Sec. 1953.5  Special provisions for standards changes.

    (a) Permanent standards. (1) Where a Federal program change is a new 
permanent standard, or a more stringent amendment to an existing 
permanent standard, the State shall promulgate a State standard adopting 
such new Federal standard, or more stringent amendment to an existing 
Federal standard, or an at least as effective equivalent thereof, within 
six months of the date of promulgation of the new Federal standard or 
more stringent amendment. The State may demonstrate that a standard 
change is not necessary because the State standard is already the same 
as or at least as effective as the Federal standard change. In order to 
avoid delays in worker protection, the effective date of the State 
standard and any of its delayed provisions must be the date of State 
promulgation or the Federal effective date

[[Page 126]]

whichever is later. The Assistant Secretary may permit a longer time 
period if the State makes a timely demonstration that good cause exists 
for extending the time limitation. State permanent standards adopted in 
response to a new or revised Federal standard shall be submitted as a 
State plan supplement within 60 days of State promulgation in accordance 
with Sec. 1953.4(b), Federal Program changes.
    (2) Because a State may include standards and standards provisions 
in addition to Federal standards within an issue covered by an approved 
plan, it would generally be unnecessary for a State to revoke a standard 
when the comparable Federal standard is revoked or made less stringent. 
If the State does not adopt the Federal action, it need only provide 
notification of its intent to retain the existing State standard to OSHA 
within 6 months of the Federal promulgation date. If the State adopts a 
change to its standard parallel to the Federal action, it shall submit 
the appropriate documentation as provided in Sec. Sec. 1953.4(b)(3) or 
(4)--Federal program changes. However, in the case of standards 
applicable to products used or distributed in interstate commerce where 
section 18(c)(2) of the Act imposes certain restrictions on State plan 
authority, the modification, revision, or revocation of the Federal 
standard may necessitate the modification, revision, or revocation of 
the comparable State standard unless the State standard is required by 
compelling local conditions and does not unduly burden interstate 
commerce.
    (3) Where a State on its own initiative adopts a permanent State 
standard for which there is no Federal parallel, the State shall submit 
it within 60 days of State promulgation in accordance with Sec. 
1953.4(d)--State-initiated changes,
    (b) Emergency temporary standards. (1) Immediately upon publication 
of an emergency temporary standard in the Federal Register, OSHA shall 
advise the States of the standard and that a Federal program change 
supplement shall be required. This notification must also provide that 
the State has 30 days after the date of promulgation of the Federal 
standard to adopt a State emergency temporary standard if the State plan 
covers that issue. The State may demonstrate that promulgation of an 
emergency temporary standard is not necessary because the State standard 
is already the same as or at least as effective as the Federal standard 
change. The State standard must remain in effect for the duration of the 
Federal emergency temporary standard which may not exceed six (6) 
months.
    (2) Within 15 days after receipt of the notice of a Federal 
emergency temporary standard, the State shall advise OSHA of the action 
it will take. State standards shall be submitted in accordance with the 
applicable procedures in Sec. 1953.4(b)--Federal Program Changes, 
except that the required documentation or plan supplement must be 
submitted within 5 days of State promulgation.
    (3) If for any reason, a State on its own initiative adopts a State 
emergency temporary standard, it shall be submitted as a plan supplement 
in accordance with Sec. 1953.4(c), but within 10 days of promulgation.