[Code of Federal Regulations]

[Title 48, Volume 1]

[Revised as of October 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 48CFR11.503]



[Page 190]

 

            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM

 

                CHAPTER 1--FEDERAL ACQUISITION REGULATION

 

PART 11_DESCRIBING AGENCY NEEDS--Table of Contents

 

                     Subpart 11.5_Liquidated Damages

 

Sec. 11.503  Contract clauses.



    (a) Use the clause at 52.211-11, Liquidated Damages--Supplies, 

Services, or Research and Development, in fixed-price solicitations and 

contracts for supplies, services, or research and development when the 

contracting officer determines that liquidated damages are appropriate 

(see 11.501(a)).

    (b) Use the clause at 52.211-12, Liquidated Damages--Construction, 

in solicitations and contracts for construction, other than cost-plus-

fixed-fee, when the contracting officer determines that liquidated 

damages are appropriate (see 11.501(a)). If the contract specifies more 

than one completion date for separate parts or stages of the work, 

revise paragraph (a) of the clause to state the amount of liquidated 

damages for delay of each separate part or stage of the work.

    (c) Use the clause at 52.211-13, Time Extensions, in solicitations 

and contracts for construction that use the clause at 52.211-12, 

Liquidated Damages--Construction, when that clause has been revised as 

provided in paragraph (b) of this section.