Sec. 36.303  Procedures.



    One solicitation may be issued covering both phases, or two 

solicitations may be issued in sequence. Proposals will be evaluated in 

Phase One to determine which offerors will submit proposals for Phase 

Two. One contract will be awarded using competitive negotiation.