[Code of Federal Regulations]
[Title 40, Volume 15]
[Revised as of July 1, 2005]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR69.22]

[Page 198-201]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
         CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)
 
PART 69_SPECIAL EXEMPTIONS FROM REQUIREMENTS OF THE CLEAN AIR ACT
--Table of Contents
 
                        Subpart B_American Samoa
 
Sec. 69.22  Title V conditional exemption.

    (a) Conditional exemption. In response to a petition submitted by 
the Governor of American Samoa (American Samoa) and pursuant to section 
325(a)

[[Page 199]]

of the Clean Air Act (Act), the Administrator of the United States EPA 
(EPA) grants the following conditional exemptions:
    (1) American Samoa is exempted from the requirement to develop, 
submit for approval, and implement an operating permit program under 
title V of the Clean Air Act on the condition that American Samoa meets 
the requirements of paragraph (b) of this section and subject to the 
provisions of paragraphs (c) through (f) of this section.
    (2) Except for sources listed under paragraph (a)(4) of this 
section, owners or operators of sources located in American Samoa 
subject to the operating permit requirements of title V of the Clean Air 
Act are exempt from the requirement to apply for and obtain a title V 
operating permit, on the condition that the owner or operator of each 
such source must apply for and obtain an operating permit under an EPA 
approved alternate program that meets the requirements of paragraph (b) 
of this section and subject to the provisions of paragraphs (c) through 
(f) of this section. The owner or operator of each such source shall 
apply for and obtain a permit under the alternate operating permit 
program by the deadlines set forth in the approved program, but in any 
event shall obtain a permit no later than January 13, 2003. If the owner 
or operator of any source has not obtained an operating permit under an 
alternate operating program approved by EPA for American Samoa by 
January 13, 2003, the exemption for such source shall expire and the 
owner or operator of such source shall become subject to the permitting 
requirements of 40 CFR part 71 on that date, consistent with paragraph 
(e)(4) of this section.
    (3) Upon EPA approval of an alternate operating permit program 
adopted by American Samoa in accordance with this Sec. 69.22, a person 
shall not violate any permit condition or term in a permit that has been 
issued under such alternate permit program.
    (4) This exemption does not apply to owners or operators of major 
sources of hazardous air pollutants (HAPs) as defined under section 112 
of the Clean Air Act or to owners or operators of solid waste 
incinerators subject to the title V requirements of section 129(e) of 
the Act. Owners or operators of major sources of HAPs or solid waste 
incinerators shall be subject to the requirements of 40 CFR part 71 and 
shall apply for and obtain a part 71 permit by the deadlines specified 
in 40 CFR part 71. Any owner or operator of a major source of HAPs 
subject to 40 CFR part 63, subpart B, shall submit a timely part 71 
permit application as required by 40 CFR part 71 and 40 CFR part 63, 
subpart B, requesting a case-by-case 112(g) or 112(j) Maximum Achievable 
Control Technology (MACT) determination.
    (b) Requirements for the alternate operating program. American Samoa 
shall develop and submit an alternate operating permit program (the 
program) to EPA for approval. Upon approval by EPA, American Samoa shall 
implement the program. The program, including the necessary statutory 
and regulatory authority, must be submitted by January 13, 1999 for 
approval. The submittal shall include the following elements:
    (1) The program must contain regulations that ensure that:
    (i) The permits shall include emission limits and standards, and 
other terms or conditions necessary to ensure compliance with all 
applicable federal requirements, as defined under 40 CFR 70.2.
    (ii) The limitations, controls, and requirements in the permits 
shall be permanent, quantifiable, and otherwise enforceable as a 
practical matter.
    (iii) Permits shall contain monitoring, recordkeeping and reporting 
requirements sufficient to ensure compliance with applicable federal 
requirements during the reporting period.
    (iv) The program shall require that the owner or operator of each 
source submit permit applications with compliance certifications 
describing the source's compliance status with all applicable 
requirements. The program shall also provide that each permit contain a 
requirement that the owner or operator of a source submit annual

[[Page 200]]

