed to another port...............................31.10-35
[[Page 523]]
Reports of engineers.............................................35.25-5
Right of appeal.................................................30.20-50
Rivers, definition..............................................30.10-61
Rudder:
Indicators......................................................35.40-35
S
Safety radio certificate........................................31.40-15
Safety requirements:
Means of escape..................................................32.02-1
Safety relief valves for cargo tanks............................38.10-15
Safety rules...............................................Subpart 35.30
Safety valve seal, breaking of..................................35.25-20
Sailing directions...............................................35.20-1
Sanitary inspection by master and chief engineer.................35.01-5
Scantlings, material and workmanship....................32.60-1, 32.65-5
Scuppers, closing of............................................35.35-10
Sea chests, examination of......................................31.10-20
Sea strainers, examination of...................................31.10-20
Sea valves, closing of..........................................35.35-10
Segregation of spaces containing the emergency source of electric
power...........................................................32.60-45
Shipboard cargo gear, certificates or registers........31.10-16, Subpart
31.37
Shipping papers required........................................35.01-10
Sleeping quarters..........................................Subpart 32.40
Smoking safety rules.............................................35.30-5
Sounding machines...............................................32.15-10
Spark arrester..................................................30.10-63
Spark producing devices.........................................35.30-35
Spray nozzles...................................................34.10-10
Specifications, material...................................Subpart 31.30
Special operating requirements.............................Subpart 35.01
Special operating requirements for tank barges carrying certain
dangerous bulk cargoes..........................................35.01-50
Stability requirements..........................................31.10-30
Station bills required...........................................35.10-1
Steam fire extinguishing systems, marking of....................35.40-10
Steam, carrying of excess.......................................35.25-15
Steam smothering system....................................Subpart 34.13
Steel hull tank vessels..............Subparts 32.70, 32.60, 32.63, 32.65
Steering apparatus on tank vessel...............................32.35-10
Steering gear, instruction for changing.........................35.40-30
Steering gear test..............................................35.20-10
Steering orders, marking........................................35.40-35
Stowage of package and general cargo............................35.35-55
Subdivision of cargo spaces............................32.60-5, 32.65-10
T
Tank barge:
Carrying bulk cargoes having dangerous characteristics in addition
to flammability and combustibility..............................35.01-50
Definition......................................................30.10-65
Watchman for....................................................35.05-15
Tankerman, definition...........................................30.10-71
Tankship:
Definition......................................................30.10-67
Licensed officers and crew.......................................35.05-1
[[Page 524]]
Tanks, portable-interpretive rulings............................30.01-20
Tank vessel:
Definition......................................................30.10-69
Laid up or dismantled............................................31.01-1
Telegraph equipment, engine order..........................Subpart 32.30
Telephone equipment, sound powered.........................Subpart 32.30
Testing of firefighting equipment...............................31.10-19
Tide tables......................................................35.20-1
Toilet facilities...............................................32.40-25
Towing vessels........................................31.15-10, 35.35-45
Trial trip inspection...........................................31.10-40
U
Ullage holes, safety rules regarding............................35.30-10
V
Valves:
Back pressure check type................................38.10-1, 38.10-5
Excess flow.............................................38.10-1, 38.10-5
Liquefied flammable gas.................................38.10-1, 38.10-5
Pressure vacuum relief.................................30.10.55, 32.20.5
Relief.............................35.35-70, 38.10-1, 38.10-10, 38.10-15
Shutoff..........................................................38.10-1
Vapor balancing:
Design and equipment for.........................................39.40-3
General requirements for.........................................39.40-1
Operational requirements for.....................................39.40-5
Vapor collection system..........................................39.20-1
Vapor control systems............................................Part 39
Applicability....................................................39.10-1
Cargo gauging system.............................................39.20-3
Definitions......................................................39.10-3
Design and equipment.......................................Subpart 39.20
General requirements.......................................Subpart 39.10
Lightering and topping-off operations with vapor balancing.......Subpart
39.40
Operational requirements.........................................39.30-1
Operations.................................................Subpart 39.30
Personnel training..............................................39.10-11
Submission of vapor control system designs......................39.10-13
Tank barge and ship vapor overpressure and vacuum protection....39.20-11
Tank barge liquid overfill protection............................39.20-9
Tankship high and low vapor pressure protection.................39.20-13
Vessel vapor processing units....................................39.10-9
Ventilation and venting:
Cargo tanks................................................Subpart 32.55
Cargo tanks, independent...................................Subpart 38.20
Cofferdams.................................................Subpart 32.55
Flame screen.....................................................36.20-1
Hold spaces.....................................................32.55-15
Pumproom.........................................................36.20-5
Tank ships with a keel laying date on or after January 1, 1975
32.55-50
Vessels coming alongside........................................35.35-42
Vessels converted to tank vessels...............................31.10-10
Vessel's name on equipment......................................35.40-40
Vessel's name.........................................32.05-10, 32.05-15
Voice tubes......................................................32.30-1
[[Page 525]]
W
Warning signals and signs........................................35.30-1
Warning signs....................................................35.30-1
Washing facilities..............................................32.40-25
Watchman for tank barge.........................................35.05-15
Water spray extinguishing systems, details.................Subpart 34-25
Application......................................................34.25-1
Capacity and arrangement.........................................34.25-5
Controls........................................................34.25-10
Installations contracted for prior to January 1, 1964...........34.25-90
Piping..........................................................34.25-15
Spray nozzles...................................................34.25-20
Water spray systems, marking of.................................35.40-18
Waters, travel permitted on................................Subpart 31.20
Welding repairs..................................................35.01-1
Whistles.........................................................32.15-5
Whistle signals for drills.......................................35.10-5
Whistling, unnecessary..........................................35.20-35
Wire rope.............................................31.37-35, 31.37-50
Work vests:
Application of...................................................35.03-1
Approved unicellular plastic foam................................35.03-5
Shipboard inspection............................................35.03-20
Shipboard stowage...............................................35.03-15
Use.............................................................35.03-10
Workmanship, material, and scantlings..................132.60-1, 32.65-5