Sec. 64.5  Deadlines for submittals.

    (a) Large pollutant-specific emissions units. For all pollutant-
specific emissions units with the potential to emit (taking into account 
control devices to the extent appropriate under the definition of this 
term in Sec. 64.1) the applicable regulated air pollutant in an amount 
equal to or greater than 100 percent of the amount, in tons per year, 
required for a source to be classified as a major source, the owner or 
operator shall submit the information required under Sec. 64.4 at the 
following times:
    (1) On or after April 20, 1998, the owner or operator shall submit 
information as part of an application for an initial part 70 or 71 
permit if, by that date, the application either:
    (i) Has not been filed; or
    (ii) Has not yet been determined to be complete by the permitting 
authority.
    (2) On or after April 20, 1998, the owner or operator shall submit 
information as part of an application for a significant permit revision 
under part 70 or 71 of this chapter, but only with respect to those 
pollutant-specific emissions units for which the proposed permit 
revision is applicable.
    (3) The owner or operator shall submit any information not submitted 
under the deadlines set forth in paragraphs (a)(1) and (2) of this 
section as part of the application for the renewal of a part 70 or 71 
permit.
    (b) Other pollutant-specific emissions units. For all other 
pollutant-specific emissions units subject to this part and not subject 
to Sec. 64.5(a), the owner or operator shall submit the information 
required under Sec. 64.4 as part of an application for a renewal of a 
part 70 or 71 permit.
    (c) The effective date for the requirement to submit information 
under Sec. 64.4 shall be as specified pursuant to paragraphs (a)-(b) of 
this section and a permit reopening to require the submittal of 
information under this section shall not be required pursuant to Sec. 
70.7(f)(1)(i) of this chapter, provided, however, that, if a part 70 or 
71 permit is reopened for cause by EPA or the permitting authority 
pursuant to Sec. 70.7(f)(1)(iii) or (iv), or Sec. 71.7(f) or (g), the 
applicable agency may require the submittal of information under this 
section for those pollutant-specific emissions units that are subject to 
this part and that are affected by the permit reopening.
    (d) Prior to approval of monitoring that satisfies this part, the 
owner or operator is subject to the requirements of Sec. 
70.6(a)(3)(i)(B).