compliance certifications. The compliance certification shall contain a 
compliance plan, and shall contain a schedule for expeditiously 
achieving compliance if the source is not in compliance with all 
applicable requirements. The program must provide that approval of a 
permit with a compliance plan and schedule does not sanction 
noncompliance.
    (2) The program shall provide for the collection of fees from 
permitted sources or other revenues in an amount that will pay for the 
cost of operation of such a program and ensure that these funds are used 
solely to support the program.
    (3) The program shall provide for public notice and a public comment 
period of at least 30 days for each permit, significant permit 
modification, and permit renewal, and shall include submittal to EPA of 
each permit, significant permit modification, and permit renewal.
    (4) The program shall provide EPA at least 45 days from receipt of a 
permit, modification, or renewal for EPA review and objection prior to 
issuance. The program shall provide that if EPA objects to a permit sent 
to EPA for review, American Samoa cannot issue such permit until the 
permit is revised in a manner that resolves EPA's objections. The 
program will provide that American Samoa will have no more than 180 days 
to resolve EPA's objections and that if the objections are not resolved 
within that time period, EPA shall issue the permit under 40 CFR part 
71.
    (5) The program shall provide that all documents other than 
confidential business information will be made available to the public.
    (6) The program shall provide American Samoa with the authority to 
enforce permits, including the authority to assess civil and criminal 
penalties up to $10,000 per day per violation and to enjoin activities 
that are in violation of the permit, the program, or the Act without 
first revoking the permit.
    (7) The program shall require that owners or operators of nonmajor 
sources of hazardous air pollutants that are required to obtain title V 
permits, and owners or operators of major sources of all other air 
pollutants as defined in 40 CFR 70.2 that are exempted from 40 CFR part 
71 under paragraph (a) of this section, obtain an operating permit under 
the approved program. The program shall include a schedule for issuing 
permits to all subject sources within three years of EPA approval of the 
program.
    (8) The program shall include a system of regular inspections of 
permitted sources, a system to identify any unpermitted major sources, 
and guidelines for appropriate responses to violations.
    (9) The program shall provide for the issuance of permits with a 
fixed term that shall not exceed five years.
    (10) The program shall allow American Samoa or the EPA to reopen a 
permit for cause. The program shall provide that if EPA provides 
American Samoa with written notice that a permit must be reopened for 
cause, American Samoa shall issue a revised permit within 180 days 
(including public notice and comment) that sufficiently addresses EPA's 
concerns. The program shall provide that if American Samoa fails to 
issue a permit that resolves EPA's concerns within 180 days, then EPA 
will terminate, modify, or revoke and reissue the permit under part 71 
after providing the permittee and the public with notice and opportunity 
for comment.
    (c) Ambient air quality program. American Samoa shall implement the 
following program to address the National Ambient Air Quality Standards 
(NAAQS) as a condition of the waiver:
    (1) American Samoa shall collect complete meteorological data and 
complete refined air quality modeling for the Pago Pago Harbor and 
submit such data and modeling results to EPA by January 13, 1999.
    (2) American Samoa shall address any NAAQS exceedances demonstrated 
through the modeling results with revisions to its SIP that shall be 
submitted by January 13, 2000. The plan shall ensure compliance with the 
NAAQS is achieved by January 14, 2002.
    (d) State Implementation Plan (SIP) submittal. In conjunction with 
the submittal of the alternative operating permit program, American 
Samoa shall, no later than January 13, 1999, submit a revision to its 
SIP that provides that

[[Page 201]]

a person shall not violate a permit condition or term in an operating 
permit that has been issued under an EPA approved alternate operating 
permit program adopted by American Samoa pursuant to the exemption 
authorized in this Sec. 69.22.
    (e) Expiration and revocation of the exemption. This exemption shall 
expire or may be revoked under the following circumstances:
    (1) If American Samoa fails to submit the required alternate 
operating permit program or modeling (and supporting data) by March 15, 
1999, the exemption shall automatically expire with no further 
rulemaking and 40 CFR part 71 shall become effective for all subject 
sources in American Samoa on that date. The exemption will also expire 
with no further rulemaking in the event that American Samoa fails to 
submit a SIP revision by January 13, 2000, consistent with paragraph 
(c)(2) of this section.
    (2) In the event that EPA disapproves American Samoa's alternate 
operating permit program because the program does not meet the 
requirements set forth in paragraph (b) of this section, EPA will revoke 
the exemption by rulemaking.
    (3) If, by March 14, 2003, the owner or operator of any subject 
source has not obtained a federally enforceable operating permit under 
an EPA approved program, the exemption shall automatically expire for 
such source and such source shall be subject to the permitting 
requirements of 40 CFR part 71. American Samoa will work with EPA to 
identify such sources prior to expiration of the exemption under this 
paragraph (d).
    (4) EPA shall revoke the exemption in its entirety through 
rulemaking if American Samoa does not adequately administer and enforce 
an alternate operating permit program approved by EPA.
    (5) EPA shall revoke the exemption by rulemaking with respect to the 
owner or operator of any source if, during the 45-day review period, EPA 
objects to issuance of a permit and American Samoa fails to resolve 
EPA's objections within 180 days. EPA shall also revoke the exemption by 
rulemaking for the owner or operator of any source in the event that EPA 
reopens a permit for cause and American Samoa does not issue a permit 
that resolves the concerns as set forth in EPA's notice to reopen within 
180 days.
    (6) EPA reserves its authority to revoke or modify this exemption in 
whole or in part.
    (f) Scope of the exemption. This exemption applies solely to the 
requirement that an owner or operator obtain an operating permit under 
title V of the Clean Air Act and the requirement that American Samoa 
implement a title V permit program. In addition, this exemption does not 
apply to owners or operators of sources set forth in paragraph (a)(4) of 
this section. Owners and operators of air pollutant sources are required 
to comply with all other applicable requirements of the Clean Air Act. 
For purposes of complying with any applicable requirement that is 
triggered or implemented by the approval of a title V permit program, 
the approval date for owners or operators to which this exemption 
applies shall be the date that EPA approves the alternate program for 
each territory or, for owners or operators of sources that are subject 
to 40 CFR part 71, the approval date shall be the effective date of 40 
CFR part 71, which is July 31, 1996.

[61 FR 58291, Nov. 13, 1996; 61 FR 66077, Dec. 16, 1996]