Sec. 50.55a  Codes and standards.

    Each operating license for a boiling or pressurized water-cooled 
nuclear power facility is subject to the conditions in paragraphs (f) 
and (g) of this section and each construction permit for a utilization 
facility is subject to

[[Page 755]]

the following conditions in addition to those specified in Sec. 50.55.
    (a)(1) Structures, systems, and components must be designed, 
fabricated, erected, constructed, tested, and inspected to quality 
standards commensurate with the importance of the safety function to be 
performed.
    (2) Systems and components of boiling and pressurized water-cooled 
nuclear power reactors must meet the requirements of the ASME Boiler and 
Pressure Vessel Code specified in paragraphs (b), (c), (d), (e), (f), 
and (g) of this section. Protection systems of nuclear power reactors of 
all types must meet the requirements specified in paragraph (h) of this 
section.
    (3) Proposed alternatives to the requirements of paragraphs (c), 
(d), (e), (f), (g), and (h) of this section or portions thereof may be 
used when authorized by the Director of the Office of Nuclear Reactor 
Regulation. The applicant shall demonstrate that:
    (i) The proposed alternatives would provide an acceptable level of 
quality and safety, or
    (ii) Compliance with the specified requirements of this section 
would result in hardship or unusual difficulty without a compensating 
increase in the level of quality and safety.
    (b) The ASME Boiler and Pressure Vessel Code and the ASME Code for 
Operation and Maintenance of Nuclear Power Plants, which are referenced 
in paragraphs (b)(1), (b)(2), and (b)(3) of this section, were approved 
for incorporation by reference by the Director of the Office of the 
Federal Register pursuant to 5 U.S.C. 552(a) and 1 CFR part 51. NRC 
Regulatory Guide 1.84, Revision 32, ``Design, Fabrication, and Materials 
Code Case Acceptability, ASME Section III'' (June 2003); NRC Regulatory 
Guide 1.147 (Revision 0--February 1981), including Revision 1 through 
Revision 13 (June 2003), ``Inservice Inspection Code Case Acceptability, 
ASME Section XI, Division 1''; and Regulatory Guide 1.192, ``Operation 
and Maintenance Code Case Acceptability, ASME OM Code'' (June 2003), 
have been approved for incorporation by reference by the Director of the 
Office of the Federal Register pursuant to 5 U.S.C. 552(a) and 1 CFR 
part 51. These regulatory guides list ASME Code cases which the NRC has 
approved in accordance with the requirements in paragraphs (b)(4), 
(b)(5), and (b)(6). Copies of the ASME Boiler and Pressure Vessel Code 
and the ASME Code for Operation and Maintenance of Nuclear Power Plants 
may be purchased from the American Society of Mechanical Engineers, 
Three Park Avenue, New York, NY 10016. Also, copies of these Codes and 
NRC Regulatory Guides 1.84, Revision 32; 1.147, through Revision 13; and 
1.192 are available for inspection and copying for a fee at the National 
Archives and Records Administration (NARA). For information on the 
availability of this material at NARA, call 202-741-6030, or go to: 
http://www.archives.gov/federal--register/code--of--federal--
regulations/ibr--locations.html, as well as the NRC Technical Library, 
Two White Flint North, 11545 Rockville Pike, Rockville, Maryland 20852-
2738. Single copies of Regulatory Guides may be obtained free of charge 
by writing the Distribution Services Section, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, or by fax to (301) 415-2289; or 
by email to DISTRIBUTION@NRC.GOV.
    (1) As used in this section, references to Section III of the ASME 
Boiler and Pressure Vessel Code refer to Section III, and include the 
1963 Edition through 1973 Winter Addenda, and the 1974 Edition (Division 
1) through the 2003 Addenda (Division 1), subject to the following 
limitations and modifications:
    (i) Section III Materials. When applying the 1992 Edition of Section 
III, licensees must apply the 1992 Edition with the 1992 Addenda of 
Section II of the ASME Boiler and Pressure Vessel Code.
    (ii) Weld leg dimensions. When applying the 1989 Addenda through the 
latest edition and addenda incorporated by reference in paragraph (b)(1) 
of this section, licensees may not apply paragraph NB-3683.4(c)(1), the 
footnote to circumferential fillet welded and socket welded joints in 
Figure NC-3673.2(b)-1 that permit a socket weld leg dimension to be less 
than 1.09 of the nominal wall thickness of the pipe or the footnote to 
circumferential fillet welded and socket welded joints in figure ND-
3673.2(b)-1 that permit a socket weld

[[Page 756]]

leg dimension to be less than 1.09 of the nominal wall thickness of the 
pipe.
    (iii) Seismic design. Licensees may use Articles NB-3200, NB-3600, 
NC-3600, and ND-3600 up to and including the 1993 Addenda, subject to 
the limitation specified in paragraph (b)(1)(ii) of this section. 
Licensees may not use these Articles in the 1994 Addenda through the 
latest edition and addenda incorporated by reference in paragraph (b)(1) 
of this section.
    (iv) Quality assurance. When applying editions and addenda later 
than the 1989 Edition of Section III, the requirements of NQA-1, 
``Quality Assurance Requirements for Nuclear Facilities,'' 1986 Edition 
through the 1992 Edition, are acceptable for use provided that the 
edition and addenda of NQA-1 specified in NCA-4000 is used in 
conjunction with the administrative, quality, and technical provisions 
contained in the edition and addenda of Section III being used.
    (v) Independence of inspection. Licensees may not apply NCA-
4134.10(a) of Section III, 1995 Edition through the latest edition and 
addenda incorporated by reference in paragraph (b)(1) of this section.
    (vi) Subsection NH. The provisions in Subsection NH, ``Class 1 
Components in Elevated Temperature Service,'' 1995 Addenda through the 
latest edition and addenda incorporated by reference in paragraph (b)(1) 
of this section, may only be used for the design and construction of 
Type 316 stainless steel pressurizer heater sleeves where service 
conditions do not cause the component to reach temperatures exceeding 
900 [deg]F.
    (2) As used in this section, references to Section XI of the ASME 
Boiler and Pressure Vessel Code refer to Section XI, and include the 
1970 Edition through the 1976 Winter Addenda, and the 1977 Edition 
(Division 1) through the 2003 Addenda (Division 1), subject to the 
following limitations and modifications:\10\
    (i) Limitations on specific editions and addenda. When applying the 
1974 Edition, only the addenda through the Summer 1975 Addenda may be 
used. When applying the 1977 Edition, all of the addenda through the 
Summer 1978 Addenda must also be used. Addenda and editions subsequent 
to the Summer 1978 Addenda, that are incorporated by reference in 
paragraph (b)(2) of this section are not affected by these limitations.
    (ii) Pressure-retaining welds in ASME Code Class 1 piping (applies 
to Table IWB-2500 and IWB-2500-1 and Category B-J). If the facility's 
application for a construction permit was docketed prior to July 1, 
1978, the extent of examination for Code Class 1 pipe welds may be 
determined by the requirements of Table IWB-2500 and Table IWB-2600 
Category B-J of Section XI of the ASME Code in the 1974 Edition and 
addenda through the Summer 1975 Addenda or other requirements the 
Commission may adopt.
    (iii) Steam generator tubing (modifies Article IWB-2000). If the 
technical specifications of a nuclear power plant include surveillance 
requirements for steam generators different than those in Article IWB-
2000, the inservice inspection program for steam generator tubing is 
governed by the requirements in the technical specifications.
    (iv) Pressure-retaining welds in ASME Code Class 2 piping (applies 
to Tables IWC-2520 or IWC-2520-1, Category C-F). (A) Appropriate Code 
Class 2 pipe welds in Residual Heat Removal Systems, Emergency Core 
Cooling Systems, and Containment Heat Removal Systems, must be examined. 
When applying editions and addenda up to the 1983 Edition through the 
Summer 1983 Addenda of section XI of the ASME Code, the extent of 
examination for these systems must be determined by the requirements of 
paragraph IWC-1220, Table IWC-2520 Category C-F and C-G, and paragraph 
IWC-2411 in the 1974 Edition and Addenda through the Summer 1975 
Addenda.
    (B) For a nuclear power plant whose application for a construction 
permit was docketed prior to July 1, 1978, when applying editions and 
addenda up to the 1983 Edition through the Summer 1983 Addenda of 
section XI of the ASME Code, the extent of examination for Code Class 2 
pipe welds may be determined by the requirements of paragraph IWC-1220, 
Table IWC-2520 Category C-F and C-G and paragraph IWC-2411 in the 1974 
Edition and Addenda through the Summer 1975 Addenda of

[[Page 757]]

