Sec. 33.000  Scope of part.









Sec.

33.000 Scope of part.



                          Subpart 33.1_Protests



33.101 Definitions.

33.102 General.

33.103 Protests to the agency.



[[Page 709]]



33.104 Protests to GAO.

33.105 [Reserved]

33.106 Solicitation provision and contract clause.



                    Subpart 33.2_Disputes and Appeals



33.201 Definitions.

33.202 Contract Disputes Act of 1978.

33.203 Applicability.

33.204 Policy.

33.205 Relationship of the Act to Pub. L. 85-804.

33.206 Initiation of a claim.

33.207 Contractor certification.

33.208 Interest on claims.

33.209 Suspected fraudulent claims.

33.210 Contracting officer's authority.

33.211 Contracting officer's decision.

33.212 Contracting officer's duties upon appeal.

33.213 Obligation to continue performance.

33.214 Alternative dispute resolution (ADR).

33.215 Contract clauses.



    Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42 U.S.C. 

2473(c).





    This part prescribes policies and procedures for filing protests and 

for processing contract disputes and appeals.



[50 FR 2270, Jan. 15, 1985]