Sec. 72.4  Submittal/payment procedures and FEMA response.



    (a) The initial fee shall be submitted with a request for FEMA 

review and processing of CLOMRs, LOMRs, and PMRs based on structural 

measures on alluvial fans; the appropriate flat user fee shall be 

submitted with all other requests for FEMA review and processing.

    (b) FEMA must receive initial or flat user fees before it will begin 

any review. The fee is non-refundable once FEMA begins its review.

    (c) Following completion of FEMA's review for any CLOMR, LOMR, or 

PMR based on structural measures on alluvial fans, FEMA shall invoice 

the requester at the established hourly rate for any actual costs 

exceeding the initial fee incurred for review and processing. FEMA shall 

not issue a determination letter or revised map panel(s) until it 

receives the invoiced amount.

    (d) For all map revision requests, FEMA shall bear the cost of 

reprinting and distributing the revised FIRM panel(s), FBFM panel(s), or 

combination.

    (e) The entity that applies to FEMA through the local community for 

review is responsible for the cost of the review. The local community 

incurs no financial obligation under the reimbursement procedures of 

this part when another party sends the application to FEMA.

    (f) Requesters shall submit payments by check or money order or by 

credit card. Checks or money orders, in U.S. funds, shall be made 

payable to the National Flood Insurance Program.

    (g) For CLOMA, CLOMR-F, LOMA, and LOMR-F requests, FEMA shall:

    (1) Notify the requester and community within 30 days as to the 

adequacy of the submittal, and

    (2) Provide to the requester and the community, within 60 days of 

receipt of adequate information and fee, a determination letter or other 

written comment in response to the request.

    (h) For CLOMR, LOMR, and PMR requests, FEMA shall:

    (1) Notify the requester and community within 60 days as to the 

adequacy of the submittal; and

    (2) Provide to the requester and the community, within 90 days of 

receipt of adequate information and fee, a CLOMR, a LOMR, other written 

comment in response to the request, or preliminary copies of the revised 

FIRM panels, FBFM panels, and/or affected portions of the FIS report for 

review and comment.



[62 FR 5737, Feb. 6, 1997]