[Code of Federal Regulations]

[Title 47, Volume 2]

[Revised as of October 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 47CFR27.803]



[Page 319]

 

                       TITLE 47--TELECOMMUNICATION

 

                         COMMISSION (CONTINUED)

 

PART 27_MISCELLANEOUS WIRELESS COMMUNICATIONS SERVICES--Table of Contents

 

                         Subpart I_1.4 GHz Band

 

Sec. 27.803  Coordination requirements.



    (a) Licensees in the 1.4 GHz band will be issued geographic area 

licenses in accordance with the service areas listed in Sec. 27.6(d) 

and (e).

    (b) Licensees in the 1.4 GHz Service must file a separate station 

application with the Commission and obtain an individual station 

license, prior to construction or operation, of any station:

    (1) That requires submission of an Environmental Assessment under 

part 1, Sec. 1.1307 of this chapter;

    (2) That requires international coordination;

    (3) That operates in areas listed in part 1, Sec. 1.924 of this 

chapter; or

    (4) That requires approval of the Frequency Advisory Subcommittee 

(FAS) of the Interdepartment Radio Advisory Committee (IRAC). Stations 

that require FAS approval are as follows:

    (i) Licensees in the 1390-1392 MHz and 1392-1395 MHz band must 

receive FAS approval prior to operation of fixed sites or mobile units 

within the NTIA recommended protection radii of the Government sites 

listed in footnote US351 of Sec. 2.106 of this chapter.

    (ii) Licensees in the 1432-1435 MHz band must receive FAS approval, 

prior to operation of fixed sites or mobile units within the NTIA 

recommended protection radii of the Government sites listed in footnote 

US361 of Sec. 2.106 of this chapter.

    (c) Prior to construction of a station, a licensee in the 1.4 GHz 

Band must register with the Commission any station antenna structure for 

which notification to the Federal Aviation Administration is required by 

part 17 of this chapter.

    (d) It is the licensee's responsibility to determine whether an 

individual station needs referral to the Commission.

    (e) The application required in paragraph (b) of this chapter must 

be filed on the Universal Licensing System.



[67 FR 41855, June 20, 2002, as amended at 69 FR 17958, Apr. 6, 2004]