[Code of Federal Regulations]
[Title 25, Volume 1]
[Revised as of April 1, 2005]
From the U.S. Government Printing Office via GPO Access
[CITE: 25CFR136.3]

[Page 358]
 
                            TITLE 25--INDIANS
 
     CHAPTER I--BUREAU OF INDIAN AFFAIRS, DEPARTMENT OF THE INTERIOR
 
PART 136_FORT HALL INDIAN IRRIGATION PROJECT, IDAHO--Table of Contents
 
Sec. 136.3  Repayment of construction costs.

    Under the terms of the contracts, the landowners agreed to repay the 
construction cost in forty (40) equal annual installments. Therefore, 
the annual per acre installment is hereby fixed at seventeen and one-
half cents (171/2 cents) per acre, due and payable on December 1st of 
each year, the first payment being due on December 1, 1955. Under 
section 4 of the repayment contracts of the landowners and the act of 
March 10, 1928 (45 Stat. 210), the charges remain a lien against the 
lands until paid.