[Code of Federal Regulations]

[Title 44, Volume 1]

[Revised as of October 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 44CFR65.10]



[Page 346-349]

 

              TITLE 44--EMERGENCY MANAGEMENT AND ASSISTANCE

 

 CHAPTER I--FEDERAL EMERGENCY MANAGEMENT AGENCY, DEPARTMENT OF HOMELAND 

                                SECURITY

 

PART 65_IDENTIFICATION AND MAPPING OF SPECIAL HAZARD AREAS--Table of 

Contents

 

Sec. 65.10  Mapping of areas protected by levee systems.



    (a) General. For purposes of the NFIP, FEMA will only recognize in 

its flood hazard and risk mapping effort those levee systems that meet, 

and continue to meet, minimum design, operation, and maintenance 

standards that are consistent with the level of protection sought 

through the comprehensive



[[Page 347]]



flood plain management criteria established by Sec. 60.3 of this 

subchapter. Accordingly, this section describes the types of information 

FEMA needs to recognize, on NFIP maps, that a levee system provides 

protection from the base flood. This information must be supplied to 

FEMA by the community or other party seeking recognition of such a levee 

system at the time a flood risk study or restudy is conducted, when a 

map revision under the provisions of part 65 of this subchapter is 

sought based on a levee system, and upon request by the Administrator 

during the review of previously recognized structures. The FEMA review 

will be for the sole purpose of establishing appropriate risk zone 

determinations for NFIP maps and shall not constitute a determination by 

FEMA as to how a structure or system will perform in a flood event.

    (b) Design criteria. For levees to be recognized by FEMA, evidence 

that adequate design and operation and maintenance systems are in place 

to provide reasonable assurance that protection from the base flood 

exists must be provided. The following requirements must be met:

    (1) Freeboard. (i) Riverine levees must provide a minimum freeboard 

of three feet above the water-surface level of the base flood. An 

additional one foot above the minimum is required within 100 feet in 

either side of structures (such as bridges) riverward of the levee or 

wherever the flow is constricted. An additional one-half foot above the 

minimum at the upstream end of the levee, tapering to not less than the 

minimum at the downstream end of the levee, is also required.

    (ii) Occasionally, exceptions to the minimum riverine freeboard 

requirement described in paragraph (b)(1)(i) of this section, may be 

approved. Appropriate engineering analyses demonstrating adequate 

protection with a lesser freeboard must be submitted to support a 

request for such an exception. The material presented must evaluate the 

uncertainty in the estimated base flood elevation profile and include, 

but not necessarily be limited to an assessment of statistical 

confidence limits of the 100-year discharge; changes in stage-discharge 

relationships; and the sources, potential, and magnitude of debris, 

sediment, and ice accumulation. It must be also shown that the levee 

will remain structurally stable during the base flood when such 

additional loading considerations are imposed. Under no circumstances 

will freeboard of less than two feet be accepted.

    (iii) For coastal levees, the freeboard must be established at one 

foot above the height of the one percent wave or the maximum wave runup 

(whichever is greater) associated with the 100-year stillwater surge 

elevation at the site.

    (iv) Occasionally, exceptions to the minimum coastal levee freeboard 

requirement described in paragraph (b)(1)(iii) of this section, may be 

approved. Appropriate engineering analyses demonstrating adequate 

protection with a lesser freeboard must be submitted to support a 

request for such an exception. The material presented must evaluate the 

uncertainty in the estimated base flood loading conditions. Particular 

emphasis must be placed on the effects of wave attack and overtopping on 

the stability of the levee. Under no circumstances, however, will a 

freeboard of less than two feet above the 100-year stillwater surge 

elevation be accepted.

    (2) Closures. All openings must be provided with closure devices 

that are structural parts of the system during operation and design 

according to sound engineering practice.

    (3) Embankment protection. Engineering analyses must be submitted 

that demonstrate that no appreciable erosion of the levee embankment can 

be expected during the base flood, as a result of either currents or 

waves, and that anticipated erosion will not result in failure of the 

levee embankment or foundation directly or indirectly through reduction 

of the seepage path and subsequent instability. The factors to be 

addressed in such analyses include, but are not limited to: Expected 

flow velocities (especially in constricted areas); expected wind and 

wave action; ice loading; impact of debris; slope protection techniques; 

duration of flooding at various stages and velocities; embankment and 

foundation materials; levee alignment, bends, and transitions; and levee 

side slopes.



[[Page 348]]



    (4) Embankment and foundation stability. Engineering analyses that 

evaluate levee embankment stability must be submitted. The analyses 

provided shall evaluate expected seepage during loading conditions 

associated with the base flood and shall demonstrate that seepage into 

or through the levee foundation and embankment will not jeopardize 

embankment or foundation stability. An alternative analysis 

demonstrating that the levee is designed and constructed for stability 

against loading conditions for Case IV as defined in the U.S. Army Corps 

of Engineers (COE) manual, ``Design and Construction of Levees'' (EM 

1110-2-1913, Chapter 6, Section II), may be used. The factors that shall 

be addressed in the analyses include: Depth of flooding, duration of 

flooding, embankment geometry and length of seepage path at critical 

locations, embankment and foundation materials, embankment compaction, 

penetrations, other design factors affecting seepage (such as drainage 

layers), and other design factors affecting embankment and foundation 

stability (such as berms).