Section XI of the ASME Code or other requirements the Commission may 
adopt.
    (v) Evaluation procedures and acceptance criteria for austenitic 
piping (applies to IWB-3640). When applying the Winter 1983 Addenda and 
Winter 1984 Addenda, the rules of paragraph IWB-3640 may be used for all 
applications permitted in that paragraph, except those associated with 
submerged arc welds (SAW) or shielded metal arc welds (SMAW). For SAW or 
SMAW, use paragraph IWB-3640, as modified by the Winter 1985 Addenda.
    (vi) Effective edition and addenda of Subsection IWE and Subsection 
IWL, Section XI. Licensees may use either the 1992 Edition with the 1992 
Addenda or the 1995 Edition with the 1996 Addenda of Subsection IWE and 
Subsection IWL as modified and supplemented by the requirements in 
paragraphs (b)(2)(viii) and (b)(2)(ix) of this section when implementing 
the initial 120-month inspection interval for the containment inservice 
inspection requirements of this section. Successive 120-month interval 
updates must be implemented in accordance with paragraph (g)(4)(ii) of 
this section.
    (vii) Section XI References to OM Part 4, OM Part 6 and OM Part 10 
(Table IWA-1600-1). When using Table IWA-1600-1, ``Referenced Standards 
and Specifications,'' in the Section XI, Division 1, 1987 Addenda, 1988 
Addenda, or 1989 Edition, the specified ``Revision Date or Indicator'' 
for ASME/ANSI OM Part 4, ASME/ANSI Part 6, and ASME/ANSI Part 10 must be 
the OMa-1988 Addenda to the OM-1987 Edition. These requirements have 
been incorporated into the OM Code which is incorporated by reference in 
paragraph (b)(3) of this section.
    (viii) Examination of concrete containments. Licensees applying 
Subsection IWL, 1992 Edition with the 1992 Addenda, shall apply 
paragraphs (b)(2)(viii)(A) through (b)(2)(viii)(E) of this section. 
Licensees applying Subsection IWL, 1995 Edition with the 1996 Addenda, 
shall apply paragraphs (b)(2)(viii)(A), (b)(2)(viii)(D)(3), and 
(b)(2)(viii)(E) of this section. Licensees applying Subsection IWL, 1998 
Edition through the 2000 Addenda shall apply paragraphs (b)(2)(viii)(E) 
and (b)(2)(viii)(F) of this section. Licensees applying Subsection IWL, 
2001 Edition through the latest edition and addenda incorporated by 
reference in paragraph (b)(2) of this section, shall apply paragraphs 
(b)(2)(viii)(E) through (b)(2)(viii)(G) of this section.
    (A) Grease caps that are accessible must be visually examined to 
detect grease leakage or grease cap deformations. Grease caps must be 
removed for this examination when there is evidence of grease cap 
deformation that indicates deterioration of anchorage hardware.
    (B) When evaluation of consecutive surveillances of prestressing 
forces for the same tendon or tendons in a group indicates a trend of 
prestress loss such that the tendon force(s) would be less than the 
minimum design prestress requirements before the next inspection 
interval, an evaluation must be performed and reported in the 
Engineering Evaluation Report as prescribed in IWL-3300.
    (C) When the elongation corresponding to a specific load (adjusted 
for effective wires or strands) during retensioning of tendons differs 
by more than 10 percent from that recorded during the last measurement, 
an evaluation must be performed to determine whether the difference is 
related to wire failures or slip of wires in anchorage. A difference of 
more than 10 percent must be identified in the ISI Summary Report 
required by IWA-6000.
    (D) The licensee shall report the following conditions, if they 
occur, in the ISI Summary Report required by IWA-6000:
    (1) The sampled sheathing filler grease contains chemically combined 
water exceeding 10 percent by weight or the presence of free water;
    (2) The absolute difference between the amount removed and the 
amount replaced exceeds 10 percent of the tendon net duct volume;
    (3) Grease leakage is detected during general visual examination of 
the containment surface.
    (E) For Class CC applications, the licensee shall evaluate the 
acceptability of inaccessible areas when conditions exist in accessible 
areas that could indicate the presence of or result in degradation to 
such inaccessible areas.

[[Page 758]]

For each inaccessible area identified, the licensee shall provide the 
following in the ISI Summary Report required by IWA-6000:
    (1) A description of the type and estimated extent of degradation, 
and the conditions that led to the degradation;
    (2) An evaluation of each area, and the result of the evaluation, 
and;
    (3) A description of necessary corrective actions.
    (F) Personnel that examine containment concrete surfaces and tendon 
hardware, wires, or strands must meet the qualification provisions in 
IWA-2300. The ``owner-defined'' personnel qualification provisions in 
IWL-2310(d) are not approved for use.
    (G) Corrosion protection material must be restored following 
concrete containment post-tensioning system repair and replacement 
activities in accordance with the quality assurance program requirements 
specified in IWA-1400.
    (ix) Examination of metal containments and the liners of concrete 
containments. Licensees applying Subsection IWE, 1992 Edition with the 
1992 Addenda, or the 1995 Edition with the 1996 Addenda, shall satisfy 
the requirements of paragraphs (b)(2)(ix)(A) through (b)(2)(ix)(E) of 
this section. Licensees applying Subsection IWE, 1998 Edition through 
the latest edition and addenda incorporated by reference in paragraph 
(b)(2) of this section, shall satisfy the requirements of paragraphs 
(b)(2)(ix)(A), (b)(2)(ix)(B), and (b)(2)(ix)(F) through (b)(2)(ix)(I) of 
this section.
    (A) For Class MC applications, the licensee shall evaluate the 
acceptability of inaccessible areas when conditions exist in accessible 
areas that could indicate the presence of or result in degradation to 
such inaccessible areas. For each inaccessible area identified, the 
licensee shall provide the following in the ISI Summary Report as 
required by IWA-6000:
    (1) A description of the type and estimated extent of degradation, 
and the conditions that led to the degradation;
    (2) An evaluation of each area, and the result of the evaluation, 
and;
    (3) A description of necessary corrective actions.
    (B) When performing remotely the visual examinations required by 
Subsection IWE, the maximum direct examination distance specified in 
Table IWA-2210-1 may be extended and the minimum illumination 
requirements specified in Table IWA-2210-1 may be decreased provided 
that the conditions or indications for which the visual examination is 
performed can be detected at the chosen distance and illumination.
    (C) The examinations specified in Examination Category E-B, Pressure 
Retaining Welds, and Examination Category E-F, Pressure Retaining 
Dissimilar Metal Welds, are optional.
    (D) Section 50.55a(b)(2)(ix)(D) may be used as an alternative to the 
requirements of IWE-2430.
    (1) If the examinations reveal flaws or areas of degradation 
exceeding the acceptance standards of Table IWE-3410-1, an evaluation 
must be performed to determine whether additional component examinations 
are required. For each flaw or area of degradation identified which 
exceeds acceptance standards, the licensee shall provide the following 
in the ISI Summary Report required by IWA-6000:
    (i) A description of each flaw or area, including the extent of 
degradation, and the conditions that led to the degradation;
    (ii) The acceptability of each flaw or area, and the need for 
additional examinations to verify that similar degradation does not 
exist in similar components, and;
    (iii) A description of necessary corrective actions.
    (2) The number and type of additional examinations to ensure 
detection of similar degradation in similar components.
    (E) A general visual examination as required by Subsection IWE must 
be performed once each period.
    (F) VT-1 and VT-3 examinations must be conducted in accordance with 
IWA-2200. Personnel conducting examinations in accordance with the VT-1 
or VT-3 examination method shall be qualified in accordance with IWA-
2300. The ``owner-defined'' personnel qualification provisions in IWE-
2330(a) for personnel that conduct VT-1 and VT-3 examinations are not 
approved for use.

[[Page 759]]

    (G) The VT-3 examination method must be used to conduct the 
examinations in Items E1.12 and E1.20 of Table IWE-2500-1, and the VT-1 
examination method must be used to conduct the examination in Item E4.11 
of Table IWE-2500-1. An examination of the pressure-retaining bolted 
connections in Item E1.11 of Table IWE-2500-1 using the VT-3 examination 
method must be conducted once each interval. The ``owner-defined'' 
visual examination provisions in IWE-2310(a) are not approved for use 
for VT-1 and VT-3 examinations.
    (H) Containment bolted connections that are disassembled during the 
scheduled performance of the examinations in Item E1.11 of Table IWE-
2500-1 must be examined using the VT-3 examination method. Flaws or 
degradation identified during the performance of a VT-3 examination must 
be examined in accordance with the VT-1 examination method. The criteria 
in the material specification or IWB-3517.1 must be used to evaluate 
containment bolting flaws or degradation. As an alternative to 
performing VT-3 examinations of containment bolted connections that are 
disassembled during the scheduled performance of Item E1.11, VT-3 
examinations of containment bolted connections may be conducted whenever 
containment bolted connections are disassembled for any reason.
    (I) The ultrasonic examination acceptance standard specified in IWE-
3511.3 for Class MC pressure-retaining components must also be applied 
to metallic liners of Class CC pressure-retaining components.
    (x) Quality Assurance. When applying Section XI editions and addenda 
later than the 1989 Edition, the requirements of NQA-1, ``Quality 
Assurance Requirements for Nuclear Facilities,'' 1979 Addenda through 
the 1989 Edition, are acceptable as permitted by IWA-1400 of Section XI, 
if the licensee uses its 10 CFR Part 50, Appendix B, quality assurance 
program, in conjunction with Section XI requirements. Commitments 
contained in the licensee's quality assurance program description that 
are more stringent than those contained in NQA-1 must govern Section XI 
activities. Further, where NQA-1 and Section XI do not address the 
commitments contained in the licensee's Appendix B quality assurance 
program description, the commitments must be applied to Section XI 
activities.
    (xi) Class 1 piping. Licensees may not apply IWB-1220, ``Components 
Exempt from Examination,'' of Section XI, 1989 Addenda through the 
latest edition and addenda incorporated by reference in paragraph (b)(2) 
of this section, and shall apply IWB-1220, 1989 Edition.
    (xii) Underwater Welding. The provisions in IWA-4660, ``Underwater 
Welding,'' of Section XI, 1997 Addenda through the latest edition and 
addenda incorporated by reference in paragraph (b)(2) of this section, 
are not approved for use on irradiated material.
    (xiii) Mechanical clamping devices. Licensees may use the provisions 
of Code Case N-523-1, ``Mechanical Clamping Devices for Class 2 and 3 
Piping.'' Licensee choosing to apply Code Case N-523-1 shall apply all 
of its provisions.
    (xiv) Appendix VIII personnel qualification. All personnel qualified 
for performing ultrasonic examinations in accordance with Appendix VIII 
shall receive 8 hours of annual hands-on training on specimens that 
contain cracks. Licensees applying the 1999 Addenda through the latest 
edition and addenda incorporated by reference in paragraph (b)(2) of 
this section may use the annual practice requirements in VII-4240 of 
Appendix VII of Section XI in place of the 8 hours of annual hands-on 
training provided that the supplemental practice is performed on 
material or welds that contain cracks, or by analyzing prerecorded data 
from material or welds that contain cracks. In either case, training 
must be completed no earlier than 6 months prior to performing 
ultrasonic examinations at a licensee's facility.
    (xv) Appendix VIII specimen set and qualification requirements. The 
following provisions may be used to modify implementation of Appendix 
VIII of Section XI, 1995 Edition through the 2001 Edition. Licensees 
choosing to apply these provisions shall apply all of the following 
provisions under this paragraph except for those in Sec. 
50.55a(b)(2)(xv)(F) which are optional.
    (A) When applying Supplements 2, 3, and 10 to Appendix VIII, the 
following

