[Code of Federal Regulations]

[Title 48, Volume 1]

[Revised as of October 1, 2005]

From the U.S. Government Printing Office via GPO Access

[CITE: 48CFR44]



[Page 822-823]

 

            TITLE 48--FEDERAL ACQUISITION REGULATIONS SYSTEM

 

                CHAPTER 1--FEDERAL ACQUISITION REGULATION

 

PART 44_SUBCONTRACTING POLICIES AND PROCEDURES--Table of Contents

 

                  Subpart 44.2_Consent to Subcontracts

 

44.201-2  Advance notification requirements.



    Under cost-reimbursement contracts, the contractor is required by 

statute to notify the contracting officer as follows:

    (a) For the Department of Defense, the Coast Guard, and the National 

Aeronautics and Space Administration, unless the contractor maintains an 

approved purchasing system, 10 U.S.C. 2306 requires notification before 

the award of any cost-plus-fixed-fee subcontract, or any fixed-price 

subcontract that exceeds the greater of the simplified acquisition 

threshold or 5 percent of the total estimated cost of the contract.



[[Page 823]]



    (b) For civilian agencies other than the Coast Guard and the 

National Aeronautics and Space Administration, even if the contractor 

has an approved purchasing system, 41 U.S.C. 254(b) requires 

notification before the award of any cost-plus-fixed-fee subcontract, or 

any fixed-price subcontract that exceeds either the simplified 

acquisition threshold or 5 percent of the total estimated cost of the 

contract.



[70 FR 11762, Mar. 9, 2005