    (5) Settlement. Engineering analyses must be submitted that assess 

the potential and magnitude of future losses of freeboard as a result of 

levee settlement and demonstrate that freeboard will be maintained 

within the minimum standards set forth in paragraph (b)(1) of this 

section. This analysis must address embankment loads, compressibility of 

embankment soils, compressibility of foundation soils, age of the levee 

system, and construction compaction methods. In addition, detailed 

settlement analysis using procedures such as those described in the COE 

manual, ``Soil Mechanics Design--Settlement Analysis'' (EM 1100-2-1904) 

must be submitted.

    (6) Interior drainage. An analysis must be submitted that identifies 

the source(s) of such flooding, the extent of the flooded area, and, if 

the average depth is greater than one foot, the water-surface 

elevation(s) of the base flood. This analysis must be based on the joint 

probability of interior and exterior flooding and the capacity of 

facilities (such as drainage lines and pumps) for evacuating interior 

floodwaters.

    (7) Other design criteria. In unique situations, such as those where 

the levee system has relatively high vulnerability, FEMA may require 

that other design criteria and analyses be submitted to show that the 

levees provide adequate protection. In such situations, sound 

engineering practice will be the standard on which FEMA will base its 

determinations. FEMA will also provide the rationale for requiring this 

additional information.

    (c) Operation plans and criteria. For a levee system to be 

recognized, the operational criteria must be as described below. All 

closure devices or mechanical systems for internal drainage, whether 

manual or automatic, must be operated in accordance with an officially 

adopted operation manual, a copy of which must be provided to FEMA by 

the operator when levee or drainage system recognition is being sought 

or when the manual for a previously recognized system is revised in any 

manner. All operations must be under the jurisdiction of a Federal or 

State agency, an agency created by Federal or State law, or an agency of 

a community participating in the NFIP.

    (1) Closures. Operation plans for closures must include the 

following:

    (i) Documentation of the flood warning system, under the 

jurisdiction of Federal, State, or community officials, that will be 

used to trigger emergency operation activities and demonstration that 

sufficient flood warning time exists for the completed operation of all 

closure structures, including necessary sealing, before floodwaters 

reach the base of the closure.

    (ii) A formal plan of operation including specific actions and 

assignments of responsibility by individual name or title.

    (iii) Provisions for periodic operation, at not less than one-year 

intervals, of the closure structure for testing and training purposes.

    (2) Interior drainage systems. Interior drainage systems associated 

with levee systems usually include storage areas, gravity outlets, 

pumping stations, or a combination thereof. These drainage systems will 

be recognized by FEMA on NFIP maps for flood protection purposes only if 

the following minimum



[[Page 349]]



criteria are included in the operation plan:

    (i) Documentation of the flood warning system, under the 

jurisdiction of Federal, State, or community officials, that will be 

used to trigger emergency operation activities and demonstration that 

sufficient flood warning time exists to permit activation of mechanized 

portions of the drainage system.

    (ii) A formal plan of operation including specific actions and 

assignments of responsibility by individual name or title.

    (iii) Provision for manual backup for the activation of automatic 

systems.

    (iv) Provisions for periodic inspection of interior drainage systems 

and periodic operation of any mechanized portions for testing and 

training purposes. No more than one year shall elapse between either the 

inspections or the operations.

    (3) Other operation plans and criteria. Other operating plans and 

criteria may be required by FEMA to ensure that adequate protection is 

provided in specific situations. In such cases, sound emergency 

management practice will be the standard upon which FEMA determinations 

will be based.

    (d) Maintenance plans and criteria. For levee systems to be 

recognized as providing protection from the base flood, the maintenance 

criteria must be as described herein. Levee systems must be maintained 

in accordance with an officially adopted maintenance plan, and a copy of 

this plan must be provided to FEMA by the owner of the levee system when 

recognition is being sought or when the plan for a previously recognized 

system is revised in any manner. All maintenance activities must be 

under the jurisdiction of a Federal or State agency, an agency created 

by Federal or State law, or an agency of a community participating in 

the NFIP that must assume ultimate responsibility for maintenance. This 

plan must document the formal procedure that ensures that the stability, 

height, and overall integrity of the levee and its associated structures 

and systems are maintained. At a minimum, maintenance plans shall 

specify the maintenance activities to be performed, the frequency of 

their performance, and the person by name or title responsible for their 

performance.

    (e) Certification requirements. Data submitted to support that a 

given levee system complies with the structural requirements set forth 

in paragraphs (b)(1) through (7) of this section must be certified by a 

registered professional engineer. Also, certified as-built plans of the 

levee must be submitted. Certifications are subject to the definition 

given at Sec. 65.2 of this subchapter. In lieu of these structural 

requirements, a Federal agency with responsibility for levee design may 

certify that the levee has been adequately designed and constructed to 

provide protection against the base flood.



[51 FR 30316, Aug. 25, 1986]