Sec. 2.206  Requests for action under this subpart.

    (a) Any person may file a request to institute a proceeding pursuant 
to Sec. 2.202 to modify, suspend, or revoke a license, or for any other 
action as may be proper. Requests must be addressed to the Executive 
Director for Operations and must be filed either by hand delivery to the 
NRC's Offices at 11555 Rockville Pike, Rockville, Maryland;

[[Page 42]]

by mail or telegram addressed to the Executive Director for Operations, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; or by 
electronic submissions, for example, via facsimile, Electronic 
Information Exchange, e-mail, or CD-ROM. Electronic submissions must be 
made in a manner that enables the NRC to receive, read, authenticate, 
distribute, and archive the submission, and process and retrieve it a 
single page at a time. Detailed guidance on making electronic 
submissions can be obtained by visiting the NRC's Web site at http://
www.nrc.gov/site-help/eie.html, by calling (301) 415-6030, by e-mail to 
EIE@nrc.gov; or by writing the Office of the Chief Information Officer, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. The 
request must specify the action requested and set forth the facts that 
constitute the basis for the request. The Executive Director for 
Operations will refer the request to the Director of the NRC office with 
responsibility for the subject matter of the request for appropriate 
action in accordance with paragraph (b) of this section.
    (b) Within a reasonable time after a request pursuant to paragraph 
(a) of this section has been received, the Director of the NRC office 
with responsibility for the subject matter of the request shall either 
institute the requested proceeding in accordance with this subpart or 
shall advise the person who made the request in writing that no 
proceeding will be instituted in whole or in part, with respect to the 
request, and the reasons for the decision.
    (c)(1) Director's decisions under this section will be filed with 
the Office of the Secretary. Within twenty-five (25) days after the date 
of the Director's decision under this section that no proceeding will be 
instituted or other action taken in whole or in part, the Commission may 
on its own motion review that decision, in whole or in part, to 
determine if the Director has abused his discretion. This review power 
does not limit in any way either the Commission's supervisory power over 
delegated staff actions or the Commission's power to consult with the 
staff on a formal or informal basis regarding institution of proceedings 
under this section.
    (2) No petition or other request for Commission review of a 
Director's decision under this section will be entertained by the 
Commission.
    (3) The Secretary is authorized to extend the time for Commission 
review on its own motion of a Director's denial under paragraph (c) of 
this section.

[39 FR 12353, Apr. 5, 1974, as amended at 42 FR 36240, July 14, 1977; 45 
FR 73466, Nov. 5, 1980; 52 FR 31608, Aug. 21, 1987; 53 FR 43419, Oct. 
27, 1988; 64 FR 48948, Sept. 9, 1999; 68 FR 58799, Oct. 10, 2003; 69 FR 
2236, Jan. 14, 2004; 69 FR 41749, July 12, 2004]