[[Page 760]]

examination coverage criteria requirements must be used:
    (1) Piping must be examined in two axial directions, and when 
examination in the circumferential direction is required, the 
circumferential examination must be performed in two directions, 
provided access is available. Dissimilar metal welds must be examined 
axially and circumferentially.
    (2) Where examination from both sides is not possible, full coverage 
credit may be claimed from a single side for ferritic welds. Where 
examination from both sides is not possible on austenitic welds or 
dissimilar metal welds, full coverage credit from a single side may be 
claimed only after completing a successful single-sided Appendix VIII 
demonstration using flaws on the opposite side of the weld. Dissimilar 
metal weld qualifications must be demonstrated from the austenitic side 
of the weld and may be used to perform examinations from either side of 
the weld.
    (B) The following provisions must be used in addition to the 
requirements of Supplement 4 to Appendix VIII:
    (1) Paragraph 3.1, Detection acceptance criteria--Personnel are 
qualified for detection if the results of the performance demonstration 
satisfy the detection requirements of ASME Section XI, Appendix VIII, 
Table VIII-S4-1 and no flaw greater than 0.25 inch through wall 
dimension is missed.
    (2) Paragraph 1.1(c), Detection test matrix--Flaws smaller than the 
50 percent of allowable flaw size, as defined in IWB-3500, need not be 
included as detection flaws. For procedures applied from the inside 
surface, use the minimum thickness specified in the scope of the 
procedure to calculate a/t. For procedures applied from the outside 
surface, the actual thickness of the test specimen is to be used to 
calculate a/t.
    (C) When applying Supplement 4 to Appendix VIII, the following 
provisions must be used:
    (1) A depth sizing requirement of 0.15 inch RMS must be used in lieu 
of the requirements in Subparagraphs 3.2(a) and 3.2(c), and a length 
sizing requirement of 0.75 inch RMS must be used in lieu of the 
requirement in Subparagraph 3.2(b).
    (2) In lieu of the location acceptance criteria requirements of 
Subparagraph 2.1(b), a flaw will be considered detected when reported 
within 1.0 inch or 10 percent of the metal path to the flaw, whichever 
is greater, of its true location in the X and Y directions.
    (3) In lieu of the flaw type requirements of Subparagraph 1.1(e)(1), 
a minimum of 70 percent of the flaws in the detection and sizing tests 
shall be cracks. Notches, if used, must be limited by the following:
    (i) Notches must be limited to the case where examinations are 
performed from the clad surface.
    (ii) Notches must be semielliptical with a tip width of less than or 
equal to 0.010 inches.
    (iii) Notches must be perpendicular to the surface within  2 degrees.
    (4) In lieu of the detection test matrix requirements in paragraphs 
1.1(e)(2) and 1.1(e)(3), personnel demonstration test sets must contain 
a representative distribution of flaw orientations, sizes, and 
locations.
    (D) The following provisions must be used in addition to the 
requirements of Supplement 6 to Appendix VIII:
    (1) Paragraph 3.1, Detection Acceptance Criteria--Personnel are 
qualified for detection if:
    (i) No surface connected flaw greater than 0.25 inch through wall 
has been missed.
    (ii) No embedded flaw greater than 0.50 inch through wall has been 
missed.
    (2) Paragraph 3.1, Detection Acceptance Criteria--For procedure 
qualification, all flaws within the scope of the procedure are detected.
    (3) Paragraph 1.1(b) for detection and sizing test flaws and 
locations--Flaws smaller than the 50 percent of allowable flaw size, as 
defined in IWB-3500, need not be included as detection flaws. Flaws 
which are less than the allowable flaw size, as defined in IWB-3500, may 
be used as detection and sizing flaws.
    (4) Notches are not permitted.
    (E) When applying Supplement 6 to Appendix VIII, the following 
provisions must be used:
    (1) A depth sizing requirement of 0.25 inch RMS must be used in lieu 
of the requirements of subparagraphs 3.2(a), 3.2(c)(2), and 3.2(c)(3).

[[Page 761]]

    (2) In lieu of the location acceptance criteria requirements in 
Subparagraph 2.1(b), a flaw will be considered detected when reported 
within 1.0 inch or 10 percent of the metal path to the flaw, whichever 
is greater, of its true location in the X and Y directions.
    (3) In lieu of the length sizing criteria requirements of 
Subparagraph 3.2(b), a length sizing acceptance criteria of 0.75 inch 
RMS must be used.
    (4) In lieu of the detection specimen requirements in Subparagraph 
1.1(e)(1), a minimum of 55 percent of the flaws must be cracks. The 
remaining flaws may be cracks or fabrication type flaws, such as slag 
and lack of fusion. The use of notches is not allowed.
    (5) In lieu of paragraphs 1.1(e)(2) and 1.1(e)(3) detection test 
matrix, personnel demonstration test sets must contain a representative 
distribution of flaw orientations, sizes, and locations.
    (F) The following provisions may be used for personnel qualification 
for combined Supplement 4 to Appendix VIII and Supplement 6 to Appendix 
VIII qualification. Licensees choosing to apply this combined 
qualification shall apply all of the provisions of Supplements 4 and 6 
including the following provisions:
    (1) For detection and sizing, the total number of flaws must be at 
least 10. A minimum of 5 flaws shall be from Supplement 4, and a minimum 
of 50 percent of the flaws must be from Supplement 6. At least 50 
percent of the flaws in any sizing must be cracks. Notches are not 
acceptable for Supplement 6.
    (2) Examination personnel are qualified for detection and length 
sizing when the results of any combined performance demonstration 
satisfy the acceptance criteria of Supplement 4 to Appendix VIII.
    (3) Examination personnel are qualified for depth sizing when 
Supplement 4 to Appendix VIII and Supplement 6 to Appendix VIII flaws 
are sized within the respective acceptance criteria of those 
supplements.
    (G) When applying Supplement 4 to Appendix VIII, Supplement 6 to 
Appendix VIII, or combined Supplement 4 and Supplement 6 qualification, 
the following additional provisions must be used, and examination 
coverage must include:
    (1) The clad to base metal interface, including a minimum of 15 
percent T (measured from the clad to base metal interface), shall be 
examined from four orthogonal directions using procedures and personnel 
qualified in accordance with Supplement 4 to Appendix VIII.
    (2) If the clad-to-base-metal-interface procedure demonstrates 
detectability of flaws with a tilt angle relative to the weld centerline 
of at least 45 degrees, the remainder of the examination volume is 
considered fully examined if coverage is obtained in one parallel and 
one perpendicular direction. This must be accomplished using a procedure 
and personnel qualified for single-side examination in accordance with 
Supplement 6. Subsequent examinations of this volume may be performed 
using examination techniques qualified for a tilt angle of at least 10 
degrees.
    (3) The examination volume not addressed by Sec. 
50.55a(b)(2)(xv)(G)(1) is considered fully examined if coverage is 
obtained in one parallel and one perpendicular direction, using a 
procedure and personnel qualified for single sided examination when the 
provisions of Sec. 50.55a(b)(2)(xv)(G)(2) are met.
    (H) When applying Supplement 5 to Appendix VIII, at least 50 percent 
of the flaws in the demonstration test set must be cracks and the 
maximum misorientation shall be demonstrated with cracks. Flaws in 
nozzles with bore diameters equal to or less than 4 inches may be 
notches.
    (I) When applying Supplement 5, Paragraph (a), to Appendix VIII, the 
following provision must be used in calculating the number of 
permissible false calls:
    (1) The number of false calls allowed must be D/10, with a maximum 
of 3, where D is the diameter of the nozzle.
    (J) [Reserved]
    (K) When performing nozzle-to-vessel weld examinations, the 
following provisions must be used when the requirements contained in 
Supplement 7 to Appendix VIII are applied for nozzle-to-vessel welds in 
conjunction with Supplement 4 to Appendix VIII, Supplement 6 to Appendix 
VIII, or combined Supplement 4 and Supplement 6 qualification.

