46.707  Pricing aspects of fixed-price incentive contract warranties.



    If a fixed-price incentive contract contains a warranty (see 

46.708), the estimated cost of the warranty to the contractor should be 

considered in establishing the incentive target price



[[Page 875]]



and the ceiling price of the contract. All costs incurred, or estimated 

to be incurred, by the contractor in complying with the warranty shall 

be considered when establishing the total final price. Contractor 

compliance with the warranty after the establishment of the total final 