Sec. 195.5  Conversion to service subject to this part.

    (a) A steel pipeline previously used in service not subject to this 
part qualifies for use under this part if the operator prepares and 
follows a written procedure to accomplish the following:
    (1) The design, construction, operation, and maintenance history of 
the pipeline must be reviewed and, where sufficient historical records 
are not available, appropriate tests must be performed to determine if 
the pipeline is in satisfactory condition for safe operation. If one or 
more of the variables necessary to verify the design pressure under 
Sec. 195.106 or to perform the testing under paragraph (a)(4) of this 
section is unknown, the design pressure may be verified and the maximum 
operating pressure determined by--
    (i) Testing the pipeline in accordance with ASME B31.8, Appendix N, 
to produce a stress equal to the yield strength; and
    (ii) Applying, to not more than 80 percent of the first pressure 
that produces a yielding, the design factor F in Sec. 195.106(a) and 
the appropriate factors in Sec. 195.106(e).
    (2) The pipeline right-of-way, all aboveground segments of the 
pipeline,

[[Page 160]]

and appropriately selected underground segments must be visually 
inspected for physical defects and operating conditions which reasonably 
could be expected to impair the strength or tightness of the pipeline.
    (3) All known unsafe defects and conditions must be corrected in 
accordance with this part.
    (4) The pipeline must be tested in accordance with subpart E of this 
part to substantiate the maximum operating pressure permitted by Sec. 
195.406.
    (b) A pipeline that qualifies for use under this section need not 
comply with the corrosion control requirements of subpart H of this part 
until 12 months after it is placed into service, notwithstanding any 
previous deadlines for compliance.
    (c) Each operator must keep for the life of the pipeline a record of 
the investigations, tests, repairs, replacements, and alterations made 
under the requirements of paragraph (a) of this section.

[Amdt. 195-22, 46 FR 38360, July 27, 1981, as amended by Amdt. 195-52, 
59 FR 33396, June 28, 1994; Amdt. 195-173, 66 FR 67004, Dec. 27, 2001]