[[Page 762]]

    (1) For examination of nozzle-to-vessel welds conducted from the 
bore, the following provisions are required to qualify the procedures, 
equipment, and personnel:
    (i) For detection, a minimum of four flaws in one or more full-scale 
nozzle mock-ups must be added to the test set. The specimens must comply 
with Supplement 6, paragraph 1.1, to Appendix VIII, except for flaw 
locations specified in Table VIII S6-1. Flaws may be either notches, 
fabrication flaws or cracks. Seventy-five (75) percent of the flaws must 
be cracks or fabrication flaws. Flaw locations and orientations must be 
selected from the choices shown in paragraph (b)(2)(xv)(K)(4) of this 
section, Table VIII-S7-1--Modified, with the exception that flaws in the 
outer eighty-five (85) percent of the weld need not be perpendicular to 
the weld. There may be no more than two flaws from each category, and at 
least one subsurface flaw must be included.
    (ii) For length sizing, a minimum of four flaws as in Sec. 
50.55a(b)(2)(xv)(K)(1)(i) must be included in the test set. The length 
sizing results must be added to the results of combined Supplement 4 to 
Appendix VIII and Supplement 6 to Appendix VIII. The combined results 
must meet the acceptance standards contained in Sec. 
50.55a(b)(2)(xv)(E)(3).
    (iii) For depth sizing, a minimum of four flaws as in Sec. 
50.55a(b)(2)(xv)(K)(1)(i) must be included in the test set. Their depths 
must be distributed over the ranges of Supplement 4, Paragraph 1.1, to 
Appendix VIII, for the inner 15 percent of the wall thickness and 
Supplement 6, Paragraph 1.1, to Appendix VIII, for the remainder of the 
wall thickness. The depth sizing results must be combined with the 
sizing results from Supplement 4 to Appendix VIII for the inner 15 
percent and to Supplement 6 to Appendix VIII for the remainder of the 
wall thickness. The combined results must meet the depth sizing 
acceptance criteria contained in Sec. Sec. 50.55a(b)(2)(xv)(C)(1), 
50.55a(b)(2)(xv)(E)(1), and 50.55a(b)(2)(xv)(F)(3).
    (2) For examination of reactor pressure vessel nozzle-to-vessel 
welds conducted from the inside of the vessel,
    (i) The clad to base metal interface and the adjacent examination 
volume to a minimum depth of 15 percent T (measured from the clad to 
base metal interface) must be examined from four orthogonal directions 
using a procedure and personnel qualified in accordance with Supplement 
4 to Appendix VIII as modified by Sec. Sec. 50.55a(b)(2)(xv)(B) and 
50.55a(b)(2)(xv)(C).
    (ii) When the examination volume defined in Sec. 
50.55a(b)(2)(xv)(K)(2)(i) cannot be effectively examined in all four 
directions, the examination must be augmented by examination from the 
nozzle bore using a procedure and personnel qualified in accordance with 
Sec. 50.55a(b)(2)(xv)(K)(1).
    (iii) The remainder of the examination volume not covered by Sec. 
50.55a(b)(2)(xv)(K)(2)(ii) or a combination of Sec. 
50.55a(b)(2)(xv)(K)(2)(i) and Sec. 50.55a(b)(2)(xv)(K)(2)(ii), must be 
examined from the nozzle bore using a procedure and personnel qualified 
in accordance with Sec. 50.55a(b)(2)(xv)(K)(1), or from the vessel 
shell using a procedure and personnel qualified for single sided 
examination in accordance with Supplement 6 to Appendix VIII, as 
modified by Sec. Sec. 50.55a(b)(2)(xv)(D), 50.55a(b)(2)(xv)(E), 
50.55a(b)(2)(xv)(F), and 50.55a(b)(2)(xv)(G).
    (3) For examination of reactor pressure vessel nozzle-to-shell welds 
conducted from the outside of the vessel,
    (i) The clad to base metal interface and the adjacent metal to a 
depth of 15 percent T, (measured from the clad to base metal interface) 
must be examined from one radial and two opposing circumferential 
directions using a procedure and personnel qualified in accordance with 
Supplement 4 to Appendix VIII, as modified by Sec. Sec. 
50.55a(b)(2)(xv)(B) and 50.55a(b)(2)(xv)(C), for examinations performed 
in the radial direction, and Supplement 5 to Appendix VIII, as modified 
by Sec. 50.55a(b)(2)(xv)(J), for examinations performed in the 
circumferential direction.
    (ii) The examination volume not addressed by Sec. 
50.55a(b)(2)(xv)(K)(3)(i) must be examined in a minimum of one radial 
direction using a procedure and personnel qualified for single sided 
examination in accordance with Supplement 6 to Appendix VIII, as 
modified by Sec. Sec. 50.55a(b)(2)(xv)(D),

[[Page 763]]

50.55a(b)(2)(xv)(E), 50.55a(b)(2)(xv)(F), and 50.55a(b)(2)(xv)(G).
    (4) Table VIII-S7-1, ``Flaw Locations and Orientations,'' Supplement 
7 to Appendix VIII, is modified as follows:

                        Table VIII-S7-1--Modified
------------------------------------------------------------------------
                     Flaw Locations and Orientations
-------------------------------------------------------------------------
                                                Parallel   Perpendicular
                                                 to weld      to weld
------------------------------------------------------------------------
Inner 15 percent.............................          X             X
OD Surface...................................          X   .............
Subsurface...................................          X   .............
------------------------------------------------------------------------

    (L) As a modification to the requirements of Supplement 8, 
Subparagraph 1.1(c), to Appendix VIII, notches may be located within one 
diameter of each end of the bolt or stud.
    (M) When implementing Supplement 12 to Appendix VIII, only the 
provisions related to the coordinated implementation of Supplement 3 to 
Supplement 2 performance demonstrations are to be applied.
    (xvi) Appendix VIII single side ferritic vessel and piping and 
stainless steel piping examination.
    (A) Examinations performed from one side of a ferritic vessel weld 
must be conducted with equipment, procedures, and personnel that have 
demonstrated proficiency with single side examinations. To demonstrate 
equivalency to two sided examinations, the demonstration must be 
performed to the requirements of Appendix VIII as modified by this 
paragraph and Sec. Sec. 50.55a(b)(2)(xv) (B) through (G), on specimens 
containing flaws with non-optimum sound energy reflecting 
characteristics or flaws similar to those in the vessel being examined.
    (B) Examinations performed from one side of a ferritic or stainless 
steel pipe weld must be conducted with equipment, procedures, and 
personnel that have demonstrated proficiency with single side 
examinations. To demonstrate equivalency to two sided examinations, the 
demonstration must be performed to the requirements of Appendix VIII as 
modified by this paragraph and Sec. 50.55a(b)(2)(xv)(A).
    (xvii) Reconciliation of Quality Requirements. When purchasing 
replacement items, in addition to the reconciliation provisions of IWA-
4200, 1995 Addenda through 1998 Edition, the replacement items must be 
purchased, to the extent necessary, in accordance with the licensee's 
quality assurance program description required by 10 CFR 
50.34(b)(6)(ii).
    (xviii) Certification of NDE personnel. (A) Level I and II 
nondestructive examination personnel shall be recertified on a 3-year 
interval in lieu of the 5-year interval specified in the 1997 Addenda 
and 1998 Edition of IWA-2314, and IWA-2314(a) and IWA-2314(b) of the 
1999 Addenda through the latest edition and addenda incorporated by 
reference in paragraph (b)(2) of this section.
    (B) Paragraph IWA-2316 of the 1998 Edition through the latest 
edition and addenda incorporated by reference in paragraph (b)(2) of 
this section, may only be used to qualify personnel that observe for 
leakage during system leakage and hydrostatic tests conducted in 
accordance with IWA-5211(a) and (b), 1998 Edition through the latest 
edition and addenda incorporated by reference in paragraph (b)(2) of 
this section.
    (C) When qualifying visual examination personnel for VT-3 visual 
examinations under paragraph IWA-2317 of the 1998 Edition through the 
latest edition and addenda incorporated by reference in paragraph (b)(2) 
of this section, the proficiency of the training must be demonstrated by 
administering an initial qualification examination and administering 
subsequent examinations on a 3-year interval.
    (xix) Substitution of alternative methods. The provisions for the 
substitution of alternative examination methods, a combination of 
methods, or newly developed techniques in the 1997 Addenda of IWA-2240 
must be applied. The provisions in IWA-2240, 1998 Edition through the 
latest edition and addenda incorporated by reference in paragraph (b)(2) 
of this section, are not approved for use. The provisions in IWA-
4520(c), 1997 Addenda through the latest edition and addenda 
incorporated by reference in paragraph (b)(2) of this section, allowing 
the substitution of alternative examination methods, a combination of 
methods, or newly developed techniques for the methods specified in the 
Construction Code are not approved for use.

[[Page 764]]

