[Code of Federal Regulations]

[Title 48, Volume 1]

[Revised as of October 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 48CFR43]



[Page 820-821]

 

            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM

 

                CHAPTER 1--FEDERAL ACQUISITION REGULATION

 

PART 43_CONTRACT MODIFICATIONS--Table of Contents

 

                       Subpart 43.2_Change Orders

 

43.205  Contract clauses.



    (a)(1) The contracting officer shall insert the clause at 52.243-1, 

Changes--Fixed-Price, in solicitations and contracts when a fixed-price 

contract for supplies is contemplated.

    (2) If the requirement is for services, other than architect-

engineer or other professional services, and no supplies are to be 

furnished, the contracting officer shall use the clause with its 

Alternate I.

    (3) If the requirement is for services (other than architect-

engineer services, transportation, or research and development) and 

supplies are to be furnished, the contracting officer shall use the 

clause with its Alternate II.

    (4) If the requirement is for architect-engineer or other 

professional services, the contracting officer shall use the clause with 

its Alternate III.

    (5) If the requirement is for transportation services, the 

contracting officer shall use the clause with its Alternate IV.

    (6) If it is desired to include the clause in solicitations and 

contracts when a research and development contract is contemplated, the 

contracting officer shall use the clause with its Alternate V.

    (b)(1) The contracting officer shall insert the clause at 52.243-2, 

Changes--Cost-Reimbursement, in solicitations and contracts when a cost-

reimbursement contract for supplies is contemplated.

    (2) If the requirement is for services and no supplies are to be 

furnished, the contracting officer shall use the clause with its 

Alternate I.

    (3) If the requirement is for services and supplies are to be 

furnished, the contracting officer shall use the clause with its 

Alternate II.

    (4) If the requirement is for construction, the contracting officer 

shall use the clause with its Alternate III.

    (5) If a facilities contract is contemplated, the contracting 

officer shall use the clause with its Alternate IV.

    (6) If it is desired to include the clause in solicitations and 

contracts when a research and development contract is contemplated, the 

contracting officer shall use the clause with its Alternate V.

    (c) Insert the clause at 52.243-3, Changes--Time-and-Materials or 

Labor-Hours, in solicitations and contracts when a time-and-materials or 

labor-hour contract is contemplated. The contracting officer may vary 

the 30-day period in paragraph (c) of the clause according to agency 

procedures.

    (d) The contracting officer shall insert the clause at 52.243-4, 

Changes, in solicitations and contracts for (1) dismantling, demolition, 

or removal of improvements; and (2) construction, when a fixed-price 

contract is contemplated and the contract amount is expected to exceed 

the simplified acquisition threshold.

    (e) The contracting officer shall insert the clause at 52.243-5, 

Changes and Changed Conditions, in solicitations and contracts for 

construction, when the contract amount is not expected to exceed the 

simplified acquisition threshold.

    (f) The contracting officer may insert a clause, substantially the 

same as the clause at 52.243-6, Change Order Accounting, in 

solicitations and contracts for supply and research and development 

contracts of significant technical complexity, if numerous changes are



[[Page 821]]



anticipated. The clause may be included in solicitations and contracts 

for construction if deemed appropriate by the contracting officer.



[48 FR 42386, Sept. 19, 1983, as amended at 56 FR 15154, Apr. 15, 1991; 

60 FR 34760, July 3, 1995; 61 FR 39190, July 26, 1996; 65 FR 46072, July 

26, 2000]