[Code of Federal Regulations]
[Title 46, Volume 2]
[Revised as of October 1, 2004]
From the U.S. Government Printing Office via GPO Access
[CITE: 46CFR52.05-15]

[Page 133]
 
                           TITLE 46--SHIPPING
 
   CHAPTER I--COAST GUARD, DEPARTMENT OF HOMELAND SECURITY (CONTINUED)
 
PART 52_POWER BOILERS--Table of Contents
 
      Subpart 52.05_Requirements for Boilers Fabricated by Welding
 
Sec. 52.05-15  Heat treatment (modifies PW-10).

    (a) Vessels and vessel parts shall be preheated and postweld heat 
treated in accordance with PW-38 and PW-39 of the ASME Code (reproduces 
PW-10). This includes boiler parts made of pipe material even though 
they may be nondestructively examined under Sec. 52.05-20.