    (xx) System leakage tests. When performing system leakage tests in 
accordance IWA-5213(a), 1997 through 2002 Addenda, a 10-minute hold time 
after attaining test pressure is required for Class 2 and Class 3 
components that are not in use during normal operating conditions, and 
no hold time is required for the remaining Class 2 and Class 3 
components provided that the system has been in operation for at least 4 
hours for insulated components or 10 minutes for uninsulated components.
    (xxi) Table IWB-2500-1 examination requirements. (A) The provisions 
of Table IWB-2500-1, Examination Category B-D, Full Penetration Welded 
Nozzles in Vessels, Items B3.40 and B3.60 (Inspection Program A) and 
Items B3.120 and B3.140 (Inspection Program B) in the 1998 Edition must 
be applied when using the 1999 Addenda through the latest edition and 
addenda incorporated by reference in paragraph (b)(2) of this section. A 
visual examination with enhanced magnification that has a resolution 
sensitivity to detect a 1-mil width wire or crack, utilizing the 
allowable flaw length criteria in Table IWB-3512-1, 1997 Addenda through 
the latest edition and addenda incorporated by reference in paragraph 
(b)(2) of this section, may be performed in place of an ultrasonic 
examination.
    (B) The provisions of Table IWB-2500-1, Examination Category B-G-2, 
Item B7.80, that are in the 1995 Edition are applicable only to reused 
bolting when using the 1997 Addenda through the latest edition and 
addenda incorporated by reference in paragraph (b)(2) of this section.
    (C) The provisions of Table IWB-2500-1, Examination Category B-K, 
Item B10.10, of the 1995 Addenda must be applied when using the 1997 
Addenda through the latest edition and addenda incorporated by reference 
in paragraph (b)(2) of this section.
    (xxii) Surface Examination. The use of the provision in IWA-2220, 
``Surface Examination,'' of Section XI, 2001 Edition through the latest 
edition and addenda incorporated by reference in paragraph (b)(2) of 
this section, that allow use of an ultrasonic examination method is 
prohibited.
    (xxiii) Evaluation of Thermally Cut Surfaces. The use of the 
provisions for eliminating mechanical processing of thermally cut 
surfaces in IWA-4461.4.2 of Section XI, 2001 Edition through the latest 
edition and addenda incorporated by reference in paragraph (b)(2) of 
this section are prohibited.
    (xxiv) Incorporation of the Performance Demonstration Initiative and 
Addition of Ultrasonic Examination Criteria. The use of Appendix VIII 
and the supplements to Appendix VIII and Article I-3000 of Section XI of 
the ASME BPV Code, 2002 Addenda through the latest edition and addenda 
incorporated by reference in paragraph (b)(2) of this section, is 
prohibited.
    (xxv) Mitigation of Defects by Modification. The use of the 
provisions in IWA-4340, ``Mitigation of Defects by Modification,'' 
Section XI, 2001 Edition through the latest edition and addenda 
incorporated by reference in paragraph (b)(2) of this section are 
prohibited.
    (xxvi) Pressure Testing Class 1, 2, and 3 Mechanical Joints. The 
repair and replacement activity provisions in IWA-4540(c) of the 1998 
Edition of Section XI for pressure testing Class 1, 2, and 3 mechanical 
joints must be applied when using the 2001 Edition through the latest 
edition and addenda incorporated by reference in paragraph (b)(2) of 
this section.
    (xxvii) Removal of Insulation. When performing visual examinations 
in accordance with IWA-5242 of Section XI, 2003 Addenda through the 
latest edition and addenda incorporated by reference in paragraph (b)(2) 
of the section, insulation must be removed from 17-4 PH or 410 stainless 
steel studs or bolts aged at a temperature below 1100 [deg]F or having a 
Rockwell Method C hardness value above 30, and from A-286 stainless 
steel studs or bolts preloaded to 100,000 pounds per square inch or 
higher.
    (3) As used in this section, references to the OM Code refer to the 
ASME Code for Operation and Maintenance of Nuclear Power Plants, and 
include the 1995 Edition through the 2003 Addenda subject to the 
following limitations and modifications:
    (i) Quality Assurance. When applying editions and addenda of the OM 
Code, the requirements of NQA-1, ``Quality

[[Page 765]]

Assurance Requirements for Nuclear Facilities,'' 1979 Addenda, are 
acceptable as permitted by ISTA 1.4 of the 1995 Edition through 1997 
Addenda or ISTA-1500 of the 1998 Edition through the latest edition and 
addenda incorporated by reference in paragraph (b)(3) of this section, 
provided the licensee uses its 10 CFR Part 50, Appendix B, quality 
assurance program in conjunction with the OM Code requirements. 
Commitments contained in the licensee's quality assurance program 
description that are more stringent than those contained in NQA-1 govern 
OM Code activities. If NQA-1 and the OM Code do not address the 
commitments contained in the licensee's Appendix B quality assurance 
program description, the commitments must be applied to OM Code 
activities.
    (ii) Motor-Operated Valve testing. Licensees shall comply with the 
provisions for testing motor-operated valves in OM Code ISTC 4.2, 1995 
Edition with the 1996 and 1997 Addenda, or ISTC-3500, 1998 Edition 
through the latest edition and addenda incorporated by reference in 
paragraph (b)(3) of this section, and shall establish a program to 
ensure that motor-operated valves continue to be capable of performing 
their design basis safety functions.
    (iii) [Reserved]
    (iv) Appendix II. Licensees applying Appendix II, ``Check Valve 
Condition Monitoring Program,'' of the OM Code, 1995 Edition with the 
1996 and 1997 Addenda, shall satisfy the requirements of (b)(3)(iv)(A), 
(b)(3)(iv)(B), and (b)(3)(iv)(C) of this section. Licensees applying 
Appendix II, 1998 Edition through the 2002 Addenda, shall satisfy the 
requirements of (b)(3)(iv)(A), (b)(3)(iv)(B), and (b)(3)(iv)(D) of this 
section.
    (A) Valve opening and closing functions must be demonstrated when 
flow testing or examination methods (nonintrusive, or disassembly and 
inspection) are used;
    (B) The initial interval for tests and associated examinations may 
not exceed two fuel cycles or 3 years, whichever is longer; any 
extension of this interval may not exceed one fuel cycle per extension 
with the maximum interval not to exceed 10 years; trending and 
evaluation of existing data must be used to reduce or extend the time 
interval between tests.
    (C) If the Appendix II condition monitoring program is discontinued, 
then the requirements of ISTC 4.5.1 through 4.5.4 must be implemented.
    (D) The provisions of ISTC-3510, ISTC-3520, and ISTC-3540 in 
addition to ISTC-5221 must be implemented if the Appendix II condition 
monitoring program is discontinued.
    (v) Subsection ISTD. Article IWF-5000, ``Inservice Inspection 
Requirements for Snubbers,'' of the ASME BPV Code, Section XI, provides 
inservice inspection requirements for examinations and tests of snubbers 
at nuclear power plants. Licensees may use Subsection ISTD, ``Inservice 
Testing of Dynamic Restraints (Snubbers) in Light-Water Reactor Power 
Plants,'' ASME OM Code, 1995 Edition through the latest edition and 
addenda incorporated by reference in paragraph (b)(3) of this section, 
in place of the requirements for snubbers in Section XI, IWF-5200(a) and 
(b) and IWF-5300(a) and (b), by making appropriate changes to their 
technical specifications or licensee-controlled documents. Preservice 
and inservice examinations must be performed using the VT-3 visual 
examination method described in IWA-2213.
    (vi) Exercise interval for manual valves. Manual valves must be 
exercised on a 2-year interval rather that the 5-year interval specified 
in paragraph ISTC-3540 of the 1999 Addenda through the latest edition 
and addenda incorporated by reference in paragraph (b)(3) of this 
section, provided that adverse conditions do not require more frequent 
testing.
    (4) Design, Fabrication, and Materials Code Cases. Licensees may 
apply the ASME Boiler and Pressure Vessel Code cases listed in NRC 
Regulatory Guide 1.84, Revision 32, without prior NRC approval subject 
to the following:
    (i) When an applicant or licensee initially applies a listed Code 
case, the applicant or licensee shall apply the most recent version of 
that Code case incorporated by reference in this paragraph.
    (ii) If an applicant or licensee has previously applied a Code case 
and a later version of the Code case is incorporated by reference in 
this paragraph,

[[Page 766]]

the applicant or licensee may continue to apply the previous version of 
the Code case as authorized, or may apply the later version of the Code 
case, including any NRC-specified conditions placed on its use, until it 
updates its Code of Record for the component being constructed.
    (iii) Application of an annulled Code case is prohibited unless an 
applicant or licensee applied the listed Code case prior to it being 
listed as annulled in Regulatory Guide 1.84. If an applicant or licensee 
has applied a listed Code case that is later listed as annulled in 
Regulatory Guide 1.84, the applicant or licensee may continue to apply 
the Code case until it updates its Code of Record for the component 
being constructed.
    (5) Inservice Inspection Code Cases. Licensees may apply the ASME 
Boiler and Pressure Vessel Code cases listed in Regulatory Guide 1.147 
through Revision 13, without prior NRC approval subject to the 
following:
    (i) When a licensee initially applies a listed Code case, the 
licensee shall apply the most recent version of that Code case 
incorporated by reference in this paragraph.
    (ii) If a licensee has previously applied a Code case and a later 
version of the Code case is incorporated by reference in this paragraph, 
the licensee may continue to apply, to the end of the current 120-month 
interval, the previous version of the Code case as authorized or may 
apply the later version of the Code case, including any NRC-specified 
conditions placed on its use.
    (iii) Application of an annulled Code case is prohibited unless a 
licensee previously applied the listed Code case prior to it being 
listed as annulled in Regulatory Guide 1.147. Any Code case listed as 
annulled in any Revision of Regulatory Guide 1.147 which a licensee has 
applied prior to it being listed as annulled, may continue to be applied 
by that licensee to the end of the 120-month interval in which the Code 
case was implemented.
    (6) Operation and Maintenance of Nuclear Power Plants Code Cases. 
Licensees may apply the ASME Operation and Maintenance Nuclear Power 
Plants Code cases listed in Regulatory Guide 1.192 without prior NRC 
approval subject to the following:
    (i) When a licensee initially applies a listed Code case, the 
licensee shall apply the most recent version of that Code case 
incorporated by reference in this paragraph.
    (ii) If a licensee has previously applied a Code case and a later 
version of the Code case is incorporated by reference in this paragraph, 
the licensee may continue to apply, to the end of the current 120-month 
interval, the previous version of the Code case as authorized or may 
apply the later version of the Code case, including any NRC-specified 
conditions placed on its use.
    (iii) Application of an annulled Code case is prohibited unless a 
licensee previously applied the listed Code case prior to it being 
listed as annulled in Regulatory Guide 1.192. If a licensee has applied 
a listed Code case that is later listed as annulled in Regulatory Guide 
1.192, the licensee may continue to apply the Code case to the end of 
the current 120-month interval.
    (c) Reactor coolant pressure boundary. (1) Components which are part 
of the reactor coolant pressure boundary must meet the requirements for 
Class 1 components in Section III \4,5\ of the ASME Boiler and Pressure 
Vessel Code, except as provided in paragraphs (c)(2), (c)(3), and (c)(4) 
of this section.
---------------------------------------------------------------------------

    See footnotes at end of section.
---------------------------------------------------------------------------

    (2) Components which are connected to the reactor coolant system and 
are part of the reactor coolant pressure boundary as defined in Sec. 
50.2 need not meet the requirements of paragraph (c)(1) of this section, 
Provided:
    (i) In the event of postulated failure of the component during 
normal reactor operation, the reactor can be shut down and cooled down 
in an orderly manner, assuming makeup is provided by the reactor coolant 
makeup system; or
    (ii) The component is or can be isolated from the reactor coolant 
system by two valves in series (both closed, both open, or one closed 
and the other open). Each open valve must be capable of automatic 
actuation and, assuming the other valve is open, its closure time must 
be such that, in the event of postulated failure of the component

