Sec. 63.7183  When do I have to comply with this subpart?



    (a) If you have a new or reconstructed affected source, you must 

comply with this subpart according to paragraphs (a)(1) and (2) of this 

section.

    (1) If you start up your affected source before May 22, 2003, then 

you must comply with the emission standards for new and reconstructed 

sources in this subpart no later than May 22, 2003.

    (2) If you start up your affected source after May 22, 2003, then 

you must comply with the emission standards for new and reconstructed 

sources in this subpart upon startup of your affected source.

    (b) If you have an existing affected source, you must comply with 

the emission standards for existing sources no later than 3 years from 

May 22, 2003.

    (c) If you have an area source that increases its emissions or its 

potential to emit such that it becomes a major source of HAP and an 

affected source subject to this subpart, paragraphs (c)(1) and (2) of 

this section apply.

    (1) Any portion of your existing facility that is a new affected 

source as specified at Sec. 63.7182(c), or a reconstructed affected 

source as specified at Sec. 63.7182(d), must be in compliance with this 

subpart upon startup.

    (2) Any portion of your facility that is an existing affected 

source, as specified at Sec. 63.7182(e), must be in compliance with 

this subpart by not later than 3 years after it becomes a major source.

    (d) You must meet the notification requirements in Sec. 63.7189 and 

in subpart A of this part. You must submit some of the notifications 

(e.g., Initial Notification) before the date you are required to comply 

with the emission limitations in this subpart.



                           Emission Standards