Sec. 205.199G  Extension of time; Interim and Ancillary Orders.

    The Director of the Office of Hearings and Appeals or his designee 
may permit upon motion any document or submission referred to in this 
subpart other than appeals to FERC to be amended or withdrawn after it 
has been filed or to be filed within a time period different from that 
specified in this subpart. The Director or his designee may upon motion 
or on his own initiative issue any interim or ancillary Orders, 
reconsider any determinations, or make any rulings or determinations 
that are deemed necessary to ensure that the proceedings specified in 
this subpart are conducted in an appropriate manner and are not unduly 
delayed.