PART 49_TERMINATION OF CONTRACTS--Table of Contents

 

                     Subpart 49.1_General Principles

 

49.114  Unsettled contract changes.



    (a) Before settlement of a completely terminated contract, the TCO 

shall obtain from the contracting office a list of all related unsettled 

contract changes. The TCO shall settle, as part of final settlement, all 

unsettled contract changes after obtaining the recommendations of the 

contracting office concerning the changes.

    (b) When the contract has been partially terminated, any outstanding 

unsettled contract changes will usually be handled by the contracting 

officer. However, the contracting officer may delegate this function to 

the TCO.