                     Subpart 11.5_Liquidated Damages

 

Sec. 11.502  Procedures.



    (a) Include the applicable liquidated damages clause and liquidated 

damages rates in solicitations when the contract will contain liquidated 

damages provisions.

    (b) Construction contracts with liquidated damages provisions must 

describe the rate(s) of liquidated damages assessed per day of delay. 

The rate(s) should include the estimated daily cost of Government 

inspection and superintendence. The rate(s) should also include an 

amount for other expected expenses associated with delayed completion 

such as--

    (1) Renting substitute property; or

    (2) Paying additional allowance for living quarters.