Sec. 639.10  When may notice be extended?

    Additional notice is required when the date or schedule of dates of 
a planned plant closing or mass layoff is extended beyond the date or 
the ending date of any 14-day period announced in the original notice as 
follows:
    (a) If the postponement is for less than 60 days, the additional 
notice should be given as soon as possible to the parties identified in 
Sec. 639.6 and should include reference to the earlier notice, the date 
(or 14-day period) to which the planned action is postponed, and the 
reasons for the postponement. The notice should be given in a manner 
which will provide the information to all affected employees.
    (b) If the postponement is for 60 days or more, the additional 
notice should be treated as new notice subject to the provisions of 
Sec. Sec. 639.5, 639.6 and 639.7 of this part. Rolling notice, in the 
sense of routine periodic notice, given whether or not a plant closing 
or mass layoff is impending, and with the intent to evade the purpose of 
the Act rather than give specific notice as required by WARN, is not 
acceptable.