Sec. 3601.44  How and when may my mining or reclamation plan be modified?



    (a) Either you or BLM may initiate a modification of an approved 

mining or reclamation plan to adjust for changed conditions or to 

correct any oversight. BLM will consult with you before requiring a 

modification.

    (b) If BLM notifies you that you must modify your plan, you must 

prepare the modification, or explain why you need more time, within 30 

days. If you fail to modify your plan to BLM's satisfaction, BLM may 

order you to stop operations under your contract or permit.

    (c) When you ask to change an approved mining or reclamation plan 

for one of the reasons in paragraph (a) of this section, BLM will notify 

you in writing within 30 days whether we approve the modification, deny 

it, or require any changes in it.