[[Page 767]]

during normal reactor operation, each valve remains operable and the 
reactor can be shut down and cooled down in an orderly manner, assuming 
makeup is provided by the reactor coolant makeup system only.
    (3) The Code edition, addenda, and optional ASME Code cases to be 
applied to components of the reactor coolant pressure boundary must be 
determined by the provisions of paragraph NCA-1140, Subsection NCA of 
Section III of the ASME Boiler and Pressure Vessel Code, but--
    (i) the edition and addenda applied to a component must be those 
which are incorporated by reference in paragraph (b)(1) of this section,
    (ii) the ASME Code provisions applied to the pressure vessel may be 
dated no earlier than the Summer 1972 Addenda of the 1971 edition,
    (iii) the ASME Code provisions applied to piping, pumps, and valves 
may be dated no earlier than the Winter 1972 Addenda of the 1971 
edition, and
    (iv) The optional Code cases applied to a component must be those 
listed in NRC Regulatory Guide 1.84 that is incorporated by reference in 
paragraph (b) of this section.
    (4) For a nuclear power plant whose construction permit was issued 
prior to May 14, 1984 the applicable Code Edition and Addenda for a 
component of the reactor coolant pressure boundary continue to be that 
Code Edition and Addenda that were required by Commission regulations 
for such component at the time of issuance of the construction permit.
    (d) Quality Group B components. (1) For a nuclear power plant whose 
application for a construction permit is docketed after May 14, 1984 
components classified Quality Group B \9\ must meet the requirements for 
Class 2 Components in Section III of the ASME Boiler and Pressure Vessel 
Code.
    (2) The Code edition, addenda, and optional ASME Code cases to be 
applied to the systems and components identified in paragraph (d)(1) of 
this section must be determined by the rules of paragraph NCA-1140, 
Subsection NCA of Section III of the ASME Boiler and Pressure Vessel 
Code, but--
    (i) the edition and addenda must be those which are incorporated by 
reference in paragraph (b)(1) of this section,
    (ii) the ASME Code provisions applied to the systems and components 
may be dated no earlier than the 1980 Edition, and
    (iii) The optional Code cases must be those listed in the NRC 
Regulatory Guide 1.84 that is incorporated by reference in paragraph (b) 
of this section.
    (e) Quality Group C components. (1) For a nuclear power plant whose 
application for a construction permit is docketed after May 14, 1984 
components classified Quality Group C \9\ must meet the requirements for 
Class 3 components in Section III of the ASME Boiler and Pressure Vessel 
Code.
    (2) The Code edition, addenda, and optional ASME Code cases to be 
applied to the systems and components identified in paragraph (e)(1) of 
this section must be determined by the rules of paragraph NCA-1140, 
subsection NCA of Section III of the ASME Boiler and Pressure Vessel 
Code, but--
    (i) the edition and addenda must be those which are incorporated by 
reference in paragraph (b)(1) of this section,
    (ii) the ASME Code provisions applied to the systems and components 
may be dated no earlier than the 1980 Edition, and
    (iii) The optional Code cases must be those listed in NRC Regulatory 
Guide 1.84 that is incorporated by reference in paragraph (b) of this 
section.
    (f) Inservice testing requirements. Requirements for inservice 
inspection of Class 1, Class 2, Class 3, Class MC, and Class CC 
components (including their supports) are located in Sec. 50.55a(g).
    (1) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued prior to January 1, 1971, pumps and 
valves must meet the test requirements of paragraphs (f)(4) and (f)(5) 
of this section to the extent practical. Pumps and valves which are part 
of the reactor coolant pressure boundary must meet the requirements 
applicable to components which are classified as ASME Code Class 1. 
Other pumps and valves that perform a function to shut down the reactor 
or maintain the reactor in a safe shutdown condition, mitigate the 
consequences of an accident, or provide

[[Page 768]]

overpressure protection for safety-related systems (in meeting the 
requirements of the 1986 Edition, or later, of the Boiler and Pressure 
Vessel or OM Code) must meet the test requirements applicable to 
components which are classified as ASME Code Class 2 or Class 3.
    (2) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued on or after January 1, 1971, but 
before July 1, 1974, pumps and valves which are classified as ASME Code 
Class 1 and Class 2 must be designed and be provided with access to 
enable the performance of inservice tests for operational readiness set 
forth in editions and addenda of Section XI of the ASME Boiler and 
Pressure Vessel Code incorporated by reference in paragraph (b) of this 
section (or the optional ASME Code cases listed in NRC Regulatory Guide 
1.147, through Revision 13, or 1.192 that are incorporated by reference 
in paragraph (b) of this section) in effect 6 months before the date of 
issuance of the construction permit. The pumps and valves may meet the 
inservice test requirements set forth in subsequent editions of this 
Code and addenda which are incorporated by reference in paragraph (b) of 
this section (or the optional ASME Code cases listed in NRC Regulatory 
Guide 1.147, through Revision 13, or 1.192 that are incorporated by 
reference in paragraph (b) of this section), subject to the applicable 
limitations and modifications listed therein.
    (3) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued on or after July 1, 1974:
    (i)-(ii) [Reserved]
    (iii)(A) Pumps and valves, in facilities whose construction permit 
was issued before November 22, 1999, which are classified as ASME Code 
Class 1 must be designed and be provided with access to enable the 
performance of inservice testing of the pumps and valves for assessing 
operational readiness set forth in the editions and addenda of Section 
XI of the ASME Boiler and Pressure Vessel Code incorporated by reference 
in paragraph (b) of this section (or the optional ASME Code cases that 
are listed in NRC Regulatory Guide 1.147, through Revision 13, that are 
incorporated by reference in paragraph (b) of this section) applied to 
the construction of the particular pump or valve or the Summer 1973 
Addenda, whichever is later.
    (B) Pumps and valves, in facilities whose construction permit is 
issued on or after November 22, 1999, which are classified as ASME Code 
Class 1 must be designed and be provided with access to enable the 
performance of inservice testing of the pumps and valves for assessing 
operational readiness set forth in editions and addenda of the ASME OM 
Code (or the optional ASME Code cases listed in NRC Regulatory Guide 
1.192 that is incorporated by reference in paragraph (b) of this 
section) referenced in paragraph (b)(3) of this section at the time the 
construction permit is issued.
    (iv)(A) Pumps and valves, in facilities whose construction permit 
was issued before November 22, 1999, which are classified as ASME Code 
Class 2 and Class 3 must be designed and be provided with access to 
enable the performance of inservice testing of the pumps and valves for 
assessing operational readiness set forth in the editions and addenda of 
Section XI of the ASME Boiler and Pressure Vessel Code incorporated by 
reference in paragraph (b) of this section (or the optional ASME Code 
cases listed in NRC Regulatory Guide 1.147, through Revision 13, that 
are incorporated by reference in paragraph (b) of this section) applied 
to the construction of the particular pump or valve or the Summer 1973 
Addenda, whichever is later.
    (B) Pumps and valves, in facilities whose construction permit is 
issued on or after November 22, 1999, which are classified as ASME Code 
Class 2 and 3 must be designed and be provided with access to enable the 
performance of inservice testing of the pumps and valves for assessing 
operational readiness set forth in editions and addenda of the ASME OM 
Code (or the optional ASME Code cases listed in the NRC Regulatory Guide 
1.192 that is incorporated by reference in paragraph (b) of this 
section) referenced in paragraph (b)(3) of this section at the time the 
construction permit is issued.

[[Page 769]]

    (v) All pumps and valves may meet the test requirements set forth in 
subsequent editions of codes and addenda or portions thereof which are 
incorporated by reference in paragraph (b) of this section, subject to 
the limitations and modifications listed in paragraph (b) of this 
section.
    (4) Throughout the service life of a boiling or pressurized water-
cooled nuclear power facility, pumps and valves which are classified as 
ASME Code Class 1, Class 2 and Class 3 must meet the inservice test 
requirements, except design and access provisions, set forth in the ASME 
OM Code and addenda that become effective subsequent to editions and 
addenda specified in paragraphs (f)(2) and (f)(3) of this section and 
that are incorporated by reference in paragraph (b) of this section, to 
the extent practical within the limitations of design, geometry and 
materials of construction of the components.
    (i) Inservice tests to verify operational readiness of pumps and 
valves, whose function is required for safety, conducted during the 
initial 120-month interval must comply with the requirements in the 
latest edition and addenda of the Code incorporated by reference in 
paragraph (b) of this section on the date 12 months before the date of 
issuance of the operating license (or the optional ASME Code cases 
listed in NRC Regulatory Guide 1.192 that is incorporated by reference 
in paragraph (b) of this section), subject to the limitations and 
modifications listed in paragraph (b) of this section.
    (ii) Inservice tests to verify operational readiness of pumps and 
valves, whose function is required for safety, conducted during 
successive 120-month intervals must comply with the requirements of the 
latest edition and addenda of the Code incorporated by reference in 
paragraph (b) of this section 12 months before the start of the 120-
month interval (or the optional ASME Code cases listed in NRC Regulatory 
Guide 1.147, through Revision 13, or 1.192 that are incorporated by 
reference in paragraph (b) of this section), subject to the limitations 
and modifications listed in paragraph (b) of this section.
    (iii) [Reserved]
    (iv) Inservice tests of pumps and valves may meet the requirements 
set forth in subsequent editions and addenda that are incorporated by 
reference in paragraph (b) of this section, subject to the limitations 
and modifications listed in paragraph (b) of this section, and subject 
to Commission approval. Portions of editions or addenda may be used 
provided that all related requirements of the respective editions or 
addenda are met.
    (5)(i) The inservice test program for a boiling or pressurized 
water-cooled nuclear power facility must be revised by the licensee, as 
necessary, to meet the requirements of paragraph (f)(4) of this section.
    (ii) If a revised inservice test program for a facility conflicts 
with the technical specification for the facility, the licensee shall 
apply to the Commission for amendment of the technical specifications to 
conform the technical specification to the revised program. The licensee 
shall submit this application, as specified in Sec. 50.4, at least 6 
months before the start of the period during which the provisions become 
applicable, as determined by paragraph (f)(4) of this section.
    (iii) If the licensee has determined that conformance with certain 
code requirements is impractical for its facility, the licensee shall 
notify the Commission and submit, as specified in Sec. 50.4, 
information to support the determination.
    (iv) Where a pump or valve test requirement by the code or addenda 
is determined to be impractical by the licensee and is not included in 
the revised inservice test program as permitted by paragraph (f)(4) of 
this section, the basis for this determination must be demonstrated to 
the satisfaction of the Commission not later than 12 months after the 
expiration of the initial 120-month period of operation from start of 
facility commercial operation and each subsequent 120-month period of 
operation during which the test is determined to be impractical.
    (6)(i) The Commission will evaluate determinations under paragraph 
(f)(5) of this section that code requirements are impractical. The 
Commission may grant relief and may impose such alternative requirements 
as it determines is

