[Code of Federal Regulations]

[Title 40, Volume 13]

[Revised as of July 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 40CFR63.7110]



[Page 40-41]

 

                   TITLE 40--PROTECTION OF ENVIRONMENT

 

         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)

 

PART 63_NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR 

SOURCE CATEGORIES--Table of Contents

 

 Subpart AAAAA_National Emission Standards for Hazardous Air Pollutants 

                      for Lime Manufacturing Plants

 

Sec. 63.7110  By what date must I conduct performance tests and other 

initial compliance demonstrations?



    (a) If you have an existing affected source, you must complete all 

applicable performance tests within January 5, 2007, according to the 

provisions in Sec. Sec. 63.7(a)(2) and 63.7114.

    (b) If you have a new affected source, and commenced construction or 

reconstruction between December 20, 2002, and January 5, 2004, you must 

demonstrate initial compliance with either the proposed emission 

limitation or the promulgated emission limitation no later than 180 

calendar days after January 5, 2004 or within 180 calendar days after 

startup of the source, whichever is later, according to Sec. Sec. 

63.7(a)(2)(ix) and 63.7114.

    (c) If you commenced construction or reconstruction between December 

20, 2002, and January 5, 2004, and you chose to comply with the proposed 

emission limitation when demonstrating initial



[[Page 41]]



compliance, you must conduct a demonstration of compliance with the 

promulgated emission limitation within January 5, 2007 or after startup 

of the source, whichever is later, according to Sec. Sec. 

63.7(a)(2)(ix) and 63.7114.

    (d) For each initial compliance requirement in Table 3 to this 

subpart that applies to you where the monitoring averaging period is 3 

hours, the 3-hour period for demonstrating continuous compliance for 

emission units within existing affected sources at LMP begins at 12:01 

a.m. on the compliance date for existing affected sources, that is, the 

day following completion of the initial compliance demonstration, and 

ends at 3:01 a.m. on the same day.

    (e) For each initial compliance requirement in Table 3 to this 

subpart that applies to you where the monitoring averaging period is 3 

hours, the 3-hour period for demonstrating continuous compliance for 

emission units within new or reconstructed affected sources at LMP 

begins at 12:01 a.m. on the day following completion of the initial 

compliance demonstration, as required in paragraphs (b) and (c) of this 

section, and ends at 3:01 a.m. on the same day.