Sec. 644.5  How long is a project period?



    (a) Except as provided in paragraph (b) of this section, a project 

period under the Educational Opportunity Centers program is four years.

    (b) The Secretary approves a project period of five years for 

applications that score in the highest ten percent of all applications 

approved for new grants under the criteria in Sec. 644.21.