Sec. 32.110  Payment of subcontractors under cost-reimbursement prime 
contracts.

    If the contractor makes financing payments to a subcontractor under 
a cost-reimbursement prime contract, the contracting officer should 
accept the financing payments as reimbursable costs of the prime 
contract only under the following conditions:
    (a) The payments are made under the criteria in subpart 32.5 for 
customary progress payments based on costs, 32.202-1 for commercial item 
purchase financing, or 32.1003 for performance-based payments, as 
applicable.
    (b) If customary progress payments are made, the payments do not 
exceed the progress payment rate in 32.501-1, unless unusual progress 
payments to the subcontractor have been approved in accordance with 
32.501-2.
    (c) If customary progress payments are made, the subcontractor 
complies with the liquidation principles of 32.503-8, 32.503-9, and 
32.503-10.
    (d) If performance-based payments are made, the subcontractor 
complies with the liquidation principles of 32.1004(d).
    (e) The subcontract contains financing payments terms as prescribed 
in this part.

[65 FR 16279, Mar. 27, 2000]