[Code of Federal Regulations]

[Title 40, Volume 13]

[Revised as of July 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 40CFR63.7113]



[Page 43-44]

 

                   TITLE 40--PROTECTION OF ENVIRONMENT

 

         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)

 

PART 63_NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR 

SOURCE CATEGORIES--Table of Contents

 

 Subpart AAAAA_National Emission Standards for Hazardous Air Pollutants 

                      for Lime Manufacturing Plants

 

Sec. 63.7113  What are my monitoring installation, operation, and 

maintenance requirements?



    (a) You must install, operate, and maintain each continuous 

parameter monitoring system (CPMS) according to your OM&M plan required 

by Sec. 63.7100(d) and paragraphs (a)(1) through (5) of this section, 

and you must install, operate, and maintain each continuous opacity 

monitoring system (COMS) as required by paragraph (g) of this section

    (1) The CPMS must complete a minimum of one cycle of operation for 

each successive 15-minute period.

    (2) To calculate a valid hourly value, you must have at least four 

equally spaced data values (or at least two, if that condition is 

included to allow for periodic calibration checks) for that hour from a 

CPMS that is not out of control according your OM&M plan, and use all 

valid data.

    (3) To calculate the average for each 3-hour block averaging period, 

you must use all valid data, and you must have at least 66 percent of 

the hourly averages for that period using only hourly average values 

that are based on valid data (i.e., not from out-of-control periods).

    (4) You must conduct a performance evaluation of each CPMS in 

accordance with your OM&M plan.

    (5) You must continuously operate and maintain the CPMS according to 

the OM&M plan, including, but not limited to, maintaining necessary 

parts for routine repairs of the monitoring equipment.

    (b) For each flow measurement device, you must meet the requirements 

in paragraphs (a)(1) through (5) and (b)(1) through (4) of this section.

    (1) Use a flow sensor with a minimum tolerance of 2 percent of the 

flow rate.

    (2) Reduce swirling flow or abnormal velocity distributions due to 

upstream and downstream disturbances.

    (3) Conduct a flow sensor calibration check at least semiannually.

    (4) At least monthly, inspect all components for integrity, all 

electrical connections for continuity, and all mechanical connections 

for leakage.

    (c) For each pressure measurement device, you must meet the 

requirements in paragraphs (a)(1) through (5) and (c)(1) through (7) of 

this section.

    (1) Locate the pressure sensor(s) in or as close to as possible a 

position that provides a representative measurement of the pressure.

    (2) Minimize or eliminate pulsating pressure, vibration, and 

internal and external corrosion.

    (3) Use a gauge with a minimum tolerance of 0.5 inch of water or a 

transducer with a minimum tolerance of 1 percent of the pressure range.

    (4) Check pressure tap pluggage daily.

    (5) Using a manometer, check gauge calibration quarterly and 

transducer calibration monthly.

    (6) Conduct calibration checks any time the sensor exceeds the 

manufacturer's specified maximum operating pressure range or install a 

new pressure sensor.

    (7) At least monthly, inspect all components for integrity, all 

electrical connections for continuity, and all mechanical connections 

for leakage.

    (d) For each bag leak detection system (BLDS), you must meet any 

applicable requirements in paragraphs (a)(1) through (5) and (d)(1) 

through (8) of this section.

    (1) The BLDS must be certified by the manufacturer to be capable of 

detecting PM emissions at concentrations of 10 milligrams per actual 

cubic meter (0.0044 grains per actual cubic foot) or less.

    (2) The sensor on the BLDS must provide output of relative PM 

emissions.

    (3) The BLDS must have an alarm that will sound automatically when 

it detects an increase in relative PM emissions greater than a preset 

level.

    (4) The alarm must be located in an area where appropriate plant 

personnel will be able to hear it.

    (5) For a positive-pressure fabric filter (FF), each compartment or 

cell must have a bag leak detector (BLD). For a negative-pressure or 

induced-air FF, the BLD must be installed downstream of the FF. If 

multiple BLD are required (for either type of FF), the detectors may 

share the system instrumentation and alarm.

    (6) Bag leak detection systems must be installed, operated, 

adjusted, and



[[Page 44]]



maintained according to the manufacturer's written specifications and 

recommendations. Standard operating procedures must be incorporated into 

the OM&M plan.

    (7) At a minimum, initial adjustment of the system must consist of 

establishing the baseline output in both of the following ways:

    (i) Adjust the range and the averaging period of the device.

    (ii) Establish the alarm set points and the alarm delay time.

    (8) After initial adjustment, the range, averaging period, alarm set 

points, or alarm delay time may not be adjusted except as specified in 

the OM&M plan required by Sec. 63.7100(d). In no event may the range be 

increased by more than 100 percent or decreased by more than 50 percent 

over a 365-day period unless a responsible official, as defined in Sec. 

63.2, certifies in writing to the Administrator that the FF has been 

inspected and found to be in good operating condition.

    (e) For each PM detector, you must meet any applicable requirements 

in paragraphs (a)(1) through (5) and (e)(1) through (8) of this section.

    (1) The PM detector must be certified by the manufacturer to be 

capable of detecting PM emissions at concentrations of 10 milligrams per 

actual cubic meter (0.0044 grains per actual cubic foot) or less.

    (2) The sensor on the PM detector must provide output of relative PM 

emissions.

    (3) The PM detector must have an alarm that will sound automatically 

when it detects an increase in relative PM emissions greater than a 

preset level.

    (4) The alarm must be located in an area where appropriate plant 

personnel will be able to hear it.

    (5) For a positive-pressure electrostatic precipitator (ESP), each 

compartment must have a PM detector. For a negative-pressure or induced-

air ESP, the PM detector must be installed downstream of the ESP. If 

multiple PM detectors are required (for either type of ESP), the 

detectors may share the system instrumentation and alarm.

    (6) Particulate matter detectors must be installed, operated, 

adjusted, and maintained according to the manufacturer's written 

specifications and recommendations. Standard operating procedures must 

be incorporated into the OM&M plan.

    (7) At a minimum, initial adjustment of the system must consist of 

establishing the baseline output in both of the following ways:

    (i) Adjust the range and the averaging period of the device.

    (ii) Establish the alarm set points and the alarm delay time.

    (8) After initial adjustment, the range, averaging period, alarm set 

points, or alarm delay time may not be adjusted except as specified in 

the OM&M plan required by Sec. 63.7100(d). In no event may the range be 

increased by more than 100 percent or decreased by more than 50 percent 

over a 365-day period unless a responsible official as defined in Sec. 

63.2 certifies in writing to the Administrator that the ESP has been 

inspected and found to be in good operating condition.

    (f) For each emission unit equipped with an add-on air pollution 

control device, you must inspect each capture/collection and closed vent 

system at least once each calendar year to ensure that each system is 

operating in accordance with the operating requirements in item 6 of 

Table 2 to this subpart and record the results of each inspection.

    (g) For each COMS used to monitor an add-on air pollution control 

device, you must meet the requirements in paragraphs (g)(1) and (2) of 

this section.

    (1) Install the COMS at the outlet of the control device.

    (2) Install, maintain, calibrate, and operate the COMS as required 

by 40 CFR part 63, subpart A, General Provisions and according to 

Performance Specification (PS)-1 of appendix B to part 60 of this 

chapter. Facilities that operate COMS installed on or before February 6, 

2001, may continue to meet the requirements in effect at the time of 

COMS installation unless specifically required to re-certify the COMS by 

their permitting authority.



[[Page 45]]