Sec. 972.236  HUD process for approving a conversion plan.

    Although a PHA will submit its conversion plan to HUD as part of the 
PHA Annual Plan, the conversion plan will be treated separately for 
purposes of HUD approval. A PHA needs a separate written approval from 
HUD in order to proceed with conversion. HUD anticipates that its review 
of a conversion plan will ordinarily occur within 90 days following 
submission of a complete plan by the PHA. A longer process may be 
required where HUD's initial review of the plan raises questions that 
require further discussion with the PHA. In any event, HUD will provide 
all PHAs with a preliminary response within 90 days following submission 
of a conversion plan. A lack of a HUD response within this time frame 
will constitute automatic HUD approval of the conversion plan.