              TITLE 44--EMERGENCY MANAGEMENT AND ASSISTANCE

 

 CHAPTER I--FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND 

                                SECURITY

 

PART 209_SUPPLEMENTAL PROPERTY ACQUISITION AND ELEVATION ASSISTANCE

--Table of Contents

 

Sec. 209.12  Oversight and results.



    (a) FEMA oversight. Our Regional Directors are responsible for 

overseeing this grant authority and for ensuring that States and 

subgrantees meet all program requirements. Regional Directors will 

review program progress quarterly.

    (b) Monitoring and enforcement. We, subgrantees, and States will 

monitor the properties purchased under this authority and ensure that 

the properties are maintained in open space use. We and the State may 

enforce the agreement by taking any measures that we or they deem 

appropriate.

    (c) Program results. The State will review the effectiveness of 

approved projects after each future flood event in the affected area to 

monitor whether projects are resulting in expected savings. The State 

will report to us on program effectiveness after project completion and 

after each subsequent flood event.



                        PARTS 210-294 [RESERVED]