[[Page 770]]

authorized by law and will not endanger life or property or the common 
defense and security and is otherwise in the public interest giving due 
consideration to the burden upon the licensee that could result if the 
requirements were imposed on the facility.
    (ii) The Commission may require the licensee to follow an augmented 
inservice test program for pumps and valves for which the Commission 
deems that added assurance of operational readiness is necessary.
    (g) Inservice inspection requirements. Requirements for inservice 
testing of Class 1, Class 2, and Class 3 pumps and valves are located in 
Sec. 50.55a(f).
    (1) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued before January 1, 1971, components 
(including supports) must meet the requirements of paragraphs (g)(4) and 
(g)(5) of this section to the extent practical. Components which are 
part of the reactor coolant pressure boundary and their supports must 
meet the requirements applicable to components which are classified as 
ASME Code Class 1. Other safety-related pressure vessels, piping, pumps 
and valves, and their supports must meet the requirements applicable to 
components which are classified as ASME Code Class 2 or Class 3.
    (2) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued on or after January 1, 1971, but 
before July 1, 1974, components (including supports) which are 
classified as ASME Code Class 1 and Class 2 must be designed and be 
provided with access to enable the performance of inservice examination 
of such components (including supports) and must meet the preservice 
examination requirements set forth in editions and addenda of Section XI 
of the ASME Boiler and Pressure Vessel Code incorporated by reference in 
paragraph (b) of this section (or the optional ASME Code cases listed in 
NRC Regulatory Guide 1.147, through Revision 13, that are incorporated 
by reference in paragraph (b) of this section) in effect six months 
before the date of issuance of the construction permit. The components 
(including supports) may meet the requirements set forth in subsequent 
editions and addenda of this Code which are incorporated by reference in 
paragraph (b) of this section (or the optional ASME Code cases listed in 
NRC Regulatory Guide 1.147, through Revision 13, that are incorporated 
by reference in paragraph (b) of this section), subject to the 
applicable limitations and modifications.
    (3) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued on or after July 1, 1974:
    (i) Components (including supports) which are classified as ASME 
Code Class 1 must be designed and be provided with access to enable the 
performance of inservice examination of these components and must meet 
the preservice examination requirements set forth in the editions and 
addenda of Section XI of the ASME Boiler and Pressure Vessel Code 
incorporated by reference in paragraph (b) of this section (or the 
optional ASME Code cases listed in NRC Regulatory Guide 1.147, through 
Revision 13, that are incorporated by reference in paragraph (b) of this 
section) applied to the construction of the particular component.
    (ii) Components which are classified as ASME Code Class 2 and Class 
3 and supports for components which are classified as ASME Code Class 1, 
Class 2, and Class 3 must be designed and be provided with access to 
enable the performance of inservice examination of these components and 
must meet the preservice examination requirements set forth in the 
editions and addenda of Section XI of the ASME Boiler and Pressure 
Vessel Code incorporated by reference in paragraph (b) of this section 
(or the optional ASME Code cases listed in NRC Regulatory Guide 1.147, 
through Revision 13, that are incorporated by reference in paragraph (b) 
of this section) applied to the construction of the particular 
component.
    (iii)-(iv) [Reserved]
    (v) All components (including supports) may meet the requirements 
set forth in subsequent editions of codes and addenda or portions 
thereof which are incorporated by reference in paragraph (b) of this 
section, subject to the limitations and modifications listed therein.

[[Page 771]]

    (4) Throughout the service life of a boiling or pressurized water-
cooled nuclear power facility, components (including supports) which are 
classified as ASME Code Class 1, Class 2 and Class 3 must meet the 
requirements, except design and access provisions and preservice 
examination requirements, set forth in Section XI of editions of the 
ASME Boiler and Pressure Vessel Code and Addenda that become effective 
subsequent to editions specified in paragraphs (g)(2) and (g)(3) of this 
section and that are incorporated by reference in paragraph (b) of this 
section, to the extent practical within the limitations of design, 
geometry and materials of construction of the components. Components 
which are classified as Class MC pressure retaining components and their 
integral attachments, and components which are classified as Class CC 
pressure retaining components and their integral attachments must meet 
the requirements, except design and access provisions and preservice 
examination requirements, set forth in Section XI of the ASME Boiler and 
Pressure Vessel Code and Addenda that are incorporated by reference in 
paragraph (b) of this section, subject to the limitation listed in 
paragraph (b)(2)(vi) of this section and the modifications listed in 
paragraphs (b)(2)(viii) and (b)(2)(ix) of this section, to the extent 
practical within the limitation of design, geometry and materials of 
construction of the components.
    (i) Inservice examinations of components and system pressure tests 
conducted during the initial 120-month inspection interval must comply 
with the requirements in the latest edition and addenda of the Code 
incorporated by reference in paragraph (b) of this section on the date 
12 months before the date of issuance of the operating license (or the 
optional ASME Code cases listed in NRC Regulatory Guide 1.147, through 
Revision 13, that are incorporated by reference in paragraph (b) of this 
section, subject to the limitations and modifications listed in 
paragraph (b) of this section.
    (ii) Inservice examination of components and system pressure tests 
conducted during successive 120-month inspection intervals must comply 
with the requirements of the latest edition and addenda of the Code 
incorporated by reference in paragraph (b) of this section 12 months 
before the start of the 120-month inspection interval (or the optional 
ASME Code cases listed in NRC Regulatory Guide 1.147, through Revision 
13, that are incorporated by reference in paragraph (b) of this 
section), subject to the limitations and modifications listed in 
paragraph (b) of this section.
    (iii) Licensees may, but are not required to, perform the surface 
examinations of High Pressure Safety Injection Systems specified in 
Table IWB-2500-1, Examination Category B-J, Item Numbers B9.20, B9.21, 
and B9.22.
    (iv) Inservice examination of components and system pressure tests 
may meet the requirements set forth in subsequent editions and addenda 
that are incorporated by reference in paragraph (b) of this section, 
subject to the limitations and modifications listed in paragraph (b) of 
this section, and subject to Commission approval. Portions of editions 
or addenda may be used provided that all related requirements of the 
respective editions or addenda are met.
    (v) For a boiling or pressurized water-cooled nuclear power facility 
whose construction permit was issued after January 1, 1956:
    (A) Metal containment pressure retaining components and their 
integral attachments must meet the inservice inspection, repair, and 
replacement requirements applicable to components which are classified 
as ASME Code Class MC;
    (B) Metallic shell and penetration liners which are pressure 
retaining components and their integral attachments in concrete 
containments must meet the inservice inspection, repair, and replacement 
requirements applicable to components which are classified as ASME Code 
Class MC; and
    (C) Concrete containment pressure retaining components and their 
integral attachments, and the post-tensioning systems of concrete 
containments must meet the inservice inspection, repair, and replacement 
requirements applicable to components which are classified as ASME Code 
Class CC.

[[Page 772]]

    (5)(i) The inservice inspection program for a boiling or pressurized 
water-cooled nuclear power facility must be revised by the licensee, as 
necessary, to meet the requirements of paragraph (g)(4) of this section.
---------------------------------------------------------------------------

    See footnotes at end of section.
---------------------------------------------------------------------------

