Sec. 45.65  Excess sheer limitations.

    The decrease in freeboard allowed in Sec. 45.63 is limited as 
follows:

                                           Sheer Calculation--Table 4
----------------------------------------------------------------------------------------------------------------
                 Station                        Actual ordinate         S. M.                Product
----------------------------------------------------------------------------------------------------------------
After Half:
  AP....................................  ...........................        1  ................................
  L/6-AP................................  ...........................        3  ................................
  L/3-AP................................  ...........................        3  ................................
  Midship...............................  ...........................        1  --------------

                              Sum of Aft Products

  After Standard Sheer .2665L+26.65\1\..  ...........................  .......  --------------
  Difference: Sum-STD...................  ...........................  .......  -------------- +Excess/-
                                                                                 Deficiency
  AFT Sheer: Diff/8.....................  ...........................  .......  -------------- Excess/Deficiency
Fwd. Half:
  FP....................................  ...........................        1  ................................
  L/6-FP................................  ...........................        3  ................................
  L/3-FP................................  ...........................        3  ................................
  Midships..............................  ...........................        1  --------------

                              Sum of Fwd Products

   Fwd Standard Sheer .5330L+53.30\1\...  ...........................  .......  --------------
  Difference: Sum-STD...................  ...........................  .......  -------------- +Excess/-
                                                                                 Deficiency
  FWD Sheer: Diff/8.....................  ...........................  .......  -------------- Excess/Deficiency
----------------------------------------------------------------------------------------------------------------
\1\ L in Standard Sheer=L or 500 whichever is less.


                             Sheer Summation
Aft Sheer              --------------
Fwd Sheer              --------------
Net Sheer              --------------
Mean: Net-2                                  -------------- Excess/
                                              Deficiency


    (a) In vessels having no enclosed superstructure from 0.1 L abaft 
amidships to 0.1 L forward of amidships, no decrease is allowed.
    (b) In vessels having enclosed superstructures amidships less than 
0.1 L before and abaft amidships, the decrease must be reduced by linear 
interpolation.
    (c) If excess sheer exists in the forward half, and the after half 
is at least 75 percent of standard sheer, the full decrease is allowed. 
If the after sheer is between 50 percent and 75 percent of standard 
sheer an intermediate decrease, determined by linear interpolation, is 
allowed for the excess sheer forward. If the after sheer is 50 percent 
of standard or less, no decrease is allowed for the excess sheer 
forward.
    (d) Where an enclosed poop or forecastle is of standard height with 
greater sheer than that of the freeboard deck, or is greater than 
standard height, an addition to the sheer of the freeboard deck may be 
made using the following formula:

S=vL'/3L

Where

s=sheer credit, to be deducted from the deficiency or added to the 
excess of sheer.
v=difference between actual and standard height of superstructure at the 
end ordinate.
L'=mean enclosed length of poop or forecastle up to a maximum length of 
0.5 L.


The superstructure deck must not be less than standard height above this 
curve at any point. This curve must be used in determining the sheer 
profile for forward and after halves of the vessel.
    (e) The maximum decreased for excess sheer must be no more than 1\1/
2\ inches per 100 feet of length.
    (f) Where the deck of an enclosed superstructure has at least the 
same sheer as the exposed freeboard deck, the sheer of the enclosed 
portion of the freeboard deck cannot be taken into account.

[[Page 81]]