Sec. 36.515  Schedules for construction contracts.



    The contracting officer may insert the clause at 52.236-15, 

Schedules for Construction Contracts, in solicitations and contracts 

when a fixed-price construction contract is contemplated, the contract 

amount is expected to exceed the simplified acquisition threshold, and 

the period of actual work performance exceeds 60 days. This clause may 

also be inserted in such solicitations and contracts when work 

performance is expected to last less than 60 days and an unusual 

situation exists that warrants imposition of the requirements. This 

clause should not be used in the same contract with clauses covering 

other management approaches for ensuring that a contractor makes 

adequate progress.