    (ii) If a revised inservice inspection program for a facility 
conflicts with the technical specification for the facility, the 
licensee shall apply to the Commission for amendment of the technical 
specifications to conform the technical specification to the revised 
program. The licensee shall submit this application, as specified in 
Sec. 50.4, at least six months before the start of the period during 
which the provisions become applicable, as determined by paragraph 
(g)(4) of this section.
    (iii) If the licensee has determined that conformance with certain 
code requirements is impractical for its facility, the licensee shall 
notify the Commission and submit, as specified in Sec. 50.4, 
information to support the determinations.
    (iv) Where an examination requirement by the code or addenda is 
determined to be impractical by the licensee and is not included in the 
revised inservice inspection program as permitted by paragraph (g)(4) of 
this section, the basis for this determination must be demonstrated to 
the satisfaction of the Commission not later than 12 months after the 
expiration of the initial 120-month period of operation from start of 
facility commercial operation and each subsequent 120-month period of 
operation during which the examination is determined to be impractical.
    (6)(i) The Commission will evaluate determinations under paragraph 
(g)(5) of this section that code requirements are impractical. The 
Commission may grant such relief and may impose such alternative 
requirements as it determines is authorized by law and will not endanger 
life or property or the common defense and security and is otherwise in 
the public interest giving due consideration to the burden upon the 
licensee that could result if the requirements were imposed on the 
facility.
    (ii) The Commission may require the licensee to follow an augmented 
inservice inspection program for systems and components for which the 
Commission deems that added assurance of structural reliability is 
necessary.
    (A) Augmented examination of reactor vessel.
    (1) All previously granted reliefs under Sec. 50.55a to licensees 
for the extent of volumetric examination of reactor vessel shell welds 
specified in Item B1.10 of Examination Category B-A, ``Pressure 
Retaining Welds in Reactor Vessel,'' in Table IWB-2500-1 of subsection 
IWB in applicable edition and addenda of section XI, Division 1, of the 
ASME Boiler and Pressure Vessel Code, during the inservice inspection 
interval in effect on September 8, 1992 are hereby revoked, subject to 
the specific modification in Sec. 50.55a(g)(6)(ii)(A)(3)(iv) for 
licensees that defer the augmented examination in accordance with Sec. 
50.55a(g)(6)(ii)(A)(3).
    (2) All licensees shall augment their reactor vessel examination by 
implementing once, as part of the inservice inspection interval in 
effect on September 8, 1992, the examination requirements for reactor 
vessel shell welds specified in Item B1.10 of Examination Category B-A, 
``Pressure Retaining Welds in Reactor Vessel,'' in Table IWB-2500-1 of 
subsection IWB of the 1989 Edition of section XI, Division 1, of the 
ASME Boiler and Pressure Vessel Code, subject to the conditions 
specified in Sec. 50.55a(g)(6)(ii)(A) (3) and (4). The augmented 
examination, when not deferred in accordance with the provisions of 
Sec. 50.55a(g)(6)(ii)(A)(3), shall be performed in accordance with the 
related procedures specified in the section XI edition and addenda 
applicable to the inservice inspection interval in effect on September 
8, 1992, and may be used as a substitute for the reactor vessel shell 
weld examination scheduled for implementation during the inservice 
inspection interval in effect on September 8, 1992. For the purpose of 
this augmented examination, ``essentially 100% as used in Table IWB-
2500-1 means more than 90 percent of the examination volume of each 
weld, where

[[Page 773]]

the reduction in coverage is due to interference by another component, 
or part geometry.
    (3) Licensees with fewer than 40 months remaining in the inservice 
inspection interval in effect on September 8, 1992 may defer the 
augmented reactor vessel examination specified in Sec. 
50.55a(g)(6)(ii)(A)(2) to the first period of the next inspection 
interval under the following conditions:
    (i) The deferred augmented examination may not be used as a 
substitute for the reactor vessel shell weld examination scheduled for 
implementation during the inservice inspection interval in effect on 
September 8, 1992.
    (ii) The deferred augmented examination may be used as a substitute 
for the reactor vessel shell weld examination normally scheduled for the 
inspection interval in which the deferred examination is performed.
    (iii) If the deferred augmented examination is used as a substitute 
for the normally scheduled reactor vessel shell weld examination, 
subsequent reactor vessel shell weld examinations must be performed 
during the first period of successive inspection intervals.
    (iv) Licensees that defer the augmented examination, as permitted 
herein, may retain all previously granted reliefs that otherwise would 
be revoked by Sec. 50.55a(g)(6)(ii)(A)(1) for the inservice inspection 
interval in effect on September 8, 1992.
    (v) Licensees with fewer than 40 months remaining in the inservice 
inspection interval in effect on September 8, 1992 may extend that 
interval in accordance with the provisions of section XI (1989 Edition) 
IWA-2430(d) for the purpose of implementing the augmented examination 
during that interval.
    (vi) The deferred augmented examination shall be performed in 
accordance with the related procedures specified in the section XI 
edition and addenda applicable to the inspection interval in which the 
augmented examination is performed.
    (4) The requirement for augmented examination of the reactor vessel 
may be satisfied by an examination of essentially 100 percent of the 
reactor vessel shell welds specified in Sec. 50.55a(g)(6)(ii)(A)(2) 
that has been completed, or is scheduled for implementation with a 
written commitment, or is required by Sec. 50.55a(g)(4)(i), during the 
inservice inspection interval in effect on September 8, 1992.
    (5) Licensees that make a determination that they are unable to 
completely satisfy the requirements for the augmented reactor vessel 
shell weld examination specified in Sec. 50.55a(g)(6)(ii)(A) shall 
submit information to the Commission to support the determination and 
shall propose an alternative to the examination requirements that would 
provide an acceptable level of quality and safety. The licensee may use 
the proposed alternative when authorized by the Director of the Office 
of Nuclear Reactor Regulation.
    (B) Licensees do not have to submit to the NRC staff for approval of 
their containment inservice inspection programs which were developed to 
satisfy the requirements of Subsection IWE and Subsection IWL with 
specified modifications and limitations. The program elements and the 
required documentation must be maintained on site for audit.
    (C) Implementation of Appendix VIII to Section XI. (1) Appendix VIII 
and the supplements to Appendix VIII to Section XI, Division 1, 1995 
Edition with the 1996 Addenda of the ASME Boiler and Pressure Vessel 
Code must be implemented in accordance with the following schedule: 
Appendix VIII and Supplements 1, 2, 3, and 8--May 22, 2000; Supplements 
4 and 6--November 22, 2000; Supplement 11--November 22, 2001; and 
Supplements 5, 7, and 10--November 22, 2002.
    (2) Licensees implementing the 1989 Edition and earlier editions and 
addenda of IWA-2232 of Section XI, Division 1, of the ASME Boiler and 
Pressure Vessel Code must implement the 1995 Edition with the 1996 
Addenda of Appendix VIII and the supplements to Appendix VIII of Section 
XI, Division 1, of the ASME Boiler and Pressure Vessel Code.
    (h) Protection and safety systems. (1) IEEE Std. 603-1991, including 
the correction sheet dated January 30, 1995, which is referenced in 
paragraphs (h)(2) and (h)(3) of this section, is approved for 
incorporation by reference by the

[[Page 774]]

Director of the Office of the Federal Register in accordance with 5 
U.S.C. 552(a) and 1 CFR Part 51. Copies of IEEE Std. 603-1991 may be 
purchased from the Institute of Electrical and Electronics Engineers 
Service Center, 445 Hoes Lane, Piscataway, NJ 08855. The standard is 
also available for inspection at the NRC Library, 11545 Rockville Pike, 
Rockville, Md; or at the National Archives and Records Administration 
(NARA). For information on the availability of this material at NARA, 
call 202-741-6030, or go to: http://www.archives.gov/federal--register/
code--of--federal--regulations/ibr--locations.htmlIEEE Std. 279, which 
is referenced in paragraph (h)(2) of this section, was approved for 
incorporation by reference by the Director of the Office of the Federal 
Register in accordance with 5 U.S.C. 552(a) and 1 CFR Part 51. Copies of 
IEEE Std. 279 are also available as indicated for IEEE Std. 603-1991.
    (2) Protection systems. For nuclear power plants with construction 
permits issued after January 1, 1971, but before May 13, 1999, 
protection systems must meet the requirements stated in either IEEE Std. 
279, ``Criteria for Protection Systems for Nuclear Power Generating 
Stations,'' or in IEEE Std. 603-1991, ``Criteria for Safety Systems for 
Nuclear Power Generating Stations,'' and the correction sheet dated 
January 30, 1995. For nuclear power plants with construction permits 
issued before January 1, 1971, protection systems must be consistent 
with their licensing basis or may meet the requirements of IEEE Std. 
603-1991 and the correction sheet dated January 30, 1995.
    (3) Safety systems. Applications filed on or after May 13, 1999 for 
preliminary and final design approvals (10 CFR Part 52, Appendix O), 
design certifications, and construction permits, operating licenses and 
combined licenses that do not reference a final design approval or 
design certification, must meet the requirements for safety systems in 
IEEE Std. 603-1991 and the correction sheet dated January 30, 1995.

    Footnotes to Sec. 50.55a:
    1-3 [Reserved]
    \4\ USAS and ASME Code addenda issued prior to the Winter 1977 
Addenda are considered to be ``in effect'' or ``effective'' 6 months 
after their date of issuance and after they are incorporated by 
reference in paragraph (b) of this section. Addenda to the ASME Code 
issued after the Summer 1977 Addenda are considered to be ``in effect'' 
or ``effective'' after the date of publication of the addenda and after 
they are incorporated by reference in paragraph (b) of this section.
    \5\ For ASME Code Editions and Addenda issued prior to the Winter 
1977 Addenda, the Code Edition and Addenda applicable to the component 
is governed by the order or contract date for the component, not the 
contract date for the nuclear energy system. For the Winter 1977 Addenda 
and subsequent editions and addenda the method for determining the 
applicable Code editions and addenda is contained in Paragraph NCA 1140 
of Section III of the ASME Code.
    6-8 [Reserved]
    \9\ Guidance for quality group classifications of components which 
are to be included in the safety analysis reports pursuant to Sec. 
50.34(a) and Sec. 50.34(b) may be found in Regulatory Guide 1.26, 
``Quality Group Classifications and Standards for Water-, Steam-, and 
Radiological-Waste-Containing Components of Nuclear Power Plants,'' and 
in Section 3.2.2 of NUREG-0800, ``Standard Review Plan for Review of 
Safety Analysis Reports for Nuclear Power Plants.''
    \10\ Supplemental inservice inspection requirements for reactor 
vessel pressure heads have been imposed by Order EA-03-09 issued to 
licensees of pressurized water reactors. The NRC expects to develop 
revised supplemental inspection requirements, based in part upon a 
review of the initial implementation of the order, and will determine 
the need for incorporating the revised inspection requirements into 10 
CFR 50.55a by rulemaking.

[36 FR 11424, June 12, 1971]