Sec. 74.34  Period of construction; certification of completion of construction.

    (a) Each aural and television broadcast auxiliary station authorized 
under subparts E and F of this part must be in operation within 18 
months from the initial date of grant.
    (b) Each remote pickup broadcast auxiliary station authorized under 
subpart D of this part must be in operation within 12 months from the 
initial date of grant.
    (c) Failure to timely begin operation means the authorization 
terminates automatically.
    (d) Requests for extension of time may be granted upon a showing of 
good cause pursuant to Sec. 1.946(e) of this chapter.
    (e) Construction of any authorized facility or frequency must be 
completed by the date specified in the license and the Commission must 
be notified pursuant to Sec. 1.946 of this chapter.

[68 FR 12763, Mar. 17, 2003]