                            TITLE 10--ENERGY
 
                CHAPTER I--NUCLEAR REGULATORY COMMISSION
 
PART 50_DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES
--Table of Contents
 
Sec. 50.35  Issuance of construction permits.\1\

---------------------------------------------------------------------------

    \1\ The Commission may issue a provisional construction permit 
pursuant to the regulations in this part in effect on March 30, 1970, 
for any facility for which a notice of hearing on an application for a 
provisional construction permit has been published on or before that 
date.
---------------------------------------------------------------------------

    (a) When an applicant has not supplied initially all of the 
technical information required to complete the application and support 
the issuance of a construction permit which approves all proposed design 
features, the Commission may issue a construction permit if the 
Commission finds that (1) the applicant has described the proposed 
design of the facility, including, but not limited to, the principal 
architectural and engineering criteria for the design, and has 
identified the major features or components incorporated therein for the 
protection of the health and safety of the public; (2) such further 
technical or design information as may be required to complete the 
safety analysis, and which can reasonably be left for later 
consideration, will be supplied in the final safety analysis report; (3) 
safety features or components, if any, which require research and 
development have been described by the applicant and the applicant has 
identified, and there will be conducted, a research and development 
program reasonably designed to resolve any safety questions associated 
with such features or components; and that (4) on the basis of the 
foregoing, there is reasonable assurance that, (i) such safety questions 
will be satisfactorily resolved at or before the latest date stated in 
the application for completion of construction of the proposed facility, 
and (ii) taking into consideration the site criteria contained in part 
100 of this chapter, the proposed facility can be constructed and 
operated at the proposed location without undue risk to the health and 
safety of the public.
    Note: When an applicant has supplied initially all of the technical 
information required to complete the application, including the final 
design of the facility, the findings required above will be 
appropriately modified to reflect that fact.
    (b) A construction permit will constitute an authorization to the 
applicant to proceed with construction but will not constitute 
Commission approval of the safety of any design feature or specification 
unless the applicant specifically requests such approval and such 
approval is incorporated in the permit. The applicant, at his option, 
may request such approvals in the construction permit or, from time to 
time, by amendment of his construction permit. The Commission may, in 
its discretion, incorporate in any construction permit provisions 
requiring the applicant to furnish periodic reports of the progress and 
results of research and development programs designed to resolve safety 
questions.
    (c) Any construction permit will be subject to the limitation that a 
license authorizing operation of the facility will not be issued by the 
Commission until (1) the applicant has submitted to the Commission, by 
amendment to the application, the complete final safety analysis report, 
portions of which may

[[Page 723]]

be submitted and evaluated from time to time, and (2) the Commission has 
found that the final design provides reasonable assurance that the 
health and safety of the public will not be endangered by operation of 
the facility in accordance with the requirements of the license and the 
regulations in this chapter.