Sec. 36.302  Scope of work.



    The agency shall develop, either in-house or by contract, a scope of 

work that defines the project and states the Government's requirements. 

The scope of work may include criteria and preliminary design, budget 

parameters, and schedule or delivery requirements. If the agency 

contracts for development of the scope of work, the procedures in 

subpart 36.6 shall be used.