[Code of Federal Regulations]
[Title 48, Volume 6]
[Revised as of October 1, 2005]
From the U.S. Government Printing Office via GPO Access
[CITE: 48CFR1515.305-72]

[Page 26]
 
            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM
 
               CHAPTER 15--ENVIRONMENTAL PROTECTION AGENCY
 
PART 1515_CONTRACTING BY NEGOTIATION--Table of Contents
 
                     Subpart 1515.3_Source Selection
 
Sec. 1515.305-72  Release of cost information.

    (a) In accordance with FAR 15.305(a)(4), the contracting officer may 
release the cost/price proposals to those members of the evaluation team 
who are evaluating proposals at his/her discretion.
    (b) These individuals would then use this information to perform a 
cost realism analysis as described in FAR 15.404-1(d). Any 
inconsistencies between the proposals and the solicitation requirements 
and/or any inconsistencies between the cost/price and other than cost/
price proposals should be identified.