                           TITLE 46--SHIPPING
 
   CHAPTER I--COAST GUARD, DEPARTMENT OF HOMELAND SECURITY (CONTINUED)
 
PART 56_PIPING SYSTEMS AND APPURTENANCES--Table of Contents
 
                          Subpart 56.01_General
 
Sec. 56.01-10  Plan approval.

    (a) Plans and specifications for new construction and major 
alterations showing the respective piping systems shall be submitted, as 
required by subpart 50.20 of this subchapter.
    (b) Piping materials and appliances, such as pipe, tubing, fittings, 
flanges, and valves, except safety valves and safety relief valves 
covered in part 162 of subchapter Q (Specifications) of this chapter, 
are not required to be specifically approved by the Commandant, but 
shall comply with the applicable requirements for materials, 
construction, markings, and testing. These materials and appliances 
shall be certified as described in part 50 of this subchapter. Drawings 
listing material specifications and showing details of welded joints for 
pressure-containing appurtenances of welded construction shall be 
submitted in accordance with paragraph (a) of this section.
    (c)(1) Prior to installation aboard ship, diagrams of the following 
systems shall be submitted for approval:
    (i) Steam and exhaust piping.
    (ii) Boiler feed and blowoff piping.
    (iii) Safety valve escape piping.
    (iv) Fuel oil service, transfer and filling piping. (Service 
includes boiler fuel and internal combustion engine fuel piping.)
    (v) Fire extinguishing systems including fire main and sprinkler 
piping, inert gas and foam.
    (vi) Bilge and ballast piping.
    (vii) Tank cleaning piping.
    (viii) Condenser circulating water piping.
    (ix) Vent, sound and overflow piping.
    (x) Sanitary drains, soil drains, deck drains, and overboard 
discharge piping.
    (xi) Internal combustion engine exhaust piping. (Refer to part 58 of 
this subchapter for requirements.)
    (xii) Cargo piping.
    (xiii) Hot water heating systems if the temperature is greater than 
121 [deg]C(250 [deg]F).
    (xiv) Compressed air piping.
    (xv) Fluid power and control systems (hydraulic, pneumatic). (Refer 
to subpart 58.30 of this subchapter for specific requirements.)
    (xvi) Lubricating oil piping.
    (xvii) Refrigeration and air conditioning piping. (Refer to part 58 
of this subchapter for specific requirements.)
    (2) Arrangement drawings of the following systems shall also be 
submitted prior to installation:
    (i) All Classes I, I-L, and II-L systems.
    (ii) All Class II firemain, foam, sprinkler, bilge and ballast, vent 
sounding and overflow systems.
    (iii) Other Class II systems only if specifically requested or 
required by regulations in this subchapter.
    (d)(1) The drawings or diagrams shall include a list of material, 
furnishing pipe diameters, wall thicknesses, design pressure, fluid 
temperature, applicable ASTM material or ANSI component specification, 
type, size, design standard, and rating of valves, flanges, and 
fittings.
    (2) Pump rated capacity and pump shutoff head shall appear on piping 
diagrams. Pump characteristic curves shall be submitted for all pumps in 
the

[[Page 177]]

firemain and foam systems. These curves need not be submitted if the 
following information is shown on the drawing:
    (i) Rated capacity and head at rated capacity.
    (ii) Shutoff head.
    (iii) Head at 150 percent rated capacity.
    (3) Standard drawings of the following fabrication details shall be 
submitted:
    (i) Welding details for piping connections.
    (ii) Welding details for nonstandard fittings (when appropriate).
    (d-1) Plans of piping for industrial systems on mobile offshore 
drilling units must be submitted under subpart 58.60 of this subchapter.
    (e) Where piping passes through watertight bulkheads and/or fire 
boundaries, plans of typical details of piping penetrations shall be 
submitted.
    (f) Arrangement drawings specified in paragraph (c)(2) of this 
section are not required if--
    (1) The location of each component for which there is a location 
requirement (i.e., shell penetration, fire station, foam monitor, etc.) 
is indicated on the piping diagram;
    (2) The diagram includes, or is accompanied by and makes reference 
to, a material schedule which describes components in sufficient detail 
to substantiate their compliance with the regulations of this 
subchapter;
    (3) A thermal stress analysis is not required; and
    (4) A dynamic analysis is neither required nor elected in lieu of 
allowable stress reduction.

[CGFR 68-82, 33 FR 18843, Dec. 18, 1968, as amended by CGFR 69-127, 35 
FR 9978, June 17, 1970; CGFR 72-59R, 37 FR 6189, Mar. 25, 1972; CGD 73-
251, 43 FR 56799, Dec. 4, 1978, CGD 77-140, 54 FR 40602, Oct. 2, 1989; 
CGD 95-012, 60 FR 48049, Sept. 18, 1995]