[Code of Federal Regulations]
[Title 10, Volume 3]
[Revised as of January 1, 2005]
From the U.S. Government Printing Office via GPO Access
[CITE: 10CFR420.33]

[Page 92-93]
 
                            TITLE 10--ENERGY
 
                    CHAPTER II--DEPARTMENT OF ENERGY
 
PART 420_STATE ENERGY PROGRAM--Table of Contents
 
    Subpart C_Implementation of Special Projects Financial Assistance
 
Sec. 420.33  Application requirements.

    (a) Consistent with Sec. 420.32 of this part, DOE shall set forth 
general and special project activity-specific requirements for 
applications for special

[[Page 93]]

projects financial assistance in the program guidance/solicitation.
    (b) In addition to any other requirements, all applications shall 
provide:
    (1) A detailed description of the proposed project, including the 
objectives of the project in relationship to DOE's program and the 
State's plan for carrying it out;
    (2) A detailed budget for the entire proposed period of support, 
with written justification sufficient to evaluate the itemized list of 
costs provided on the entire project; and
    (3) An implementation schedule for carrying out the project.
    (c) DOE may, subsequent to receipt of an application, request 
additional budgetary information from a State when necessary for 
clarification or to make informed preaward determinations.
    (d) DOE may return an application which does not include all 
information and documentation required by this subpart, 10 CFR part 600, 
or the program guidance/solicitation, when the nature of the omission 
precludes review of the application.

[61 FR 35895, July 8, 1996, as amended at 64 FR 46114, Aug. 24, 1999]